Puthur Smart City mall in Trichy progresses at snail’s pace
SMART CITIES

Puthur Smart City mall in Trichy progresses at snail’s pace

The construction of an air-conditioned mall in Puthur under the Smart Cities Mission is progressing at a snail’s pace, with the Trichy Corporation completing only 60% of the civil work so far. The timely commissioning of the project seems to be an uphill task as funding under the Smart Cities programme is to cease by March 2023.

As per the design, the Rs 202-million mall will have three floors with basement parking. Of the three floors, structural work has been completed only on the first floor. Electrical works and façade development still look far off. This has raised doubts whether the project could be commissioned before the fund lapses.

The mall was designed to have a 106,000 sq ft built-up area including office space, commercial outlets, food courts and movie halls on the third floor.

The delay in commissioning the project means the liveability parameters of the city, which is crucial to attract investments in the IT sector, are lagging.

Capitalising on the demand, private mall projects have come up along the Trichy-Chennai National Highway and near the international airport.

“Shortage of raw materials during the Covid-19 pandemic and fund crunch were stated as reasons for the delay. We have told the contractors to expedite the pending work before March 2023,” a senior corporation official said.

Preliminary work on the mall was launched in December 2019. The major work on the mall commenced in October 2020.

See also:
Nagaland Smart City and commercial capital rank bottom ten
What are the implications of increased GST on Smart Cities?


The construction of an air-conditioned mall in Puthur under the Smart Cities Mission is progressing at a snail’s pace, with the Trichy Corporation completing only 60% of the civil work so far. The timely commissioning of the project seems to be an uphill task as funding under the Smart Cities programme is to cease by March 2023. As per the design, the Rs 202-million mall will have three floors with basement parking. Of the three floors, structural work has been completed only on the first floor. Electrical works and façade development still look far off. This has raised doubts whether the project could be commissioned before the fund lapses. The mall was designed to have a 106,000 sq ft built-up area including office space, commercial outlets, food courts and movie halls on the third floor. The delay in commissioning the project means the liveability parameters of the city, which is crucial to attract investments in the IT sector, are lagging. Capitalising on the demand, private mall projects have come up along the Trichy-Chennai National Highway and near the international airport. “Shortage of raw materials during the Covid-19 pandemic and fund crunch were stated as reasons for the delay. We have told the contractors to expedite the pending work before March 2023,” a senior corporation official said. Preliminary work on the mall was launched in December 2019. The major work on the mall commenced in October 2020. See also: Nagaland Smart City and commercial capital rank bottom tenWhat are the implications of increased GST on Smart Cities?

Next Story
Equipment

Handling concrete better

Efficiently handling the transportation and placement of concrete is essential to help maintain the quality of construction, meet project timelines by minimising downtimes, and reduce costs – by 5 to 15 per cent, according to Sandeep Jain, Director, Arkade Developers. CW explores what the efficient handling of concrete entails.Select wellFirst, a word on choosing the right equipment, such as a mixer with a capacity aligned to the volume required onsite, from Vaibhav Kulkarni, Concrete Expert. “An overly large mixer will increase the idle time (and cost), while one that ..

Next Story
Real Estate

Elevated floors!

Raised access flooring, also called false flooring, is a less common interiors feature than false ceilings, but it has as many uses – if not more.A raised floor is a modular panel installed above the structural floor. The space beneath the raised flooring is typically used to accommodate utilities such as electrical cables, plumbing and HVAC systems. And so, raised flooring is usually associated with buildings with heavy cabling and precise air distribution needs, such as data centres.That said, CW interacted with designers and architects and discovered that false flooring can come in handy ..

Next Story
Infrastructure Urban

The Variation Challenge

A variation or change in scope clause is defined in construction contracts to take care of situations arising from change in the defined scope of work. Such changes may arise due to factors such as additions or deletions in the scope of work, modifications in the type, grade or specifications of materials, alterations in specifications or drawings, and acts or omissions of other contractors. Further, ineffective planning, inadequate investigations or surveys and requests from the employer or those within the project’s area of influence can contribute to changes in the scope of work. Ext..

Advertisement

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Advertisement

Talk to us?