DMK Govt Supports Rs 35.70 Bn Port–Maduravoyal Elevated Expressway

The Tamil Nadu Public Works Department (PWD) Minister E V Velu has confirmed the DMK government’s full cooperation for the Rs 35.70-billion Port–Maduravoyal elevated expressway project by signing the State Support Agreement. This move is expected to facilitate the smooth implementation of the Centre-led infrastructure initiative.

Originally launched during the Congress-led UPA regime, the expressway project was stalled in 2012 by the AIADMK government under J Jayalalithaa. The project was revived after renewed efforts by the National Highways Authority of India (NHAI), which issued the work order in November 2023. However, site handover occurred only in May last year due to objections raised by the Water Resources Department (WRD).

In a recent update presented in the Tamil Nadu Assembly, the PWD Minister provided details on the current status of the project. Out of the 5,296 planned piles, 812 have been constructed, and 41 out of 882 pile caps have been completed. Work faced a temporary three-month halt during the last monsoon season following an order from the National Green Tribunal (NGT).

The 15-kilometre expressway, which is being built over the Cooum River, has now received the necessary no-objection certificate from the WRD. Construction of the superstructure is progressing at two designated casting yards, with 14 segments completed out of a total 9,415.

To ensure faster progress, regular review meetings are being conducted involving key stakeholders such as NHAI, WRD, Tangedco, the police, Greater Chennai Corporation, Tamil Nadu Urban Habitat Development Board, the Indian Navy, and contractors. Efforts are also underway to resettle families residing along the riverbanks and to relocate electricity infrastructure as part of the project execution.

Additionally, suggestions have been made in the Assembly to name the expressway after former Chief Minister M Karunanidhi and to extend it from Poonamallee to the Outer Ring Road.

News source: News on Projects

The Tamil Nadu Public Works Department (PWD) Minister E V Velu has confirmed the DMK government’s full cooperation for the Rs 35.70-billion Port–Maduravoyal elevated expressway project by signing the State Support Agreement. This move is expected to facilitate the smooth implementation of the Centre-led infrastructure initiative. Originally launched during the Congress-led UPA regime, the expressway project was stalled in 2012 by the AIADMK government under J Jayalalithaa. The project was revived after renewed efforts by the National Highways Authority of India (NHAI), which issued the work order in November 2023. However, site handover occurred only in May last year due to objections raised by the Water Resources Department (WRD). In a recent update presented in the Tamil Nadu Assembly, the PWD Minister provided details on the current status of the project. Out of the 5,296 planned piles, 812 have been constructed, and 41 out of 882 pile caps have been completed. Work faced a temporary three-month halt during the last monsoon season following an order from the National Green Tribunal (NGT). The 15-kilometre expressway, which is being built over the Cooum River, has now received the necessary no-objection certificate from the WRD. Construction of the superstructure is progressing at two designated casting yards, with 14 segments completed out of a total 9,415. To ensure faster progress, regular review meetings are being conducted involving key stakeholders such as NHAI, WRD, Tangedco, the police, Greater Chennai Corporation, Tamil Nadu Urban Habitat Development Board, the Indian Navy, and contractors. Efforts are also underway to resettle families residing along the riverbanks and to relocate electricity infrastructure as part of the project execution. Additionally, suggestions have been made in the Assembly to name the expressway after former Chief Minister M Karunanidhi and to extend it from Poonamallee to the Outer Ring Road. News source: News on Projects

Next Story
Resources

Jyoti Structures Launches Heat Safety Drive Across Sites

Jyoti Structures (JSL) has strengthened heat safety measures across its project sites and manufacturing facilities as temperatures rise across India. The company has implemented a Summer Safety Plan covering all transmission line projects to address risks related to heat stress, dehydration and worker fatigue.The initiative includes rescheduling work away from peak afternoon temperatures, provision of drinking water, ORS and lemon-salt solutions, and installation of rest shelters near work areas. Daily toolbox talks, worker health monitoring, first-aid preparedness, emergency transport arrange..

Next Story
Real Estate

MHADA Declares 82 Buildings Most Dangerous in Central and South Mumbai

The Maharashtra Housing and Area Development Authority (MHADA) has declared 82 buildings as most dangerous across Central and South Mumbai and has appealed to residents to vacate immediately. The list, prepared after structural assessments by the authority, identifies buildings judged to pose imminent risk to occupants and to passersby. Local civic bodies have been asked to coordinate evacuations and to make arrangements for temporary shelter and rehabilitation for displaced households. Officials said the authority prioritised buildings with visible structural distress, severe cracking, tiltin..

Next Story
Infrastructure Transport

Damage Reported At Halwara Airport Terminal After First Rains

Severe damage was reported at the terminal of Halwara Airport during the first major rain spell of the season, prompting immediate concern among aviation and local authorities. Images from the site showed water ingress and visible deterioration of the terminal interior, affecting passenger areas and ancillary services. The airport authority suspended certain operations temporarily to assess structural safety and ensure passenger wellbeing. Preliminary inspections have prioritised electrical systems and roof seals to prevent further water ingress. State aviation officials ordered a formal inqui..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement