SCR electrifies stretch between Khanapur-Latur Road rail stations
RAILWAYS & METRO RAIL

SCR electrifies stretch between Khanapur-Latur Road rail stations

South Central Railways (SCR) has completed the electrification of a huge stretch of 98.7 route km between Khanapur-Latur Road stations, covering both Karnataka and Maharashtra states in one go. This section is completed as part of the Vikarabad-Parli Vaijnath electrification project.

With this, a continuous stretch of 204 route km has now been electrified between Vikarabad-Latur Road. The stretch between Khanapur-Latur Road for a distance of 98.7 route km is part of Vikarabad-Parli Vaijnath electrification project, which was sanctioned in 2018-19 at an estimated cost of Rs 262 crore for a distance of 269 route km.

While the stretch between Vikarabad-Kohir Deccan (45 km) was commissioned in March 2021, the stretch between Kohir Deccan-Khanapur (60.4 km) was completed in January 2021. Of the electrification of the present stretch of 98.7 route km, 46.8 km is in Maharashtra and 51.9 km is in Karnataka.

Trains originating and terminating from Latur Road and Bidar towards the southern direction can now run with electric traction, which will help in seamless transportation.

Work in the remaining stretch i.e., Latur Road - Parli Vaijnath is progressing at a fast pace. Electrification of these railway lines will strengthen rail infrastructure in Telangana, Karnataka and Maharashtra.

South Central Railways (SCR) has completed the electrification of a huge stretch of 98.7 route km between Khanapur-Latur Road stations, covering both Karnataka and Maharashtra states in one go. This section is completed as part of the Vikarabad-Parli Vaijnath electrification project. With this, a continuous stretch of 204 route km has now been electrified between Vikarabad-Latur Road. The stretch between Khanapur-Latur Road for a distance of 98.7 route km is part of Vikarabad-Parli Vaijnath electrification project, which was sanctioned in 2018-19 at an estimated cost of Rs 262 crore for a distance of 269 route km. While the stretch between Vikarabad-Kohir Deccan (45 km) was commissioned in March 2021, the stretch between Kohir Deccan-Khanapur (60.4 km) was completed in January 2021. Of the electrification of the present stretch of 98.7 route km, 46.8 km is in Maharashtra and 51.9 km is in Karnataka. Trains originating and terminating from Latur Road and Bidar towards the southern direction can now run with electric traction, which will help in seamless transportation. Work in the remaining stretch i.e., Latur Road - Parli Vaijnath is progressing at a fast pace. Electrification of these railway lines will strengthen rail infrastructure in Telangana, Karnataka and Maharashtra.

Next Story
Infrastructure Urban

Naidu Seeks Rs 563 Crore For AP Sports Infrastructure

Andhra Pradesh Chief Minister N Chandrababu Naidu has sought Rs 563 crore from the Centre to boost sports infrastructure in the state, including Rs 538 crore for stadium development and Rs 25 crore to host the Khelo India Martial Arts Games 2025. Naidu made the request during a meeting with Union Youth Services and Sports Minister Mansukh Mandaviya in New Delhi on Wednesday.The CM urged early completion of Khelo India infrastructure projects in Tirupati, Rajahmundry, Kakinada, and Narasaraopeta, and called for an international-standard badminton training centre and a national aquatic sports hu..

Next Story
Infrastructure Transport

Tough Bidding Norms Slow NHAI Road Project Awards

Stringent bidding rules imposed by the Ministry of Road Transport & Highways (MoRTH) have led to a slowdown in project awards by the National Highways Authority of India (NHAI), despite a robust Rs 3.5 trillion pipeline. According to an HDFC Securities report, the shift to more cautious developer models now favours firms with strong balance sheets, as tighter qualification norms limit aggressive bidders.The revised norms mandate additional performance security, targeting the exclusion of players that previously submitted low bids—often 25 to 40 per cent below NHAI cost estimates—raisin..

Next Story
Infrastructure Transport

Mumbai Gets Coastal Nod for Next Promenade Phase

As Mumbai prepares to open two major sections of its expansive seafront promenade this week, the city’s civic authority has secured a key coastal clearance to advance further construction. The Maharashtra Coastal Zone Management Authority (MCZMA) has approved the commencement of work on the segment between Haji Ali and Baroda Palace, with tendering expected soon after project cost assessments.The promenade, stretching 7.5 km in length and 20 metres wide, is being designed as a flagship open space for walkers, joggers, and cyclists. Two critical stretches—2.75 km from Tata Garden to Haji Al..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Talk to us?