Status of Mumbai-Ahmedabad bullet train
RAILWAYS & METRO RAIL

Status of Mumbai-Ahmedabad bullet train

The only High-Speed Rail project in the nation that has been approved is the Mumbai-Ahmedabad route. The execution of the project is being helped by the Japanese government. According to the railway ministry, more than a quarter of the whole project is finished.

According to the railways minister, 26% of the work on the Mumbai-Ahmedabad bullet train project has been completed. The project is expected to be delayed by four years from its initial date of December 2023.

According to the ministry, as of February 28, 2023, there has been a total physical advancement of 26.33 percent. It said that 13.72 percent of the whole work has been finished by Maharashtra. Gujarat, on the other hand, had completed more than 52% of the civil work and currently has a total completion percentage of 36.33%.

The Railways Ministry reports that pier work up to 155.48 km and piling work up to 257.06 km have both been finished. Also, it mentioned the launch of 37.64 km of girders to support the building.

Around 8000 trees have been moved for the project so far, and 83,600 saplings have been planted.

"Join industry leaders at RAHSTA Expo, India's premier platform for roads, highways and traffic infrastructure. Register now to explore innovations, network with experts and shape the future of mobility."

The only High-Speed Rail project in the nation that has been approved is the Mumbai-Ahmedabad route. The execution of the project is being helped by the Japanese government. According to the railway ministry, more than a quarter of the whole project is finished. According to the railways minister, 26% of the work on the Mumbai-Ahmedabad bullet train project has been completed. The project is expected to be delayed by four years from its initial date of December 2023. According to the ministry, as of February 28, 2023, there has been a total physical advancement of 26.33 percent. It said that 13.72 percent of the whole work has been finished by Maharashtra. Gujarat, on the other hand, had completed more than 52% of the civil work and currently has a total completion percentage of 36.33%. The Railways Ministry reports that pier work up to 155.48 km and piling work up to 257.06 km have both been finished. Also, it mentioned the launch of 37.64 km of girders to support the building. Around 8000 trees have been moved for the project so far, and 83,600 saplings have been planted.

Next Story
Infrastructure Urban

ABS Marine Sees CRISIL Credit Rating Upgrade

ABS Marine Services has secured an upgrade to its long term and short term credit ratings from CRISIL, reflecting improved profitability and revenue growth through long term contracts. CRISIL moved the long term rating from BBB+/Stable to A-/Stable and revised the short term rating from A2 to A2+. The action signals strengthened financial metrics and operational resilience. The company benefited from durable client relationships with firms such as ONGC and Schlumberger. The rating decision followed stronger cash flows and an enlarged bank loan facility, which increased from Rs 3,705 million (m..

Next Story
Infrastructure Transport

Project BRAHMANK Marks 16 Years Of Strategic Roads In Arunachal

Project BRAHMANK is marking 16 years of work to establish strategic road and bridge links across Arunachal Pradesh, maintaining and developing 811 kilometres of roads and nearly 86 bridges that range from small culverts to large steel and arch bridges. These transport links are described as critical for ensuring year-round movement of defence personnel, equipment and essential supplies while improving everyday travel for people in remote villages. The project balances national security requirements with regional development by focusing on reliable access in challenging terrain. Notable enginee..

Next Story
Infrastructure Transport

Longleng CSOs Give One Week Ultimatum Over Two-Lane Highway

Civil society organisations (CSOs) in Longleng district have demanded immediate restoration of the deteriorating Changtongya–Longleng two-lane road and sought a detailed status report on the stalled construction within one week. The demand followed a consultative meeting convened under the Phom Peoples' Council (PPC) to discuss welfare and development concerns. PPC president YB Angam Phom said prolonged non-maintenance had caused hardship to commuters and affected transportation, local commerce and the district's development. The meeting urged authorities to undertake immediate restoration a..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement