Track laying starts on  Mumbai-Ahmedabad HSR Corridor
RAILWAYS & METRO RAIL

Track laying starts on Mumbai-Ahmedabad HSR Corridor

Construction has commenced on the first reinforced concrete (RC) track bed for the Mumbai-Ahmedabad high-speed rail corridor, utilizing the Japanese Shinkansen-inspired J-slab ballastless track system. This marks the first time utilisation of this track system in India.

The J-slab system consists of pre-cast track slabs on which fastening devices and rails are mounted. These slabs are supported by the RC track bed, with an approximate thickness of 300mm, constructed in situ for individual up and down track lines on the viaduct top. The RC track bed measures 2420mm in width.

RC anchors are integrated to prevent any longitudinal and lateral restraint to the track slab. These RC anchors, with a diameter of 520mm and a height of 260mm, are spaced at approximately 5-meter intervals. They facilitate achieving the desired alignment, both horizontally and vertically, suitable for train operations at speeds of up to 320kmph.

Contracts for track works in the entire Gujarat portion of the corridor have been awarded, with material procurement at an advanced stage. Over 14,000 MT of JIS rails and 50 molds for casting track slabs have been received from Japan. Dedicated factories have been established to manufacture the track slabs, equipped with state-of-the-art technology and infrastructure for precise slab production.

Specialized construction machinery, including rail feeder cars, slab laying cars, and CAM (Cement Asphalt Mortar) laying cars, will be employed for track works. To ensure proper execution, extensive training and certification for Indian contractor personnel are being organized in collaboration with Japan Railway Technical Services (JARTS) as the Training and Certification agency.

Construction has commenced on the first reinforced concrete (RC) track bed for the Mumbai-Ahmedabad high-speed rail corridor, utilizing the Japanese Shinkansen-inspired J-slab ballastless track system. This marks the first time utilisation of this track system in India.The J-slab system consists of pre-cast track slabs on which fastening devices and rails are mounted. These slabs are supported by the RC track bed, with an approximate thickness of 300mm, constructed in situ for individual up and down track lines on the viaduct top. The RC track bed measures 2420mm in width.RC anchors are integrated to prevent any longitudinal and lateral restraint to the track slab. These RC anchors, with a diameter of 520mm and a height of 260mm, are spaced at approximately 5-meter intervals. They facilitate achieving the desired alignment, both horizontally and vertically, suitable for train operations at speeds of up to 320kmph.Contracts for track works in the entire Gujarat portion of the corridor have been awarded, with material procurement at an advanced stage. Over 14,000 MT of JIS rails and 50 molds for casting track slabs have been received from Japan. Dedicated factories have been established to manufacture the track slabs, equipped with state-of-the-art technology and infrastructure for precise slab production.Specialized construction machinery, including rail feeder cars, slab laying cars, and CAM (Cement Asphalt Mortar) laying cars, will be employed for track works. To ensure proper execution, extensive training and certification for Indian contractor personnel are being organized in collaboration with Japan Railway Technical Services (JARTS) as the Training and Certification agency.

Next Story
Real Estate

Serene, Gardencity to Develop Rs 3 Billion Senior Living Project in Bengaluru

Serene Communities, a leading senior living brand, has partnered with Gardencity Realty to develop a premium senior living community in Budigere, one of Bengaluru’s fastest-growing residential micro-markets. The project will span approximately 300,000 sq ft, with a Gross Development Value of about Rs 3 billion, and will add roughly 250 senior-friendly residences to the city’s growing retirement housing segment.The launch forms part of Serene Communities’ national expansion strategy. The company has 11 new projects under development with a planned investment of Rs 25 billion that will add..

Next Story
Real Estate

Alliance City Developers Marks Major 2025 Milestones in Vile Parle

Alliance City Developers Realtors has announced significant project milestones and expansions in 2025, underscoring what the company terms a transformational year. The developer completed multiple residential projects and launched two premium developments in Vile Parle (East), one of Mumbai’s most sought-after neighbourhoods.During the year, Alliance Legacy in Matunga (East) received its Occupancy Certificate (OC), while Alliance Eternis in Borivali (West) and Alliance Vista in Vile Parle (East) were granted Completion Certificates (CC), marking final project delivery. Alliance Abhimanyu is ..

Next Story
Infrastructure Energy

Moro Hub and PwC Middle East Partner to Accelerate Smart City Solutions

Moro Hub, a subsidiary of Digital DEWA, the digital arm of Dubai Electricity and Water Authority (DEWA), has announced a strategic collaboration with PwC Middle East to advance Smart City, Integrated Command Centre (ICC), Critical Infrastructure Monitoring and Internet of Things (IoT) initiatives across the region. The partnership brings together Moro Hub’s digital infrastructure and IoT capabilities with PwC’s global expertise in digital trust, smart city strategy and cybersecurity to support the UAE’s vision for intelligent and sustainable cities.“Our collaboration with PwC Middle Ea..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Advertisement

Open In App