Railways capex improves after months of slide
RAILWAYS & METRO RAIL

Railways capex improves after months of slide

Capital expenditure by the Indian Railways, which deteriorated significantly back in the period from April through July this year has since shown a quick recovery. According to official data, around Rs 94,000 crore—or 58%—of the FY21 target was spent until end November.

During the same period in 2019, the Railways’ capital expenditure stood at Rs 96,000 crore. However, the nationwide lockdown has resulted in the railways losing out pre-monsoon momentum in project execution.

A Railways official said a lot of time had been lost in the March-May phase, which is the most proactive period for various activities. Projects have been disrupted in many parts of the country this year due to heavier rainfall and flood-like situations.

The construction targets for this include 3,750 km of new lines, gauge conversions, doubling or tripling of different railways lines and electrification of 6,000 km of several rail routes.

Although the work on projects has picked up in the last few months, the Railways are witnessing another problem at hand mainly to accelerate its capex. The transporter includes projects worth Rs 1.5 lakh crore that are stuck because of instructions directed by the Railway Board to all Zonal officers. It has directed all officers to rationalise expenditure. Additionally, the Finance Ministry has directed to halt all infrastructure projects that were sanctioned in the current financial year and the ones approved in FY20 whose work has been stagnant.

The projects that have been impacted are cut across states and includes Rs 8,500 crore of new projects’ approved in FY21. Currently, the Railways are undertaking work on projects with an investment of Rs 9.5 lakh crore that includes those carried over from the previous years.

As per sources, the projects on hold would be valid only till the end of FY21. However, there is uncertainty whether the restrictions would be extended. Clarity is expected in the Budget 2021-22.

The Finance Ministry’s rationale was to mobilise the capital for projects by relying on budgetary funds that needed to be controlled due to the tight fiscal constraints.

The Railway Board’s communique has confirmed that new works that are included in the Pink Book 2020-21 would be kept in abeyance. Those works that are likely to impact the running of trains will be considered essential and will be sanctioned. The essentiality of such projects will be examined by the concerned members.

Additionally, the work which has been approved till 2019-20 but has not made significant physical progress will be frozen until further order. It excludes those that are essentially required for the safe running of trains. Moreover, the unutilised provision of different umbrella works of both 2018-19 and 2019-20 may be suspended.

Capital expenditure by the Indian Railways, which deteriorated significantly back in the period from April through July this year has since shown a quick recovery. According to official data, around Rs 94,000 crore—or 58%—of the FY21 target was spent until end November.During the same period in 2019, the Railways’ capital expenditure stood at Rs 96,000 crore. However, the nationwide lockdown has resulted in the railways losing out pre-monsoon momentum in project execution. A Railways official said a lot of time had been lost in the March-May phase, which is the most proactive period for various activities. Projects have been disrupted in many parts of the country this year due to heavier rainfall and flood-like situations. The construction targets for this include 3,750 km of new lines, gauge conversions, doubling or tripling of different railways lines and electrification of 6,000 km of several rail routes. Although the work on projects has picked up in the last few months, the Railways are witnessing another problem at hand mainly to accelerate its capex. The transporter includes projects worth Rs 1.5 lakh crore that are stuck because of instructions directed by the Railway Board to all Zonal officers. It has directed all officers to rationalise expenditure. Additionally, the Finance Ministry has directed to halt all infrastructure projects that were sanctioned in the current financial year and the ones approved in FY20 whose work has been stagnant. The projects that have been impacted are cut across states and includes Rs 8,500 crore of new projects’ approved in FY21. Currently, the Railways are undertaking work on projects with an investment of Rs 9.5 lakh crore that includes those carried over from the previous years. As per sources, the projects on hold would be valid only till the end of FY21. However, there is uncertainty whether the restrictions would be extended. Clarity is expected in the Budget 2021-22. The Finance Ministry’s rationale was to mobilise the capital for projects by relying on budgetary funds that needed to be controlled due to the tight fiscal constraints. The Railway Board’s communique has confirmed that new works that are included in the Pink Book 2020-21 would be kept in abeyance. Those works that are likely to impact the running of trains will be considered essential and will be sanctioned. The essentiality of such projects will be examined by the concerned members. Additionally, the work which has been approved till 2019-20 but has not made significant physical progress will be frozen until further order. It excludes those that are essentially required for the safe running of trains. Moreover, the unutilised provision of different umbrella works of both 2018-19 and 2019-20 may be suspended.

Next Story
Infrastructure Energy

South West Pinnacle Wins Rs 30 Cr Oman Mining Contract

South West Pinnacle Exploration Ltd has secured a Rs 30 crore contract from Minerals Development Oman (MDO) for mining exploration in concession areas 12B and 13.The two-year project will be carried out via Alara Resources LLC, a JV in Oman. MDO, backed by Oman’s investment authorities, focuses on monetising mineral wealth.The contract covers copper, gold, and chromite and highlights South West Pinnacle’s growing footprint in international exploration and mining services. ..

Next Story
Equipment

Godrej GEG Boosts Intralogistics with AI and Green Tech

Godrej Enterprises Group (GEG) is revolutionising warehouse and factory logistics through its Material Handling Equipment and Storage Solutions arms by integrating AI, IoT, and automation.With 20–25% market share and 85% local sourcing, GEG champions Atmanirbhar Bharat and sustainability. The Chennai plant, a green manufacturing leader, uses RoHS-compliant materials and has slashed energy consumption by 60%.GEG serves e-commerce, FMCG, retail, and cold chains with high-performance racking and electric forklifts. Upcoming IoT-enabled forklifts and telematics solutions aim to improve speed, sa..

Next Story
Infrastructure Urban

Amit Shah Inaugurates Key Projects Across Gujarat

Union Home Minister Amit Shah inaugurated and laid the foundation stone for various projects in Gujarat’s Panchmahal district and Ahmedabad.In Godhra, he inaugurated the Center of Excellence building, sports complex, reservoir, and Miyawaki plantation. In Ahmedabad, he unveiled a new cooperative complex in Adaroda village and a primary school in Juwal.These projects, under the Model Co-op Village scheme, aim to boost education, sustainability, and rural development across the state. ..

Advertisement

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Advertisement

Talk to us?