Status of Mumbai-Ahmedabad bullet train
RAILWAYS & METRO RAIL

Status of Mumbai-Ahmedabad bullet train

The only High-Speed Rail project in the nation that has been approved is the Mumbai-Ahmedabad route. The execution of the project is being helped by the Japanese government. According to the railway ministry, more than a quarter of the whole project is finished.

According to the railways minister, 26% of the work on the Mumbai-Ahmedabad bullet train project has been completed. The project is expected to be delayed by four years from its initial date of December 2023.

According to the ministry, as of February 28, 2023, there has been a total physical advancement of 26.33 percent. It said that 13.72 percent of the whole work has been finished by Maharashtra. Gujarat, on the other hand, had completed more than 52% of the civil work and currently has a total completion percentage of 36.33%.

The Railways Ministry reports that pier work up to 155.48 km and piling work up to 257.06 km have both been finished. Also, it mentioned the launch of 37.64 km of girders to support the building.

Around 8000 trees have been moved for the project so far, and 83,600 saplings have been planted.

The only High-Speed Rail project in the nation that has been approved is the Mumbai-Ahmedabad route. The execution of the project is being helped by the Japanese government. According to the railway ministry, more than a quarter of the whole project is finished. According to the railways minister, 26% of the work on the Mumbai-Ahmedabad bullet train project has been completed. The project is expected to be delayed by four years from its initial date of December 2023. According to the ministry, as of February 28, 2023, there has been a total physical advancement of 26.33 percent. It said that 13.72 percent of the whole work has been finished by Maharashtra. Gujarat, on the other hand, had completed more than 52% of the civil work and currently has a total completion percentage of 36.33%. The Railways Ministry reports that pier work up to 155.48 km and piling work up to 257.06 km have both been finished. Also, it mentioned the launch of 37.64 km of girders to support the building. Around 8000 trees have been moved for the project so far, and 83,600 saplings have been planted.

Related Stories

Gold Stories

Next Story
Infrastructure Urban

Vedanta Metal Bazaar Expands to Global Markets

Vedanta Aluminium has expanded its digital e-commerce platform, Vedanta Metal Bazaar, to international markets, enabling overseas customers to order and purchase aluminium products online.The platform will now be available to buyers across Asia, Europe, Africa and the Americas, providing a digital gateway for export transactions with 24x7 access.In FY26, Vedanta Metal Bazaar processed transactions worth nearly $4.1 billion, or over Rs 380 billion, and fulfilled more than 23,000 orders. The platform is also used regularly by more than 550 MSMEs in India alongside large OEM customers.The export ..

Next Story
Infrastructure Urban

Ramky Infrastructure Q1 FY27 Revenue Rises 24.3%

Ramky Infrastructure Limited reported a 24.3% year-on-year increase in consolidated revenue from operations to Rs 471.2 crore for Q1 FY27, compared with Rs 3.79 billion in the corresponding quarter of FY26.Standalone revenue from operations rose 27.5% YoY to Rs 4.51 billion from Rs 3.54 billion, while total standalone income increased 35% to Rs 5.32 billion.Consolidated profit before tax stood at Rs 540.9 million during the quarter. The company highlighted a sharp sequential improvement compared with a pre-exceptional loss of Rs 190.1 million in Q4 FY26.Two of the three projects awarded during..

Next Story
Technology

LTTS Launches AgenticIQ AI Platform for Engineering

L&T Technology Services (LTTS) has launched AgenticIQ, an end-to-end agentic AI platform designed for engineering and manufacturing organisations.The platform is aimed at helping enterprises move beyond isolated AI pilots by enabling autonomous, multi-agent workflows across engineering, product development, manufacturing, industrial operations and customer experience.AgenticIQ is built on LTTS’ Engineering Intelligence portfolio and converts existing engineering capabilities into specialised, reusable AI agents. Its planning-first architecture is embedded into engineering and production ..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement