Status of Mumbai-Ahmedabad bullet train
RAILWAYS & METRO RAIL

Status of Mumbai-Ahmedabad bullet train

The only High-Speed Rail project in the nation that has been approved is the Mumbai-Ahmedabad route. The execution of the project is being helped by the Japanese government. According to the railway ministry, more than a quarter of the whole project is finished.

According to the railways minister, 26% of the work on the Mumbai-Ahmedabad bullet train project has been completed. The project is expected to be delayed by four years from its initial date of December 2023.

According to the ministry, as of February 28, 2023, there has been a total physical advancement of 26.33 percent. It said that 13.72 percent of the whole work has been finished by Maharashtra. Gujarat, on the other hand, had completed more than 52% of the civil work and currently has a total completion percentage of 36.33%.

The Railways Ministry reports that pier work up to 155.48 km and piling work up to 257.06 km have both been finished. Also, it mentioned the launch of 37.64 km of girders to support the building.

Around 8000 trees have been moved for the project so far, and 83,600 saplings have been planted.

The only High-Speed Rail project in the nation that has been approved is the Mumbai-Ahmedabad route. The execution of the project is being helped by the Japanese government. According to the railway ministry, more than a quarter of the whole project is finished. According to the railways minister, 26% of the work on the Mumbai-Ahmedabad bullet train project has been completed. The project is expected to be delayed by four years from its initial date of December 2023. According to the ministry, as of February 28, 2023, there has been a total physical advancement of 26.33 percent. It said that 13.72 percent of the whole work has been finished by Maharashtra. Gujarat, on the other hand, had completed more than 52% of the civil work and currently has a total completion percentage of 36.33%. The Railways Ministry reports that pier work up to 155.48 km and piling work up to 257.06 km have both been finished. Also, it mentioned the launch of 37.64 km of girders to support the building. Around 8000 trees have been moved for the project so far, and 83,600 saplings have been planted.

Next Story
Real Estate

Bent Collective Unveils Sculptural Papillon Sofa

Bent Collective has introduced the Papillon Sofa, a sculptural seating piece that combines artistic design with everyday comfort. Defined by a fluid silhouette, the sofa features a gently curved backrest, asymmetrical form, rounded seating, a single rolled arm and sleek legs, creating a soft yet expressive presence for contemporary interiors. Upholstered in a soothing blue tone, the Papillon Sofa is designed to bring a sense of calm, movement and visual lightness to living spaces. Its organic form moves away from rigid lines, reflecting the brand’s focus on furniture that is both i..

Next Story
Infrastructure Urban

MHIEC Completes Relay Centre Project In Nagasaki

 Mitsubishi Heavy Industries Environmental & Chemical Engineering Co., Ltd. (MHIEC) has completed construction of the Nanbu Relay Center in Minamishimabara City for the Ken’ou-Kennan Clean Authority in Nagasaki Prefecture. The project includes the development of the new facility and the operation of three relay centres, including the existing Tobu and Seibu sites, under a contract awarded in 2024. The initiative is aimed at enabling the efficient transfer of combustible waste from multiple municipalities to the Ken’ou-Kennan Clean Center in Isahaya City, which is scheduled to co..

Next Story
Infrastructure Urban

Kala Ghoda Boutique Redefines Compact Retail Design

Located in Kala Ghoda, Noir Éclat, an 80 sq ft jewellery boutique by Mint Leaf Design, showcases how compact retail spaces can deliver a high-impact experience. Designed as a ‘jewel box’, the boutique blends Parisian-inspired aesthetics with a monochrome palette of black and white, highlighted by fuchsia accents that add a distinctive visual identity. The design leverages vertical space to overcome size constraints, featuring sculptural wall-mounted busts arranged in grids that transform product displays into artistic installations. Carefully planned lighting enhances depth and creates a..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement