Pune Metro Line 3 Completion Delayed to April 2025
RAILWAYS & METRO RAIL

Pune Metro Line 3 Completion Delayed to April 2025

The 23-km Pune Metro Line 3, connecting Maan to Shivajinagar, is now expected to be completed by late next year. The Pune Metropolitan Region Development Authority (PMRDA) has announced that the integrated flyover, a crucial element of the corridor, is likely to be ready by April 2025. Initially planned for completion in November this year and later extended to December, the flyover’s construction has faced delays due to pending permissions and construction hurdles. “The ramp and deck slab construction is yet to be completed. Additionally, certain stretches still require permissions, so the 1.7-km flyover will likely be finished only by April 2025,” said a PMRDA official. The integrated flyover is critical for the operational readiness of the metro line, with officials confirming that services cannot commence without its completion. While construction along the entire metro corridor is progressing, it is expected to be finalized only by the end of 2025 Heavy traffic along the busy corridor has significantly impacted the pace of work. Delays have also stemmed from the need for multiple clearances, including right-of-way permissions and shifting of utility lines. Despite regular review meetings, these issues have slowed progress. The government had previously instructed the PMRDA concessionaire, Pune IT City Metro Rail Limited (PITCMRL), to prioritize completing the flyover from Savitribai Phule Pune University (SPPU) to E Square Junction by November this year. However, this deadline has now been extended to April 2025. The Pune Metro Line 3 project remains a significant initiative to ease urban traffic congestion, and PMRDA assures that efforts are ongoing to expedite the work despite the setbacks.

The 23-km Pune Metro Line 3, connecting Maan to Shivajinagar, is now expected to be completed by late next year. The Pune Metropolitan Region Development Authority (PMRDA) has announced that the integrated flyover, a crucial element of the corridor, is likely to be ready by April 2025. Initially planned for completion in November this year and later extended to December, the flyover’s construction has faced delays due to pending permissions and construction hurdles. “The ramp and deck slab construction is yet to be completed. Additionally, certain stretches still require permissions, so the 1.7-km flyover will likely be finished only by April 2025,” said a PMRDA official. The integrated flyover is critical for the operational readiness of the metro line, with officials confirming that services cannot commence without its completion. While construction along the entire metro corridor is progressing, it is expected to be finalized only by the end of 2025 Heavy traffic along the busy corridor has significantly impacted the pace of work. Delays have also stemmed from the need for multiple clearances, including right-of-way permissions and shifting of utility lines. Despite regular review meetings, these issues have slowed progress. The government had previously instructed the PMRDA concessionaire, Pune IT City Metro Rail Limited (PITCMRL), to prioritize completing the flyover from Savitribai Phule Pune University (SPPU) to E Square Junction by November this year. However, this deadline has now been extended to April 2025. The Pune Metro Line 3 project remains a significant initiative to ease urban traffic congestion, and PMRDA assures that efforts are ongoing to expedite the work despite the setbacks.

Next Story
Real Estate

Integrated Waterproofing Strategies

Waterproofing buildings used to be an annual pre-monsoon affair but the evolution of real-estate development has changed that approach. In new developments, developers are weaving waterproofing solutions into both the design and construction phases, an approach that Nikhil Madan, Managing Director, Mahima Group, says, “is all about ensuring lasting durability [of the building] and keeping lifecycle risks including water seepage and extensive maintenance to a minimum.”Watertight by designAluminium formwork systems aren’t commonly thought of as a waterproofing tool but at the Mahima Group,..

Next Story
Infrastructure Urban

GROHE Showcases Water-Led Design At Milan

GROHE unveiled its GROHE SPA Aqua Sanctuary at Milan Design Week 2026, transforming Piccolo Teatro Studio Melato into an immersive showcase of water, design and wellbeing. Built on the philosophy of ‘Wellbeing Through Water’, the installation reimagined bathrooms as holistic spaces for relaxation, rejuvenation and self-care.The Aqua Sanctuary was presented through three interconnected sanctums. The first showcased the 3D-printed GROHE SPA AquaTree shower and faucet, highlighting bespoke innovation and biophilic design. The second featured the Atrio Private Collection and GROHE SPA x Buster..

Next Story
Infrastructure Transport

Rahee Group Expands Rail Manufacturing Capacity

Rahee Group has outlined a multi-year investment roadmap to expand its operational footprint and strengthen manufacturing capabilities for India’s growing railway and urban transit sector. The Group is expanding in Odisha with a new Track Component Casting Unit, for which the groundbreaking ceremony was held on 8 April 2026 in the presence of Odisha Chief Minister Mohan Charan Majhi.The Group’s flagship EPC arm, Rahee Infratech Ltd, continues to focus on complex rail infrastructure projects, including track systems, bridges, viaducts and ballastless infrastructure. Its wholly owned subsidi..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement