+
Puthur Smart City mall in Trichy progresses at snail’s pace
SMART CITIES

Puthur Smart City mall in Trichy progresses at snail’s pace

The construction of an air-conditioned mall in Puthur under the Smart Cities Mission is progressing at a snail’s pace, with the Trichy Corporation completing only 60% of the civil work so far. The timely commissioning of the project seems to be an uphill task as funding under the Smart Cities programme is to cease by March 2023.

As per the design, the Rs 202-million mall will have three floors with basement parking. Of the three floors, structural work has been completed only on the first floor. Electrical works and façade development still look far off. This has raised doubts whether the project could be commissioned before the fund lapses.

The mall was designed to have a 106,000 sq ft built-up area including office space, commercial outlets, food courts and movie halls on the third floor.

The delay in commissioning the project means the liveability parameters of the city, which is crucial to attract investments in the IT sector, are lagging.

Capitalising on the demand, private mall projects have come up along the Trichy-Chennai National Highway and near the international airport.

“Shortage of raw materials during the Covid-19 pandemic and fund crunch were stated as reasons for the delay. We have told the contractors to expedite the pending work before March 2023,” a senior corporation official said.

Preliminary work on the mall was launched in December 2019. The major work on the mall commenced in October 2020.

See also:
Nagaland Smart City and commercial capital rank bottom ten
What are the implications of increased GST on Smart Cities?


The construction of an air-conditioned mall in Puthur under the Smart Cities Mission is progressing at a snail’s pace, with the Trichy Corporation completing only 60% of the civil work so far. The timely commissioning of the project seems to be an uphill task as funding under the Smart Cities programme is to cease by March 2023. As per the design, the Rs 202-million mall will have three floors with basement parking. Of the three floors, structural work has been completed only on the first floor. Electrical works and façade development still look far off. This has raised doubts whether the project could be commissioned before the fund lapses. The mall was designed to have a 106,000 sq ft built-up area including office space, commercial outlets, food courts and movie halls on the third floor. The delay in commissioning the project means the liveability parameters of the city, which is crucial to attract investments in the IT sector, are lagging. Capitalising on the demand, private mall projects have come up along the Trichy-Chennai National Highway and near the international airport. “Shortage of raw materials during the Covid-19 pandemic and fund crunch were stated as reasons for the delay. We have told the contractors to expedite the pending work before March 2023,” a senior corporation official said. Preliminary work on the mall was launched in December 2019. The major work on the mall commenced in October 2020. See also: Nagaland Smart City and commercial capital rank bottom tenWhat are the implications of increased GST on Smart Cities?

Related Stories

Gold Stories

Next Story
Infrastructure Transport

97 Per Cent Of Rongjeng-Mangsang-Adokgre Road Nears Completion

Deputy Chief Minister in-charge of public works Prestone Tynsong said in Shillong on 26 August that 97 per cent physical progress had been achieved on the ongoing Rongjeng-Mangsang-Adokgre road being constructed under the Non-Lapsable Central Pool of Resources (NLCPR). He noted the project was sanctioned in 2017 and that the stipulated time for completion had been 24 months from issue of the final work order. The deputy chief minister informed the assembly that the government had decided to include the remaining work under a World Bank project. In reply to a query from Rongjeng MLA Jim M Sangm..

Next Story
Infrastructure Transport

First TBM Starts Digging Five Point Three Kilometre Tunnel Under SGNP

The Goregaon-Mulund Link Road (GMLR) Phase three (B) project has reached a key milestone as the first tunnel boring machine (TBM) began excavation of the first of two tunnels beneath the Sanjay Gandhi National Park (SGNP). The machine, named Tulsi, started cutting a five point three kilometre bore that will link Dadasaheb Phalke Chitranagari in Goregaon East with Amar Nagar in Mulund West. Officials issued a statement noting the commencement of tunnelling work under the protected green belt. The twin tunnels are being constructed using mechanised tunnelling methods that aim to limit surface di..

Next Story
Infrastructure Transport

UP Approves Two Expressways And Rs 240 bn Infrastructure Push

The Uttar Pradesh Cabinet approved a series of infrastructure and industrial investment proposals totalling Rs 240 billion (Rs 240 bn), including two major expressway projects, a manufacturing and logistics cluster in Sultanpur and incentives for 11 industrial projects across the state. The decisions, taken at a meeting chaired by Chief Minister Yogi Adityanath, underline the state government’s focus on expanding road connectivity around emerging industrial hubs while attracting manufacturing investment to districts beyond major urban centres. The approvals cover both greenfield expressway c..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

SPECIAL OFFER
QR Code