Pre-construction activities of Hyderabad airport works in full swing
RAILWAYS & METRO RAIL

Pre-construction activities of Hyderabad airport works in full swing

According to NVS Reddy, managing director of Hyderabad Airport Metro Ltd (HAML), a lot of pre-construction activities have been started in parallel processing mode and are moving along quickly to speed up the grounding of Airport Metro works.

While survey work to fine-tune the metro route and station sites was underway, the deadline for General Consultant (GC) bids to be submitted was January 20. These skilled engineering experts would be in place by early next month.

According to him, the survey work was being carried out utilizing both the Electronic Total Station with built-in programs for greater accuracy and the capture of exact coordinates and the satellite-based Differential Global Positioning System (DGPS). The survey would be finished by the end of the month and has already covered 21 kilometres up to Fort Grand underpass near Shamshabad town. The alignment would then begin to be marked with pegs.

While the DPR used a standard railway engineering method to determine the station locations, an innovative approach was now being used by taking into account the significant commercial and residential developments that have recently occurred in the Nanakramguda, Financial District, Kokapet, Narsingi, Rajendranagar, and Shamshabad areas, as well as HMDA's master plan for development of this area of the city and its outskirts.

This was in line with the goal of Chief Minister K Chandrashekhar Rao, who wanted to spread out the growth of the city to its periphery and offer inexpensive homes within a commute distance of less than 30 minutes to workplaces.

See also:
HAML gears up to expedite Hyderabad Airport Metro works
Hyderabad Airport Metro Rail extends the date for submission


According to NVS Reddy, managing director of Hyderabad Airport Metro Ltd (HAML), a lot of pre-construction activities have been started in parallel processing mode and are moving along quickly to speed up the grounding of Airport Metro works. While survey work to fine-tune the metro route and station sites was underway, the deadline for General Consultant (GC) bids to be submitted was January 20. These skilled engineering experts would be in place by early next month. According to him, the survey work was being carried out utilizing both the Electronic Total Station with built-in programs for greater accuracy and the capture of exact coordinates and the satellite-based Differential Global Positioning System (DGPS). The survey would be finished by the end of the month and has already covered 21 kilometres up to Fort Grand underpass near Shamshabad town. The alignment would then begin to be marked with pegs. While the DPR used a standard railway engineering method to determine the station locations, an innovative approach was now being used by taking into account the significant commercial and residential developments that have recently occurred in the Nanakramguda, Financial District, Kokapet, Narsingi, Rajendranagar, and Shamshabad areas, as well as HMDA's master plan for development of this area of the city and its outskirts. This was in line with the goal of Chief Minister K Chandrashekhar Rao, who wanted to spread out the growth of the city to its periphery and offer inexpensive homes within a commute distance of less than 30 minutes to workplaces. See also: HAML gears up to expedite Hyderabad Airport Metro works Hyderabad Airport Metro Rail extends the date for submission

Next Story
Infrastructure Energy

BMW Industries partners with IOCL for PNG supply at Bokaro plant

BMW Industries has entered into a strategic partnership with Indian Oil Corporation (IOCL) for the supply of Piped Natural Gas (PNG), reinforcing its commitment to adopting cleaner and more efficient energy sources for its operations.The agreement was signed at the Eastern Region Pipelines (ERPL) headquarters in Kolkata. The partnership is expected to support the company’s upcoming manufacturing facility in Bokaro by facilitating the use of natural gas as a primary energy source.According to the company, the adoption of PNG will help enhance operational efficiency while also contributing to ..

Next Story
Real Estate

Bombay Realty Secures RERA for Three ICC Tower in South Mumbai

Bombay Realty, the real estate arm of Bombay Dyeing and part of the Wadia Group, has received Real Estate Regulatory Authority (RERA) certification for Three ICC – Wing A, the latest luxury residential tower at Island City Center in Mumbai’s Dadar.The RERA registration marks a key milestone in the development timeline and reinforces the company’s focus on regulatory transparency, timely project delivery, and high construction standards.Following the success of One ICC and Two ICC, the upcoming Three ICC tower represents the next phase of the Island City Center development. The project ai..

Next Story
Infrastructure Energy

Flender launches India’s largest wind gearbox test rig in Walajabad

Flender has inaugurated a 13.5 MW wind turbine gearbox test rig at its Walajabad facility near Chennai, marking the largest installation of its kind in India. The new facility is expected to strengthen the company’s manufacturing and testing capabilities while supporting the growing demands of the wind power sector in both domestic and global markets.The test rig was inaugurated on March 5 in the presence of Andreas Evertz, Group CEO, Flender; Lars Wiegemann, Vice President Wind Gears, Flender; and Vinod Shetty, CEO, Flender India, along with key industry customers and stakeholders.The insta..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement