Vande Bharats to Run on Bullet Train Corridor until Shinkansens Arrive
RAILWAYS & METRO RAIL

Vande Bharats to Run on Bullet Train Corridor until Shinkansens Arrive

Amid delays in finalizing the deal for the procurement of Japanese Shinkansen bullet trains for India’s first high-speed Mumbai-Ahmedabad corridor, the railway ministry has now invited bids for a signalling system that will enable Vande Bharat trains, with a maximum design speed of 280 kph, to run on this route.

Initially, the ministry had stated that Shinkansen trains would make their debut on the Surat-Bilimora section by August 2026. However, it has become clear that these high-speed trains may not be a reality until after 2030. According to sources, the complete operation of Shinkansen trains along the entire corridor—whose foundation stone was laid in September 2017—will only happen by 2033.

This became apparent when the National High-Speed Rail Corporation (NHRSCL) published the tender for the signalling system required for Vande Bharat trains. The tender outlines that the successful bidder will need to design, manufacture, supply, install, and maintain the signalling and train control system, which will use the European Train Control System (ETCS) Level-2. This is distinct from the Japanese DS-ATC signalling used for Shinkansen trains.

The contract period for ETCS-2 is seven years from the date of work award. Sources mention that deploying the ETCS-2 system will ensure the infrastructure is utilized efficiently. The plan is to start commercial operations of Vande Bharat trains on this track by 2027.

“There is no point in leaving this capital-intensive project unused while waiting for the Japanese trains. Once Vande Bharat trains are operational, the installation of the Japanese signalling system for Shinkansen can proceed. The timeline for introducing the E-10 series trains (an advanced version of bullet trains) in 2030 or later will be determined once trains suitable for Indian conditions are available,” a source said.

As per the plan, once the Shinkansen trains are fully operational, the advanced versions of Vande Bharat trains and the ETCS will be shifted to other projects.

Amid delays in finalizing the deal for the procurement of Japanese Shinkansen bullet trains for India’s first high-speed Mumbai-Ahmedabad corridor, the railway ministry has now invited bids for a signalling system that will enable Vande Bharat trains, with a maximum design speed of 280 kph, to run on this route. Initially, the ministry had stated that Shinkansen trains would make their debut on the Surat-Bilimora section by August 2026. However, it has become clear that these high-speed trains may not be a reality until after 2030. According to sources, the complete operation of Shinkansen trains along the entire corridor—whose foundation stone was laid in September 2017—will only happen by 2033. This became apparent when the National High-Speed Rail Corporation (NHRSCL) published the tender for the signalling system required for Vande Bharat trains. The tender outlines that the successful bidder will need to design, manufacture, supply, install, and maintain the signalling and train control system, which will use the European Train Control System (ETCS) Level-2. This is distinct from the Japanese DS-ATC signalling used for Shinkansen trains. The contract period for ETCS-2 is seven years from the date of work award. Sources mention that deploying the ETCS-2 system will ensure the infrastructure is utilized efficiently. The plan is to start commercial operations of Vande Bharat trains on this track by 2027. “There is no point in leaving this capital-intensive project unused while waiting for the Japanese trains. Once Vande Bharat trains are operational, the installation of the Japanese signalling system for Shinkansen can proceed. The timeline for introducing the E-10 series trains (an advanced version of bullet trains) in 2030 or later will be determined once trains suitable for Indian conditions are available,” a source said. As per the plan, once the Shinkansen trains are fully operational, the advanced versions of Vande Bharat trains and the ETCS will be shifted to other projects.

Related Stories

Gold Stories

Next Story
Resources

Schindler named among Forbes’ World’s Best Employers 2026

Schindler has been named among Forbes’ World’s Best Employers 2026, a global ranking recognising companies for their workplace environments.Compiled by Forbes in partnership with Statista, the ranking is based on independent employee feedback, including whether employees would recommend their organisation to friends and family.The company said the recognition reflected its focus on creating a workplace where employees can develop their expertise and build careers. ..

Next Story
Infrastructure Urban

India needs an export-execution mindset: Vishesh Jain

Interview with Vishesh Jain, Founder & CEO, EximpleWhat gaps in India’s global trade ecosystem led you to build Eximple, and what problem did you see businesses struggling with most?Eximple came out of a problem that all three founders had seen from different choke points in the trade ecosystem. India has millions of MSMEs and manufacturers, and many of them can make products that are genuinely competitive on quality. Yet only a small fraction is able to build meaningful international businesses. In our experience, the gap is usually not manufacturing capability; it is the ability to exe..

Next Story
Building Material

Nuvoco reports 13.5% revenue growth in Q2 FY27

Nuvoco Vistas Corp. Ltd. reported consolidated revenue of Rs 27.9 billion for Q2 FY27, up 13.5% year on year. Cement sales volume rose 9% to 4.7 million tonnes (MMT), while EBITDA increased 11% to Rs 4.11 billion.The company said it began its cement operations in 2014 with a 2.3 MMT per annum (MMTPA) operation at Nimbol. It now aims to reach 35 MMTPA of cement capacity by FY28, nearly 15 times its initial capacity. Its portfolio spans cement, ready-mix concrete and modern building materials.On sustainability and cost efficiency, Nuvoco partnered with CleanMax for a 46.4 MW wind-solar hybrid re..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

SPECIAL OFFER
QR Code