Pune Metro Line 3 Completion Delayed to April 2025
RAILWAYS & METRO RAIL

Pune Metro Line 3 Completion Delayed to April 2025

The 23-km Pune Metro Line 3, connecting Maan to Shivajinagar, is now expected to be completed by late next year. The Pune Metropolitan Region Development Authority (PMRDA) has announced that the integrated flyover, a crucial element of the corridor, is likely to be ready by April 2025. Initially planned for completion in November this year and later extended to December, the flyover’s construction has faced delays due to pending permissions and construction hurdles. “The ramp and deck slab construction is yet to be completed. Additionally, certain stretches still require permissions, so the 1.7-km flyover will likely be finished only by April 2025,” said a PMRDA official. The integrated flyover is critical for the operational readiness of the metro line, with officials confirming that services cannot commence without its completion. While construction along the entire metro corridor is progressing, it is expected to be finalized only by the end of 2025 Heavy traffic along the busy corridor has significantly impacted the pace of work. Delays have also stemmed from the need for multiple clearances, including right-of-way permissions and shifting of utility lines. Despite regular review meetings, these issues have slowed progress. The government had previously instructed the PMRDA concessionaire, Pune IT City Metro Rail Limited (PITCMRL), to prioritize completing the flyover from Savitribai Phule Pune University (SPPU) to E Square Junction by November this year. However, this deadline has now been extended to April 2025. The Pune Metro Line 3 project remains a significant initiative to ease urban traffic congestion, and PMRDA assures that efforts are ongoing to expedite the work despite the setbacks.

The 23-km Pune Metro Line 3, connecting Maan to Shivajinagar, is now expected to be completed by late next year. The Pune Metropolitan Region Development Authority (PMRDA) has announced that the integrated flyover, a crucial element of the corridor, is likely to be ready by April 2025. Initially planned for completion in November this year and later extended to December, the flyover’s construction has faced delays due to pending permissions and construction hurdles. “The ramp and deck slab construction is yet to be completed. Additionally, certain stretches still require permissions, so the 1.7-km flyover will likely be finished only by April 2025,” said a PMRDA official. The integrated flyover is critical for the operational readiness of the metro line, with officials confirming that services cannot commence without its completion. While construction along the entire metro corridor is progressing, it is expected to be finalized only by the end of 2025 Heavy traffic along the busy corridor has significantly impacted the pace of work. Delays have also stemmed from the need for multiple clearances, including right-of-way permissions and shifting of utility lines. Despite regular review meetings, these issues have slowed progress. The government had previously instructed the PMRDA concessionaire, Pune IT City Metro Rail Limited (PITCMRL), to prioritize completing the flyover from Savitribai Phule Pune University (SPPU) to E Square Junction by November this year. However, this deadline has now been extended to April 2025. The Pune Metro Line 3 project remains a significant initiative to ease urban traffic congestion, and PMRDA assures that efforts are ongoing to expedite the work despite the setbacks.

Next Story
Infrastructure Transport

Gurgaon-Pataudi-Rewari Highway Set for Completion by December 2025

The National Highways Authority of India (NHAI) has set a new target to complete the four-lane Gurgaon-Pataudi-Rewari highway by December 2025, following a two-year delay.Originally planned in 2018 to upgrade the two-lane state highway into a national highway, the project is estimated to cost Rs 9 billion. Construction, which began in 2021, was initially scheduled for completion in November 2023. According to NHAI, around 70 per cent of the work is already complete, with two major structures still pending: a railway overbridge at Pahari village and a two-lane unidirectional flyover on Dwarka E..

Next Story
Infrastructure Transport

UP Plans Rs 900 Million Extensions to Hindon Elevated Road

The Uttar Pradesh state bridge corporation has prepared the detailed project report and cost estimates for two proposed extensions of the 10.3-km Hindon elevated road, officials said on Thursday. The road connects Raj Nagar Extension to UP-Gate near the east Delhi border, and the project is expected to cost around Rs 900 million.The two extensions, each 400 metres long, will be added to the existing elevated road to ensure smoother traffic flow. “One of the extensions will be from near the Kanawani culvert (near Indirapuram) to the elevated road for commuters heading towards Delhi. The other..

Next Story
Infrastructure Urban

Goa Likely to Miss October Deadline for Maritime Master Plan

Goa is expected to miss the October 31 deadline for submitting its maritime and waterways master plan, which covers the state’s 105 km coastline and river network. The delay is due to the project management consultant not yet being appointed. The plan is now anticipated to be completed by December, Captain of Ports Octavio Rodrigues stated at the India Maritime Week 2025 roadshow.“We have already selected the consultant and will bring them on board within a week. Only then can we begin drafting the master plan, which is essential to secure central government funding,” Rodrigues added.A c..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Talk to us?