NHSRCL finishes 75 km pier work of MAHSR
RAILWAYS & METRO RAIL

NHSRCL finishes 75 km pier work of MAHSR

National High-Speed Rail Corporation (NHSRCL) has completed the 75 km pier work of an under-construction high-speed rail line connecting India’s economic hub Mumbai with the city of Ahmedabad. Mumbai-Ahmedabad High-Speed Rail Corridor (MAHSR) will be India’s first high-speed rail line. The construction of this rail project is expected to be completed by December 2023.

In 2013, a memorandum of understanding (MoU) was signed between the Ministry of Railways and the Société Nationale des Chemins de Fer Français (SNCF), the French national railways, for technical cooperation in the field of railways. Both agreed to carry out jointly an “operations and development” feasibility project on the Mumbai-Ahmedabad high-speed rail corridor.

Moreover, due to delays in acquiring land in Maharashtra, a completion date for the whole corridor is uncertain, though the 352km stretch through Gujarat may open in 2027. A stretch of 50 km (31 mi), from Surat to Bilimora, is expected to be completed by 2026.

Also read:
M G Contractors emerges lowest bidder for five bridges of MAHSR


National High-Speed Rail Corporation (NHSRCL) has completed the 75 km pier work of an under-construction high-speed rail line connecting India’s economic hub Mumbai with the city of Ahmedabad. Mumbai-Ahmedabad High-Speed Rail Corridor (MAHSR) will be India’s first high-speed rail line. The construction of this rail project is expected to be completed by December 2023. In 2013, a memorandum of understanding (MoU) was signed between the Ministry of Railways and the Société Nationale des Chemins de Fer Français (SNCF), the French national railways, for technical cooperation in the field of railways. Both agreed to carry out jointly an “operations and development” feasibility project on the Mumbai-Ahmedabad high-speed rail corridor. Moreover, due to delays in acquiring land in Maharashtra, a completion date for the whole corridor is uncertain, though the 352km stretch through Gujarat may open in 2027. A stretch of 50 km (31 mi), from Surat to Bilimora, is expected to be completed by 2026. Also read: M G Contractors emerges lowest bidder for five bridges of MAHSR

Next Story
Infrastructure Urban

Titan Intech Strengthens UltraLED Push With Global LED Veteran

Titan Intech has announced the induction of global LED industry veteran Su Piow Ko to its Board of Directors, marking a strategic step in strengthening its UltraLED Displays roadmap and building globally competitive LED display solutions from India.The appointment aligns with Titan Intech’s ambition to position India as a hub for advanced, high-quality LED display manufacturing. With an increased focus on UltraLED Displays, the company aims to enhance technical governance, raise manufacturing standards and expand its presence across global markets.Su Piow Ko brings over three decades of inte..

Next Story
Infrastructure Urban

Dun & Bradstreet Flags New Growth Engines in India 2026 Outlook

Dun & Bradstreet has released its India 2026: D&B’s Perspective report, projecting a stable macroeconomic environment underpinned by fresh opportunities for productivity-led and inclusive growth. The report outlines how India’s next growth phase will be driven by digitised logistics, trusted data ecosystems, clean energy and rising city vitality.According to the outlook, India’s GDP growth is expected to reach around 6.6 per cent by FY2027, supported by resilient consumer demand and sustained public investment. Manufacturing is seen entering a new phase, moving beyond scale towar..

Next Story
Building Material

Sources Unlimited Introduces Vitamine Pendant Lamp by Melogranoblu

Sources Unlimited has launched the Vitamine Pendant Lamp by Melogranoblu in India, expanding its portfolio of curated international luxury lighting solutions. Designed and crafted in Italy, the Vitamine pendant reflects contemporary glass artistry, combining hand-blown craftsmanship with refined aesthetics and atmospheric illumination.The Vitamine Pendant Lamp is sculpted in hand-blown glass and is available in frosted, silver and black metallised finishes. Each finish offers a distinct visual identity while maintaining a cohesive and sophisticated design language. The lamp’s softly contoure..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Advertisement

Open In App