Status of Mumbai-Ahmedabad bullet train
RAILWAYS & METRO RAIL

Status of Mumbai-Ahmedabad bullet train

The only High-Speed Rail project in the nation that has been approved is the Mumbai-Ahmedabad route. The execution of the project is being helped by the Japanese government. According to the railway ministry, more than a quarter of the whole project is finished.

According to the railways minister, 26% of the work on the Mumbai-Ahmedabad bullet train project has been completed. The project is expected to be delayed by four years from its initial date of December 2023.

According to the ministry, as of February 28, 2023, there has been a total physical advancement of 26.33 percent. It said that 13.72 percent of the whole work has been finished by Maharashtra. Gujarat, on the other hand, had completed more than 52% of the civil work and currently has a total completion percentage of 36.33%.

The Railways Ministry reports that pier work up to 155.48 km and piling work up to 257.06 km have both been finished. Also, it mentioned the launch of 37.64 km of girders to support the building.

Around 8000 trees have been moved for the project so far, and 83,600 saplings have been planted.

The only High-Speed Rail project in the nation that has been approved is the Mumbai-Ahmedabad route. The execution of the project is being helped by the Japanese government. According to the railway ministry, more than a quarter of the whole project is finished. According to the railways minister, 26% of the work on the Mumbai-Ahmedabad bullet train project has been completed. The project is expected to be delayed by four years from its initial date of December 2023. According to the ministry, as of February 28, 2023, there has been a total physical advancement of 26.33 percent. It said that 13.72 percent of the whole work has been finished by Maharashtra. Gujarat, on the other hand, had completed more than 52% of the civil work and currently has a total completion percentage of 36.33%. The Railways Ministry reports that pier work up to 155.48 km and piling work up to 257.06 km have both been finished. Also, it mentioned the launch of 37.64 km of girders to support the building. Around 8000 trees have been moved for the project so far, and 83,600 saplings have been planted.

Next Story
Infrastructure Transport

NHAI Debars Contractor After Slope Collapse on NH-66

The National Highways Authority of India (NHAI) has taken stringent action by debaring its concessionaire, Megha Engineering and Infrastructure Ltd., for one year following the collapse of slope protection works on the Chengala–Neeleshwaram section of National Highway 66 in Kerala. The failure, which occurred on 16 June 2025 in Cherkkala, Kasaragod district, was attributed to inadequate drainage, improper design, and substandard slope protection measures.In addition to the debarment, NHAI has issued a show-cause notice that may result in a monetary penalty of up to Rs 90 million. Under the t..

Next Story
Infrastructure Urban

KVIC Disburses Rs 3 Billion in Subsidies via PMEGP

The Khadi and Village Industries Commission (KVIC) has disbursed Rs 3 billion in margin money subsidies to 11,480 service-sector beneficiaries across India under the Prime Minister’s Employment Generation Programme (PMEGP). This move follows the sanctioning of loan amounts totalling Rs 9.06 billion. The online disbursement was initiated on 17 June 2025 by KVIC Chairman Manoj Kumar, along with senior officials, from the Rajghat office in New Delhi.Chairman Kumar remarked that under Prime Minister Narendra Modi’s leadership, PMEGP has become a powerful tool for fostering employment and sel..

Next Story
Infrastructure Urban

Electric Vehicles Power Waste Collection in Indian Cities

Under the Swachh Bharat Mission–Urban, major Indian cities are leading a shift towards electric vehicles (EVs) for waste collection, reducing emissions and operational costs while improving urban sanitation.In Guntur, Andhra Pradesh, over 200 electric autos have replaced diesel garbage trucks. These EVs cover the city's 159 square kilometres and help save more than 71,000 litres of diesel annually. Over ten years, this is projected to reduce greenhouse gas emissions by nearly 21,000 tonnes, significantly improving air and noise pollution levels.Chennai has deployed 5,478 electric rickshaws f..

Advertisement

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Advertisement

Talk to us?