Oscillation trials for Navi Mumbai metro begins
RAILWAYS & METRO RAIL

Oscillation trials for Navi Mumbai metro begins

The Indian Railways' Research Design and Standard Organisation (RDSO) started oscillation trials for a section of the metro rail system in Navi Mumbai on Saturday to ensure the system's safety and quality ahead of its planned launch later this year.

The City and Industrial Development Corporation (CIDCO) is constructing the four elevated corridors for the Navi Mumbai Metro project, intending to launch public service soon after the oscillation trials are completed.

These oscillation tests are considered a crucial step in the metro service commissioning process. Before declaring the network open to passenger service, the Indian Railways' research wing will test the braking system, the tracks, and the safety of the metro cars at various times.

RDSO will conduct oscillation trials for Metro Line 1 from Pendhar Station to Central Park Station starting August 28th, according to a tweet from CIDCO on Tuesday. CIDCO will build elevated corridors for the Navi Mumbai Metro that will connect several nodes and improve public transportation efficiency.

The Navi Mumbai Metro is a rapid transit system in the Indian city of Navi Mumbai, Maharashtra, that is currently under construction. The City and Industrial Development Corporation is in charge of the Navi Mumbai Metro's planning and construction (CIDCO). The system will be made up of three rail lines that will span a total distance of 106.4 km. The project's foundation stone was laid on May 1, 2011, and the metro's first line was scheduled to open in 2020, despite construction delays.

Owing to the ongoing Covid-19 pandemic, which has resulted in lockdowns, curfews, and a labour shortage, the completion date for the first line (Line 1) of the Navi Mumbai Metro has been pushed back to 2022.

Image Source


Also readNavi Mumbai Metro Line 1: Oscillation trials to begin this week

The Indian Railways' Research Design and Standard Organisation (RDSO) started oscillation trials for a section of the metro rail system in Navi Mumbai on Saturday to ensure the system's safety and quality ahead of its planned launch later this year.The City and Industrial Development Corporation (CIDCO) is constructing the four elevated corridors for the Navi Mumbai Metro project, intending to launch public service soon after the oscillation trials are completed.These oscillation tests are considered a crucial step in the metro service commissioning process. Before declaring the network open to passenger service, the Indian Railways' research wing will test the braking system, the tracks, and the safety of the metro cars at various times.RDSO will conduct oscillation trials for Metro Line 1 from Pendhar Station to Central Park Station starting August 28th, according to a tweet from CIDCO on Tuesday. CIDCO will build elevated corridors for the Navi Mumbai Metro that will connect several nodes and improve public transportation efficiency.The Navi Mumbai Metro is a rapid transit system in the Indian city of Navi Mumbai, Maharashtra, that is currently under construction. The City and Industrial Development Corporation is in charge of the Navi Mumbai Metro's planning and construction (CIDCO). The system will be made up of three rail lines that will span a total distance of 106.4 km. The project's foundation stone was laid on May 1, 2011, and the metro's first line was scheduled to open in 2020, despite construction delays.Owing to the ongoing Covid-19 pandemic, which has resulted in lockdowns, curfews, and a labour shortage, the completion date for the first line (Line 1) of the Navi Mumbai Metro has been pushed back to 2022.Image SourceAlso read: Navi Mumbai Metro Line 1: Oscillation trials to begin this week

Next Story
Infrastructure Transport

Tripura Rail Survey Approved For Jirania–Bodhjung Link

The Ministry of Railways has approved a Final Location Survey (FLS) for a proposed new railway line between Jirania and Bodhjung Nagar in Tripura. The planned section will span 14 km and is estimated to cost around Rs 4.2 million, with the entire alignment located within West Tripura district. The approval marks a key step towards strengthening railway infrastructure and supporting industrial growth in the state. Bodhjung Nagar is Tripura’s principal industrial and commercial hub, developed mainly for resource-based industries such as rubber, bamboo and food processing. The proposed Jirania..

Next Story
Infrastructure Transport

MCF Raebareli Rolls Out Its 15,000th Passenger Coach

The Modern Coach Factory (MCF) in Raebareli, Uttar Pradesh, has reached a major production milestone with the manufacture of its 15,000th passenger coach on December 15, the Ministry of Railways said. During the current financial year 2025–26, the unit has produced a total of 1,310 coaches so far. Established in 2007 at Lalganj in Raebareli, MCF is among India’s most advanced passenger coach manufacturing facilities. Built at a cost of around Rs 31.92 billion, the factory has an installed annual capacity of 1,000 coaches and is located about 3 km from Lalganj on the Kanpur–Raebareli Roa..

Next Story
Infrastructure Transport

RVNL Wins Gandak River Rail Bridge Contract

Rail Vikas Nigam Limited (RVNL) has received a Letter of Award from North Eastern Railway for a major railway infrastructure project valued at Rs 1.65 billion. The contract relates to the construction of the substructure for a key railway bridge over the Gandak River. The bridge will be constructed between Paniyahwa and Valmikinagar stations as part of the doubling of the Gorakhpur Cantt–Valmikinagar railway section. Designed to enhance capacity and operational efficiency, the structure will comprise 14 spans of 61 metres each and will be supported by double D-type well foundations. The des..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Advertisement

Open In App