Status of Mumbai-Ahmedabad bullet train
RAILWAYS & METRO RAIL

Status of Mumbai-Ahmedabad bullet train

The only High-Speed Rail project in the nation that has been approved is the Mumbai-Ahmedabad route. The execution of the project is being helped by the Japanese government. According to the railway ministry, more than a quarter of the whole project is finished.

According to the railways minister, 26% of the work on the Mumbai-Ahmedabad bullet train project has been completed. The project is expected to be delayed by four years from its initial date of December 2023.

According to the ministry, as of February 28, 2023, there has been a total physical advancement of 26.33 percent. It said that 13.72 percent of the whole work has been finished by Maharashtra. Gujarat, on the other hand, had completed more than 52% of the civil work and currently has a total completion percentage of 36.33%.

The Railways Ministry reports that pier work up to 155.48 km and piling work up to 257.06 km have both been finished. Also, it mentioned the launch of 37.64 km of girders to support the building.

Around 8000 trees have been moved for the project so far, and 83,600 saplings have been planted.

The only High-Speed Rail project in the nation that has been approved is the Mumbai-Ahmedabad route. The execution of the project is being helped by the Japanese government. According to the railway ministry, more than a quarter of the whole project is finished. According to the railways minister, 26% of the work on the Mumbai-Ahmedabad bullet train project has been completed. The project is expected to be delayed by four years from its initial date of December 2023. According to the ministry, as of February 28, 2023, there has been a total physical advancement of 26.33 percent. It said that 13.72 percent of the whole work has been finished by Maharashtra. Gujarat, on the other hand, had completed more than 52% of the civil work and currently has a total completion percentage of 36.33%. The Railways Ministry reports that pier work up to 155.48 km and piling work up to 257.06 km have both been finished. Also, it mentioned the launch of 37.64 km of girders to support the building. Around 8000 trees have been moved for the project so far, and 83,600 saplings have been planted.

Related Stories

Gold Stories

Next Story
Infrastructure Urban

Infrastructure Opportunity Outlook by IMPACCT.Info

India’s infrastructure pipeline is witnessing dynamic activity across stages — from immediate bidding to future planning. IMPACCT segments these into three categories: Immediate, 3–6 Month, and Future Opportunities, enabling businesses to identify, prepare, and participate in high-value tenders and projects across sectors.To read full article Click Here ..

Next Story
Real Estate

Glass, Reframed!

Glass façades, quintessential aesthetic building envelopes globally, have been widely adopted in India as well. But when the focus is high-performance building systems that deliver energy efficiency, comfort and architectural identity, glass isn’t the only preference. Combination solutions, involving glass and some other material, improve façade outcomes. Some combinations come at comparable prices, some at a higher price. Here is a selection of performance-oriented solutions...To read the full story Click Here ..

Next Story
Infrastructure Urban

Beyond Building Faster

India’s cities are expanding at an unprecedented pace, bringing new infrastructure and development opportunities while also intensifying challenges around mobility, public spaces, liveability and supporting infrastructure. The question, therefore, is not simply whether India can build faster, but whether it can build cities that work better.At a CW webinar, Are We Designing Better Cities – or Just Building Faster?, moderator Ar. Samir Shaikh, Founding Principal, AR&UD Studio, brought together perspectives from design, development, master planning and technology...To read the full artic..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

SPECIAL OFFER
QR Code