Status of Mumbai-Ahmedabad bullet train
RAILWAYS & METRO RAIL

Status of Mumbai-Ahmedabad bullet train

The only High-Speed Rail project in the nation that has been approved is the Mumbai-Ahmedabad route. The execution of the project is being helped by the Japanese government. According to the railway ministry, more than a quarter of the whole project is finished.

According to the railways minister, 26% of the work on the Mumbai-Ahmedabad bullet train project has been completed. The project is expected to be delayed by four years from its initial date of December 2023.

According to the ministry, as of February 28, 2023, there has been a total physical advancement of 26.33 percent. It said that 13.72 percent of the whole work has been finished by Maharashtra. Gujarat, on the other hand, had completed more than 52% of the civil work and currently has a total completion percentage of 36.33%.

The Railways Ministry reports that pier work up to 155.48 km and piling work up to 257.06 km have both been finished. Also, it mentioned the launch of 37.64 km of girders to support the building.

Around 8000 trees have been moved for the project so far, and 83,600 saplings have been planted.

The only High-Speed Rail project in the nation that has been approved is the Mumbai-Ahmedabad route. The execution of the project is being helped by the Japanese government. According to the railway ministry, more than a quarter of the whole project is finished. According to the railways minister, 26% of the work on the Mumbai-Ahmedabad bullet train project has been completed. The project is expected to be delayed by four years from its initial date of December 2023. According to the ministry, as of February 28, 2023, there has been a total physical advancement of 26.33 percent. It said that 13.72 percent of the whole work has been finished by Maharashtra. Gujarat, on the other hand, had completed more than 52% of the civil work and currently has a total completion percentage of 36.33%. The Railways Ministry reports that pier work up to 155.48 km and piling work up to 257.06 km have both been finished. Also, it mentioned the launch of 37.64 km of girders to support the building. Around 8000 trees have been moved for the project so far, and 83,600 saplings have been planted.

Next Story
Infrastructure Urban

Panasonic Showcases Connected Display Solutions

Panasonic Life Solutions India showcased its integrated display, projection, broadcast and communication technologies at Panasonic Tech Summit 2026 in New Delhi. Hosted through its System Solutions Division, the two-day event highlighted connected technology solutions for education, healthcare, retail, transportation, corporate offices and entertainment.The summit, themed ‘Turning Technology into Value’, featured experience-led zones covering QSR, retail, transit, corporate offices, healthcare, education, security, projection, home theatre and professional displays. Panasonic also introduc..

Next Story
Infrastructure Transport

Kapsch to Deliver India’s First C-ITS Project

"Kapsch TrafficCom will deliver India’s first Cooperative Intelligent Transport Systems project on a key expressway near New Delhi. The project will be implemented with Superwave Communication And Infrasolution Limited to demonstrate how connected mobility can improve road safety and traffic efficiency.The pilot will use real-time connectivity and AI-enabled situational awareness to support road users, especially in high-risk areas such as temporary work zones. Drivers will receive alerts on roadworks, maintenance vehicles, hazardous locations, traffic queues and temporary virtual signage di..

Next Story
Infrastructure Urban

Eurobond Net Profit Rises 44 Per Cent

Euro Panel Products, the parent company of Eurobond, reported a 44.13 per cent year-on-year rise in net profit for FY25–26. The company’s revenue from operations grew 18.91 per cent to Rs 503.20 crore, compared to Rs 423.18 crore in the previous financial year.The company’s full-year EBITDA stood at Rs 56.67 crore, marking a 31.82 per cent increase. Profit after tax rose to Rs 26.56 crore, while net worth increased 20.15 per cent to Rs 160.07 crore. Earnings per share for the year stood at Rs 10.84.Divyam Rajesh Shah, Whole Time Director and CFO, Euro Panel Products, said the company’s..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

-->