+
V O Chidambaranar Port Authority floats fresh tenders
PORTS & SHIPPING

V O Chidambaranar Port Authority floats fresh tenders

V O Chidambaranar Port Authority, the state-owned entity that runs the port at Thoothukudi in Tamil Nadu, is testing the waters yet again by floating a fresh tender to build an ambitious 4 million twenty-foot equivalent units (TEUs) capacity container terminal in the southern port’s outer harbour with private funds of Rs 70.55 billion.

On October 30, the port authority cancelled a six-month long tender for the project after the two groups that filed initial bids failed to qualify for the project.

The tender terms have been kept unchanged from the previous attempt to conform to a government stand that the project parameters approved by the cabinet and the tender conditions can be changed only after two attempts turn futile. This view was revealed by a senior government official during a road show in Mumbai earlier this year during the first attempt in which bidders raised several concerns on the project structuring and cost estimates.

“We are at a take-off point where these things will happen and I will assure you that anything that takes to make such projects work we have built in the necessary provisions in the sanction orders which enables us to be more flexible,” the official had said.

“So, if the sum total of all the industry representative’s opinions is that some things need change, and due to that we have a problem in getting the bids that we expected, then we’ll go back to the drawing board, there is no hesitation in doing that. We have been given that authority to go back to the drawing board and look at what can be changed but for that we need one cycle to go through,” he had said.

“If some other model is to be brought in including viability gap funding (VGF) spread over some more period or longer phases or even in some cases we have been looking at the Hybrid Annuity Model (HAM) like in the case of the Vadhvan port, we might bring in more changes but for that we need suggestions from the industry which can be looked at, though there will be constraints on what we will like to do,” he had said.

The fact that potential bidders were not enthusiastic about the project was evident right from the start after the tender was floated in February this year.

During a road show in Mumbai in March and the subsequent pre-bid meetings, potential bidders drew the attention of the port authority on concerns over what they cited as “unrealistic” cost estimates worked out by the VOC Port Authority with the help of the National Technology Centre for Ports, Waterways and Coasts (NTCPWC) under the Indian Institute of Technology Madras (IITM) on dredging and break water construction. The National Technology Centre for Ports, Waterways and Coasts, the technology arm of the Ministry of Ports, Shipping and Waterways, was hired on nomination basis by VOC Port Authority to write the Detailed Project Report (DPR) for the mega project.

While IIT Madras has been providing technical services to VOC Port for many years, this was the first time it wrote a “commercial proposal” for the port, covering traffic forecast, cost estimate, financial analysis and viability, among other things.

“The tender result shows that the advice given by IIT Madras has hurt VOC Port. The port authority has lost investors’ confidence in the project due to unmarketable and non-bankable PPP proposal based on the advice given by IIT Madras which potential bidders felt was unreliable,” a port industry source said.

V O Chidambaranar Port Authority, the state-owned entity that runs the port at Thoothukudi in Tamil Nadu, is testing the waters yet again by floating a fresh tender to build an ambitious 4 million twenty-foot equivalent units (TEUs) capacity container terminal in the southern port’s outer harbour with private funds of Rs 70.55 billion. On October 30, the port authority cancelled a six-month long tender for the project after the two groups that filed initial bids failed to qualify for the project. The tender terms have been kept unchanged from the previous attempt to conform to a government stand that the project parameters approved by the cabinet and the tender conditions can be changed only after two attempts turn futile. This view was revealed by a senior government official during a road show in Mumbai earlier this year during the first attempt in which bidders raised several concerns on the project structuring and cost estimates. “We are at a take-off point where these things will happen and I will assure you that anything that takes to make such projects work we have built in the necessary provisions in the sanction orders which enables us to be more flexible,” the official had said. “So, if the sum total of all the industry representative’s opinions is that some things need change, and due to that we have a problem in getting the bids that we expected, then we’ll go back to the drawing board, there is no hesitation in doing that. We have been given that authority to go back to the drawing board and look at what can be changed but for that we need one cycle to go through,” he had said. “If some other model is to be brought in including viability gap funding (VGF) spread over some more period or longer phases or even in some cases we have been looking at the Hybrid Annuity Model (HAM) like in the case of the Vadhvan port, we might bring in more changes but for that we need suggestions from the industry which can be looked at, though there will be constraints on what we will like to do,” he had said. The fact that potential bidders were not enthusiastic about the project was evident right from the start after the tender was floated in February this year. During a road show in Mumbai in March and the subsequent pre-bid meetings, potential bidders drew the attention of the port authority on concerns over what they cited as “unrealistic” cost estimates worked out by the VOC Port Authority with the help of the National Technology Centre for Ports, Waterways and Coasts (NTCPWC) under the Indian Institute of Technology Madras (IITM) on dredging and break water construction. The National Technology Centre for Ports, Waterways and Coasts, the technology arm of the Ministry of Ports, Shipping and Waterways, was hired on nomination basis by VOC Port Authority to write the Detailed Project Report (DPR) for the mega project. While IIT Madras has been providing technical services to VOC Port for many years, this was the first time it wrote a “commercial proposal” for the port, covering traffic forecast, cost estimate, financial analysis and viability, among other things. “The tender result shows that the advice given by IIT Madras has hurt VOC Port. The port authority has lost investors’ confidence in the project due to unmarketable and non-bankable PPP proposal based on the advice given by IIT Madras which potential bidders felt was unreliable,” a port industry source said.

Related Stories

Gold Stories

Next Story
Infrastructure Transport

97 Per Cent Of Rongjeng-Mangsang-Adokgre Road Nears Completion

Deputy Chief Minister in-charge of public works Prestone Tynsong said in Shillong on 26 August that 97 per cent physical progress had been achieved on the ongoing Rongjeng-Mangsang-Adokgre road being constructed under the Non-Lapsable Central Pool of Resources (NLCPR). He noted the project was sanctioned in 2017 and that the stipulated time for completion had been 24 months from issue of the final work order. The deputy chief minister informed the assembly that the government had decided to include the remaining work under a World Bank project. In reply to a query from Rongjeng MLA Jim M Sangm..

Next Story
Infrastructure Transport

First TBM Starts Digging Five Point Three Kilometre Tunnel Under SGNP

The Goregaon-Mulund Link Road (GMLR) Phase three (B) project has reached a key milestone as the first tunnel boring machine (TBM) began excavation of the first of two tunnels beneath the Sanjay Gandhi National Park (SGNP). The machine, named Tulsi, started cutting a five point three kilometre bore that will link Dadasaheb Phalke Chitranagari in Goregaon East with Amar Nagar in Mulund West. Officials issued a statement noting the commencement of tunnelling work under the protected green belt. The twin tunnels are being constructed using mechanised tunnelling methods that aim to limit surface di..

Next Story
Infrastructure Transport

UP Approves Two Expressways And Rs 240 bn Infrastructure Push

The Uttar Pradesh Cabinet approved a series of infrastructure and industrial investment proposals totalling Rs 240 billion (Rs 240 bn), including two major expressway projects, a manufacturing and logistics cluster in Sultanpur and incentives for 11 industrial projects across the state. The decisions, taken at a meeting chaired by Chief Minister Yogi Adityanath, underline the state government’s focus on expanding road connectivity around emerging industrial hubs while attracting manufacturing investment to districts beyond major urban centres. The approvals cover both greenfield expressway c..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

SPECIAL OFFER
QR Code