Track laying starts on Mumbai-Ahmedabad HSR Corridor

Construction has commenced on the first reinforced concrete (RC) track bed for the Mumbai-Ahmedabad high-speed rail corridor, utilizing the Japanese Shinkansen-inspired J-slab ballastless track system. This marks the first time utilisation of this track system in India.

The J-slab system consists of pre-cast track slabs on which fastening devices and rails are mounted. These slabs are supported by the RC track bed, with an approximate thickness of 300mm, constructed in situ for individual up and down track lines on the viaduct top. The RC track bed measures 2420mm in width.

RC anchors are integrated to prevent any longitudinal and lateral restraint to the track slab. These RC anchors, with a diameter of 520mm and a height of 260mm, are spaced at approximately 5-meter intervals. They facilitate achieving the desired alignment, both horizontally and vertically, suitable for train operations at speeds of up to 320kmph.

Contracts for track works in the entire Gujarat portion of the corridor have been awarded, with material procurement at an advanced stage. Over 14,000 MT of JIS rails and 50 molds for casting track slabs have been received from Japan. Dedicated factories have been established to manufacture the track slabs, equipped with state-of-the-art technology and infrastructure for precise slab production.

Specialized construction machinery, including rail feeder cars, slab laying cars, and CAM (Cement Asphalt Mortar) laying cars, will be employed for track works. To ensure proper execution, extensive training and certification for Indian contractor personnel are being organized in collaboration with Japan Railway Technical Services (JARTS) as the Training and Certification agency.

Construction has commenced on the first reinforced concrete (RC) track bed for the Mumbai-Ahmedabad high-speed rail corridor, utilizing the Japanese Shinkansen-inspired J-slab ballastless track system. This marks the first time utilisation of this track system in India.The J-slab system consists of pre-cast track slabs on which fastening devices and rails are mounted. These slabs are supported by the RC track bed, with an approximate thickness of 300mm, constructed in situ for individual up and down track lines on the viaduct top. The RC track bed measures 2420mm in width.RC anchors are integrated to prevent any longitudinal and lateral restraint to the track slab. These RC anchors, with a diameter of 520mm and a height of 260mm, are spaced at approximately 5-meter intervals. They facilitate achieving the desired alignment, both horizontally and vertically, suitable for train operations at speeds of up to 320kmph.Contracts for track works in the entire Gujarat portion of the corridor have been awarded, with material procurement at an advanced stage. Over 14,000 MT of JIS rails and 50 molds for casting track slabs have been received from Japan. Dedicated factories have been established to manufacture the track slabs, equipped with state-of-the-art technology and infrastructure for precise slab production.Specialized construction machinery, including rail feeder cars, slab laying cars, and CAM (Cement Asphalt Mortar) laying cars, will be employed for track works. To ensure proper execution, extensive training and certification for Indian contractor personnel are being organized in collaboration with Japan Railway Technical Services (JARTS) as the Training and Certification agency.

Next Story
Infrastructure Urban

India Plans 500 km Rail Expansion Along Northeastern Frontier

India is set to strengthen its northeastern frontier with the construction of 500 kilometres of new rail lines, including bridges and tunnels, to improve connectivity, accelerate logistics, and ensure military readiness along borders with China, Bangladesh, Myanmar, and Bhutan. The project is expected to cost Rs 300 billion ($3.4 billion) and is targeted for completion within four years.Though relations with China have recently improved, the infrastructure push reflects India’s long-term contingency planning amid a history of cycles of rapprochement and tension. The new rail corridors will c..

Next Story
Real Estate

BlackRock Leases Bengaluru Office for Rs 410 Billion

BlackRock Services India Pvt Ltd, the Indian arm of global asset manager BlackRock Inc, has leased 1.43 lakh sq ft of office space in Bengaluru’s Ashok Nagar for Rs 410 billion over a 10-year period, according to property registration documents accessed by Propstack.The commercial space, located in KNG Tower 1 and leased from IndiQube Space Limited, covers the ground floor and five additional floors. The monthly rent is set at Rs 2.72 billion at Rs 190 per sq ft, with an annual escalation of 5 per cent. A security deposit of Rs 21.75 billion has been paid. The lease transaction was registere..

Next Story
Infrastructure Energy

India Launches First Geothermal Energy Policy

India has unveiled its first National Policy on Geothermal Energy, marking a major step in its clean energy journey. Announced by the Ministry of New and Renewable Energy (MNRE), the policy seeks to integrate geothermal energy into the country’s renewable energy portfolio, supporting its goal of net-zero emissions by 2070.Geothermal energy, which harnesses the Earth’s natural heat, offers 24/7 electricity, grid stability, and energy access for remote areas. The policy places emphasis on research and development, particularly improving exploration and drilling methods, while also encouragin..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Talk to us?