Nashik Completes 18 of 21 Smart City projects; Final Handovers Begin
SMART CITIES

Nashik Completes 18 of 21 Smart City projects; Final Handovers Begin

The Nashik Municipal Smart City Development Corporation (NMSCDCL) has not yet completed three of the 21 projects under the Smart City Mission, even though the official term of the program ended on March 31. On March 28, the state government directed NMSCDCL to transfer the completed projects to the Nashik Municipal Corporation (NMC) for further management. Under the Smart City Mission, NMSCDCL launched 21 projects with a total investment of Rs 10 billion. Of these, 18 projects, worth Rs 6.50 billion, have been completed, while three remain under development.

Sumant More, the CEO of NMSCDCL, confirmed that 15 of the completed projects had already been handed over to NMC, with the remaining three, including Goda Park and roadworks in gaothan areas, in the process of being transferred. Among the pending projects, two are progressing steadily and are expected to be completed by the end of April, while the third is slated for completion by December. More assured that these projects will be formally handed over to NMC, ensuring their continued operation and maintenance.

The Smart City Mission was originally designed as a five-year initiative, scheduled to conclude in June 2022. However, the central government extended the program until March 31 of this year, providing additional time for the completion of ongoing projects. The total estimated cost for the 21 smart city projects is Rs 11.22 billion, including Rs 1.75 billion for two projects—streetlight installation and solar panel implementation—executed under the public-private partnership (PPP) model. The remaining 19 projects, valued at Rs 9.46 billion, have been financed by the smart city corporation.

NMSCDCL has received Rs 8.97 billion in funding from the central and state governments, as well as from NMC. This includes Rs 4.65 billion from the central government, Rs 2.32 billion from the state government, and Rs 2 billion from NMC. However, NMC has yet to release Rs 480.51 million in outstanding funds. To date, NMSCDCL has spent Rs 6.50 billion on various smart city initiatives.

Despite the progress made, the timely completion of the remaining projects remains a priority. The transfer of completed projects to NMC will ensure their continued management and maintenance, reinforcing the city’s commitment to urban development, technological advancement, improved transportation networks, and enhanced infrastructure.

News source: Prop News Time

The Nashik Municipal Smart City Development Corporation (NMSCDCL) has not yet completed three of the 21 projects under the Smart City Mission, even though the official term of the program ended on March 31. On March 28, the state government directed NMSCDCL to transfer the completed projects to the Nashik Municipal Corporation (NMC) for further management. Under the Smart City Mission, NMSCDCL launched 21 projects with a total investment of Rs 10 billion. Of these, 18 projects, worth Rs 6.50 billion, have been completed, while three remain under development. Sumant More, the CEO of NMSCDCL, confirmed that 15 of the completed projects had already been handed over to NMC, with the remaining three, including Goda Park and roadworks in gaothan areas, in the process of being transferred. Among the pending projects, two are progressing steadily and are expected to be completed by the end of April, while the third is slated for completion by December. More assured that these projects will be formally handed over to NMC, ensuring their continued operation and maintenance. The Smart City Mission was originally designed as a five-year initiative, scheduled to conclude in June 2022. However, the central government extended the program until March 31 of this year, providing additional time for the completion of ongoing projects. The total estimated cost for the 21 smart city projects is Rs 11.22 billion, including Rs 1.75 billion for two projects—streetlight installation and solar panel implementation—executed under the public-private partnership (PPP) model. The remaining 19 projects, valued at Rs 9.46 billion, have been financed by the smart city corporation. NMSCDCL has received Rs 8.97 billion in funding from the central and state governments, as well as from NMC. This includes Rs 4.65 billion from the central government, Rs 2.32 billion from the state government, and Rs 2 billion from NMC. However, NMC has yet to release Rs 480.51 million in outstanding funds. To date, NMSCDCL has spent Rs 6.50 billion on various smart city initiatives. Despite the progress made, the timely completion of the remaining projects remains a priority. The transfer of completed projects to NMC will ensure their continued management and maintenance, reinforcing the city’s commitment to urban development, technological advancement, improved transportation networks, and enhanced infrastructure. News source: Prop News Time

Next Story
Technology

AI-Enabled Workflows Lift Profitability and Productivity

Organisations modernising frontline workflows with artificial intelligence, automation and real-time data are reporting stronger financial performance, higher productivity and improved employee engagement, according to a global study by Zebra Technologies and Oxford Economics.The research covered 1,000 senior leaders across retail, manufacturing, transportation and logistics in the US, Mexico, the UK, Germany, India, Japan, Australia and New Zealand.In transportation and logistics, 54 per cent of companies that improved picking and packing operations reported faster operational performance, wh..

Next Story
Real Estate

India Leads Global AI Readiness but Implementation Lags

Indian companies lead global averages across all eight artificial intelligence readiness indicators tracked by JLL, but only 19 per cent have started making changes to their workplaces, according to the JLL 2026 Future of Work Survey.The study found that 77 per cent of Indian business leaders expect AI to change their office requirements, creating a 58-percentage-point gap between awareness and implementation. The survey covered more than 2,200 CEOs, CFOs and real estate leaders across 21 countries during the first quarter of 2026.Despite concerns over automation, 58 per cent of Indian leaders..

Next Story
Equipment

Three WOLFF Cranes Build Riyadh Cable-Stayed Bridges

Three WOLFF 180 B luffing jib cranes are supporting the construction of two cable-stayed bridges alongside the existing Wadi Laban Bridge in Riyadh, Saudi Arabia. The project is being developed for the Royal Commission for Riyadh City and executed by the ICRC joint venture comprising IC Ictas and Al Rashid Trading & Contracting Company.The cranes are handling lifting operations including formwork, reinforcement, concrete placement, work platforms, surveying equipment and other construction materials. Each crane is fitted with a 40 m jib, reaches a hook height of 157 m and offers a maximum ..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement