Over 400 Mumbai infra projects hit by cost and time overruns
Over 400 Mumbai infra projects hit by cost and time overruns
SMART CITIES

Over 400 Mumbai infra projects hit by cost and time overruns

As many as 442 infrastructure projects in Mumbai, each worth Rs 150 crore or more, have taken a hit due to cost overruns of more than Rs 4.34 lakh crore.

All infrastructure projects that are worth Rs 150 crore or more are monitored by the Ministry of Statistics and Programme Implementation. Of a total of 1,671 projects, nearly 442 witnessed cost overruns and 536 have suffered postponement.

The total original cost of implementation of nearly 1,671 projects was calculated as Rs 21.21 lakh crore. The expected completion cost is Rs 25.56 lakh crore. It reflects the overall cost overruns of nearly Rs 4.34 lakh crore. It is 20.49% of its original cost.

During November 2020, the expenditure incurred on these projects was Rs 11.94 lakh crore, which is 46.71% of the anticipated costs.

If a delay is calculated based on the latest schedule of completion, then the number of delayed projects gets reduced to 412. For 942 projects, neither the year of commissioning nor the tentative gestation period has been reported.

Of 536 delayed projects, close to 120 have an overall delta of 1-12 months. Whereas, 13 projects are likely to see 13-24 months. Also, 162 indicate delay for 25-60 months and nearly 120 reflect a delay of 61 months and more. Hence, the average time overrun for 536 delayed projects is 44.15 months.

The reasons behind the time overruns:

  • Delay in tie-up for project financing
  • Delays in finalisation of detailed engineering
  • Change in scope
  • Delay in tendering
  • Ordering and equipment supply
  • Law and order issues
  • Delays in land acquisition
  • Delays in obtaining forest and environmental clearances
  • Lockdown in various states in the country

Various project agencies have not reported revisited cost estimates and commissioning schedules for projects. It indicates the time and cost overrun figures to be under-reported.

Image Source

As many as 442 infrastructure projects in Mumbai, each worth Rs 150 crore or more, have taken a hit due to cost overruns of more than Rs 4.34 lakh crore. All infrastructure projects that are worth Rs 150 crore or more are monitored by the Ministry of Statistics and Programme Implementation. Of a total of 1,671 projects, nearly 442 witnessed cost overruns and 536 have suffered postponement. The total original cost of implementation of nearly 1,671 projects was calculated as Rs 21.21 lakh crore. The expected completion cost is Rs 25.56 lakh crore. It reflects the overall cost overruns of nearly Rs 4.34 lakh crore. It is 20.49% of its original cost. During November 2020, the expenditure incurred on these projects was Rs 11.94 lakh crore, which is 46.71% of the anticipated costs. If a delay is calculated based on the latest schedule of completion, then the number of delayed projects gets reduced to 412. For 942 projects, neither the year of commissioning nor the tentative gestation period has been reported. Of 536 delayed projects, close to 120 have an overall delta of 1-12 months. Whereas, 13 projects are likely to see 13-24 months. Also, 162 indicate delay for 25-60 months and nearly 120 reflect a delay of 61 months and more. Hence, the average time overrun for 536 delayed projects is 44.15 months. The reasons behind the time overruns: Delay in tie-up for project financing Delays in finalisation of detailed engineering Change in scope Delay in tendering Ordering and equipment supply Law and order issues Delays in land acquisition Delays in obtaining forest and environmental clearances Lockdown in various states in the country Various project agencies have not reported revisited cost estimates and commissioning schedules for projects. It indicates the time and cost overrun figures to be under-reported. Image Source

Next Story
Infrastructure Transport

Vishnu Prakash R Punglia Wins Rs.90.89 Crore Railway Contract

Vishnu Prakash R Punglia Ltd. has announced the receipt of a significant letter of acceptance (LoA) from the Office of DYCE-C-BKN-ENGINEERING, North Western Railway, Bikaner. The contract, valued at ?908.9 million, encompasses a range of infrastructure works between Sadulpur and Churu as part of the Churu-Sadulpur Doubling Project. The project involves extensive earthwork including filling and cutting in formation, blanketing, construction of minor bridges, low-height subways (LHS), foot overbridges (FOB), platforms and platform shelters, as well as S&T structures, cable ducting, and other an..

Next Story
Infrastructure Urban

India and US to Lead Critical Tech Development, Says NSA Ajit Doval

India and the United States must stay at the forefront of developing critical technologies to protect their value systems and strategic interests, National Security Advisor Ajit Doval stated. Doval made these remarks alongside his American counterpart, Jake Sullivan, during the iCET (India-US initiative on Critical and Emerging Technology) industry roundtable hosted by the Confederation of Indian Industry (CII). Doval's comments followed the unveiling of a series of transformative initiatives aimed at deepening India-US cooperation in areas such as artificial intelligence, semiconductors, cri..

Next Story
Infrastructure Energy

NTPC Partners with Macawber Beekay for Green Coal Projects in India

State-owned power giant NTPC has enlisted Macawber Beekay to supply green coal, derived from municipal solid waste (MSW), to reduce carbon emissions in electricity generation, announced the waste-to-energy firm. Macawber Beekay Private Ltd (MBL) revealed in a statement that it has secured three NTPC Green Coal projects located in Noida (Uttar Pradesh), Bhopal (Madhya Pradesh), and Hubbali (Karnataka). Green coal, a type of charcoal produced through the thermal treatment process of torrefaction in an oxygen-deficient environment, will be manufactured in three new units. These units will treat 9..

Hi There!

"Now get regular updates from CW Magazine on WhatsApp!

Join the CW WhatsApp channel for the latest news, industry events, expert insights, and project updates from the construction and infrastructure industry.

Click the link below to join"

+91 81086 03000

Join us Telegram