Nashik Completes 18 of 21 Smart City projects; Final Handovers Begin
SMART CITIES

Nashik Completes 18 of 21 Smart City projects; Final Handovers Begin

The Nashik Municipal Smart City Development Corporation (NMSCDCL) has not yet completed three of the 21 projects under the Smart City Mission, even though the official term of the program ended on March 31. On March 28, the state government directed NMSCDCL to transfer the completed projects to the Nashik Municipal Corporation (NMC) for further management. Under the Smart City Mission, NMSCDCL launched 21 projects with a total investment of Rs 10 billion. Of these, 18 projects, worth Rs 6.50 billion, have been completed, while three remain under development.

Sumant More, the CEO of NMSCDCL, confirmed that 15 of the completed projects had already been handed over to NMC, with the remaining three, including Goda Park and roadworks in gaothan areas, in the process of being transferred. Among the pending projects, two are progressing steadily and are expected to be completed by the end of April, while the third is slated for completion by December. More assured that these projects will be formally handed over to NMC, ensuring their continued operation and maintenance.

The Smart City Mission was originally designed as a five-year initiative, scheduled to conclude in June 2022. However, the central government extended the program until March 31 of this year, providing additional time for the completion of ongoing projects. The total estimated cost for the 21 smart city projects is Rs 11.22 billion, including Rs 1.75 billion for two projects—streetlight installation and solar panel implementation—executed under the public-private partnership (PPP) model. The remaining 19 projects, valued at Rs 9.46 billion, have been financed by the smart city corporation.

NMSCDCL has received Rs 8.97 billion in funding from the central and state governments, as well as from NMC. This includes Rs 4.65 billion from the central government, Rs 2.32 billion from the state government, and Rs 2 billion from NMC. However, NMC has yet to release Rs 480.51 million in outstanding funds. To date, NMSCDCL has spent Rs 6.50 billion on various smart city initiatives.

Despite the progress made, the timely completion of the remaining projects remains a priority. The transfer of completed projects to NMC will ensure their continued management and maintenance, reinforcing the city’s commitment to urban development, technological advancement, improved transportation networks, and enhanced infrastructure.

News source: Prop News Time

The Nashik Municipal Smart City Development Corporation (NMSCDCL) has not yet completed three of the 21 projects under the Smart City Mission, even though the official term of the program ended on March 31. On March 28, the state government directed NMSCDCL to transfer the completed projects to the Nashik Municipal Corporation (NMC) for further management. Under the Smart City Mission, NMSCDCL launched 21 projects with a total investment of Rs 10 billion. Of these, 18 projects, worth Rs 6.50 billion, have been completed, while three remain under development. Sumant More, the CEO of NMSCDCL, confirmed that 15 of the completed projects had already been handed over to NMC, with the remaining three, including Goda Park and roadworks in gaothan areas, in the process of being transferred. Among the pending projects, two are progressing steadily and are expected to be completed by the end of April, while the third is slated for completion by December. More assured that these projects will be formally handed over to NMC, ensuring their continued operation and maintenance. The Smart City Mission was originally designed as a five-year initiative, scheduled to conclude in June 2022. However, the central government extended the program until March 31 of this year, providing additional time for the completion of ongoing projects. The total estimated cost for the 21 smart city projects is Rs 11.22 billion, including Rs 1.75 billion for two projects—streetlight installation and solar panel implementation—executed under the public-private partnership (PPP) model. The remaining 19 projects, valued at Rs 9.46 billion, have been financed by the smart city corporation. NMSCDCL has received Rs 8.97 billion in funding from the central and state governments, as well as from NMC. This includes Rs 4.65 billion from the central government, Rs 2.32 billion from the state government, and Rs 2 billion from NMC. However, NMC has yet to release Rs 480.51 million in outstanding funds. To date, NMSCDCL has spent Rs 6.50 billion on various smart city initiatives. Despite the progress made, the timely completion of the remaining projects remains a priority. The transfer of completed projects to NMC will ensure their continued management and maintenance, reinforcing the city’s commitment to urban development, technological advancement, improved transportation networks, and enhanced infrastructure. News source: Prop News Time

Next Story
Resources

Skyview by Empyrean is Making Benchmarks in the Indian Ropeway Industry

FIL Industries Private Limited, the parent company of Empyrean Skyview Projects that pioneered ropeway mobility solutions in India with Jammu’s Skyview Gondola, is currently developing the Dehradun-Mussoorie ropeway and is on track to complete Phase I by September 2026. The ropeway is set to be India’s longest passenger aerial monocable covering 5.8 km between the foothills of Dehradun in Purkulgam and MDDA taxi stand in the hills of Mussoorie in just under 20 minutes. The firm pioneered green mobility solutions in India with the development of the flagship Skyview Gondola in Jam..

Next Story
Technology

Creativity is for Humans, Productivity is for Robots!

On most construction sites, the rhythm of progress is measured by the clang of steel, the hum of machinery and the sweat of thousands. But increasingly, new sounds are entering the mix: the quiet efficiency of algorithms, the hum of drones overhead, and the precision of robotic arms at work. Behind the concrete and cables, an invisible force is taking hold: data. It is turning blueprints into living simulations, managing fleets of machines, and helping engineers make decisions before a single brick is laid. This is not the construction of tomorrow; it is the architecture of today – built on ..

Next Story
Infrastructure Urban

Bhartiya Urban Unveils ‘Bhartiya Converge’ GCC Enablement Platform

Bhartiya Urban has launched Bhartiya Converge, its latest business venture designed to become India’s premier platform for enabling Global Capability Centres (GCCs). The initiative offers an integrated ecosystem aimed at helping global clients gain a competitive edge in today’s rapidly evolving business environment. Focused on enhancing turnaround time and operational efficiencies, the company seeks to deliver better business outcomes powered by top-tier talent. Bhartiya Converge presents a customised and integrated suite of microservices that addresses the nuanced and evolving operational..

Advertisement

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Advertisement

Talk to us?