DMK Govt Supports Rs 35.70 Bn Port–Maduravoyal Elevated Expressway
PORTS & SHIPPING

DMK Govt Supports Rs 35.70 Bn Port–Maduravoyal Elevated Expressway

The Tamil Nadu Public Works Department (PWD) Minister E V Velu has confirmed the DMK government’s full cooperation for the Rs 35.70-billion Port–Maduravoyal elevated expressway project by signing the State Support Agreement. This move is expected to facilitate the smooth implementation of the Centre-led infrastructure initiative.

Originally launched during the Congress-led UPA regime, the expressway project was stalled in 2012 by the AIADMK government under J Jayalalithaa. The project was revived after renewed efforts by the National Highways Authority of India (NHAI), which issued the work order in November 2023. However, site handover occurred only in May last year due to objections raised by the Water Resources Department (WRD).

In a recent update presented in the Tamil Nadu Assembly, the PWD Minister provided details on the current status of the project. Out of the 5,296 planned piles, 812 have been constructed, and 41 out of 882 pile caps have been completed. Work faced a temporary three-month halt during the last monsoon season following an order from the National Green Tribunal (NGT).

The 15-kilometre expressway, which is being built over the Cooum River, has now received the necessary no-objection certificate from the WRD. Construction of the superstructure is progressing at two designated casting yards, with 14 segments completed out of a total 9,415.

To ensure faster progress, regular review meetings are being conducted involving key stakeholders such as NHAI, WRD, Tangedco, the police, Greater Chennai Corporation, Tamil Nadu Urban Habitat Development Board, the Indian Navy, and contractors. Efforts are also underway to resettle families residing along the riverbanks and to relocate electricity infrastructure as part of the project execution.

Additionally, suggestions have been made in the Assembly to name the expressway after former Chief Minister M Karunanidhi and to extend it from Poonamallee to the Outer Ring Road.

News source: News on Projects

The Tamil Nadu Public Works Department (PWD) Minister E V Velu has confirmed the DMK government’s full cooperation for the Rs 35.70-billion Port–Maduravoyal elevated expressway project by signing the State Support Agreement. This move is expected to facilitate the smooth implementation of the Centre-led infrastructure initiative. Originally launched during the Congress-led UPA regime, the expressway project was stalled in 2012 by the AIADMK government under J Jayalalithaa. The project was revived after renewed efforts by the National Highways Authority of India (NHAI), which issued the work order in November 2023. However, site handover occurred only in May last year due to objections raised by the Water Resources Department (WRD). In a recent update presented in the Tamil Nadu Assembly, the PWD Minister provided details on the current status of the project. Out of the 5,296 planned piles, 812 have been constructed, and 41 out of 882 pile caps have been completed. Work faced a temporary three-month halt during the last monsoon season following an order from the National Green Tribunal (NGT). The 15-kilometre expressway, which is being built over the Cooum River, has now received the necessary no-objection certificate from the WRD. Construction of the superstructure is progressing at two designated casting yards, with 14 segments completed out of a total 9,415. To ensure faster progress, regular review meetings are being conducted involving key stakeholders such as NHAI, WRD, Tangedco, the police, Greater Chennai Corporation, Tamil Nadu Urban Habitat Development Board, the Indian Navy, and contractors. Efforts are also underway to resettle families residing along the riverbanks and to relocate electricity infrastructure as part of the project execution. Additionally, suggestions have been made in the Assembly to name the expressway after former Chief Minister M Karunanidhi and to extend it from Poonamallee to the Outer Ring Road. News source: News on Projects

Next Story
Infrastructure Transport

Mumbai-Ahmedabad Bullet Train Set to Launch by 2028

India’s first bullet train is set to revolutionize high-speed travel along the western corridor, with the Mumbai-Ahmedabad high-speed rail project aiming for a 2028 launch. This announcement marks a major milestone in India’s infrastructure goals, as it promises to reduce travel time between the two economic hubs from eight hours to just three.Spanning a planned 508-kilometre stretch, the corridor stands as a flagship example of Indo-Japanese collaboration in technology and engineering. Once operational, the train is expected to transform intercity mobility and place India among the select..

Next Story
Infrastructure Transport

Mumbai-Gandhinagar Train Service Enhances Passenger Capacity

The Mumbai Central–Gandhinagar Capital Vande Bharat Express has increased its passenger capacity by adding four additional AC chair car coaches to meet the growing commuter demand on one of India’s busiest business corridors. This upgrade, effective from 11 May, raised the train’s seating capacity from 1,128 to 1,440 passengers, allowing it to serve 936 more passengers daily in both directions. The increase was described as a practical measure to accommodate the surging demand on the busy Mumbai–Ahmedabad–Gandhinagar route, which regularly operates at over 150 percent seat occupancy...

Next Story
Infrastructure Urban

Delhi Plans 12 Sewage Plants to Clean Najafgarh Drain Efficiently

Delhi’s ambitious plan to improve the water quality of the Yamuna River has gained significant momentum as the Delhi Jal Board (DJB) has begun work on 12 new sewage treatment plants (STPs) aimed at reducing the volume of untreated sewage being discharged from the Najafgarh Drain.This initiative forms part of the ongoing efforts to clean the Yamuna and restore the river’s health, which has long been a critical environmental issue for the national capital. Given the alarming pollution levels in the Yamuna, experts and officials consider this project a vital step toward addressing the persist..

Advertisement

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Advertisement

Talk to us?