+
Pune Metro Line 3 Completion Delayed to April 2025
RAILWAYS & METRO RAIL

Pune Metro Line 3 Completion Delayed to April 2025

The 23-km Pune Metro Line 3, connecting Maan to Shivajinagar, is now expected to be completed by late next year. The Pune Metropolitan Region Development Authority (PMRDA) has announced that the integrated flyover, a crucial element of the corridor, is likely to be ready by April 2025. Initially planned for completion in November this year and later extended to December, the flyover’s construction has faced delays due to pending permissions and construction hurdles. “The ramp and deck slab construction is yet to be completed. Additionally, certain stretches still require permissions, so the 1.7-km flyover will likely be finished only by April 2025,” said a PMRDA official. The integrated flyover is critical for the operational readiness of the metro line, with officials confirming that services cannot commence without its completion. While construction along the entire metro corridor is progressing, it is expected to be finalized only by the end of 2025 Heavy traffic along the busy corridor has significantly impacted the pace of work. Delays have also stemmed from the need for multiple clearances, including right-of-way permissions and shifting of utility lines. Despite regular review meetings, these issues have slowed progress. The government had previously instructed the PMRDA concessionaire, Pune IT City Metro Rail Limited (PITCMRL), to prioritize completing the flyover from Savitribai Phule Pune University (SPPU) to E Square Junction by November this year. However, this deadline has now been extended to April 2025. The Pune Metro Line 3 project remains a significant initiative to ease urban traffic congestion, and PMRDA assures that efforts are ongoing to expedite the work despite the setbacks.

The 23-km Pune Metro Line 3, connecting Maan to Shivajinagar, is now expected to be completed by late next year. The Pune Metropolitan Region Development Authority (PMRDA) has announced that the integrated flyover, a crucial element of the corridor, is likely to be ready by April 2025. Initially planned for completion in November this year and later extended to December, the flyover’s construction has faced delays due to pending permissions and construction hurdles. “The ramp and deck slab construction is yet to be completed. Additionally, certain stretches still require permissions, so the 1.7-km flyover will likely be finished only by April 2025,” said a PMRDA official. The integrated flyover is critical for the operational readiness of the metro line, with officials confirming that services cannot commence without its completion. While construction along the entire metro corridor is progressing, it is expected to be finalized only by the end of 2025 Heavy traffic along the busy corridor has significantly impacted the pace of work. Delays have also stemmed from the need for multiple clearances, including right-of-way permissions and shifting of utility lines. Despite regular review meetings, these issues have slowed progress. The government had previously instructed the PMRDA concessionaire, Pune IT City Metro Rail Limited (PITCMRL), to prioritize completing the flyover from Savitribai Phule Pune University (SPPU) to E Square Junction by November this year. However, this deadline has now been extended to April 2025. The Pune Metro Line 3 project remains a significant initiative to ease urban traffic congestion, and PMRDA assures that efforts are ongoing to expedite the work despite the setbacks.

Related Stories

Gold Stories

Next Story
Infrastructure Transport

97 Per Cent Of Rongjeng-Mangsang-Adokgre Road Nears Completion

Deputy Chief Minister in-charge of public works Prestone Tynsong said in Shillong on 26 August that 97 per cent physical progress had been achieved on the ongoing Rongjeng-Mangsang-Adokgre road being constructed under the Non-Lapsable Central Pool of Resources (NLCPR). He noted the project was sanctioned in 2017 and that the stipulated time for completion had been 24 months from issue of the final work order. The deputy chief minister informed the assembly that the government had decided to include the remaining work under a World Bank project. In reply to a query from Rongjeng MLA Jim M Sangm..

Next Story
Infrastructure Transport

First TBM Starts Digging Five Point Three Kilometre Tunnel Under SGNP

The Goregaon-Mulund Link Road (GMLR) Phase three (B) project has reached a key milestone as the first tunnel boring machine (TBM) began excavation of the first of two tunnels beneath the Sanjay Gandhi National Park (SGNP). The machine, named Tulsi, started cutting a five point three kilometre bore that will link Dadasaheb Phalke Chitranagari in Goregaon East with Amar Nagar in Mulund West. Officials issued a statement noting the commencement of tunnelling work under the protected green belt. The twin tunnels are being constructed using mechanised tunnelling methods that aim to limit surface di..

Next Story
Infrastructure Transport

UP Approves Two Expressways And Rs 240 bn Infrastructure Push

The Uttar Pradesh Cabinet approved a series of infrastructure and industrial investment proposals totalling Rs 240 billion (Rs 240 bn), including two major expressway projects, a manufacturing and logistics cluster in Sultanpur and incentives for 11 industrial projects across the state. The decisions, taken at a meeting chaired by Chief Minister Yogi Adityanath, underline the state government’s focus on expanding road connectivity around emerging industrial hubs while attracting manufacturing investment to districts beyond major urban centres. The approvals cover both greenfield expressway c..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

SPECIAL OFFER
QR Code