Trichy Corporation’s 5 smart city projects drags beyond deadlines
SMART CITIES

Trichy Corporation’s 5 smart city projects drags beyond deadlines

At least five smart cities mission projects started by Trichy Corporation face a test of survival due to a fund crunch with the construction work dragging on for three years now.

As the work on the two multi-level car parking projects has not even been completed even up to 70%, the corporation is under stress to complete the remaining work swiftly to avail budget before getting it lapsed.

Among the projects stalled by the corporation were the Multi-Level Car Parking (MLCP) on West Boulevard Road, Purathana Park near Rockfort, the vegetable market-cum-MLCP on Kaliammankoil Road near Chathiram bus stand, and an air-conditioned mall at Puthur.

Even as the initial work on the MLCP on the West Boulevard Road began in September 2019, the urban local body could achieve only 62% of the total work. The MLCP was expected to be completed by the last quarter of 2021.

The Purathana park on Butterworth Road, one of the oldest Smart cities mission proposals by the Trichy civic body, is still staggering towards completion. Launched in December 2019, only 60% of the construction work was completed.

A senior official with Trichy Corporation said that they had outsourced a few artistic structures in Purathana Park from state-run Poompuhar handicrafts, and they deferred the delivery. The contractor was urged to expedite the work.

Even as the MLCP project officially took off in August 2020, another MLCP project with a vegetable market on Kaliammankoil Street near the Chathiram bus stand has finished only 50% of the civil work.

Only 44% of work on the Puthur commercial market cum mall has been finished. The mall was expected to be completed by December 2022. Even though the Thillai Nayagam ghats redevelopment civil work was launched in 2019, the work has not made any progress.

The senior official said that the pandemic and lockdowns slowed down the work. As Smart cities mission projects of Trichy will get lapsed after March 2023, the works should be completed before the deadline.

Image Source

At least five smart cities mission projects started by Trichy Corporation face a test of survival due to a fund crunch with the construction work dragging on for three years now. As the work on the two multi-level car parking projects has not even been completed even up to 70%, the corporation is under stress to complete the remaining work swiftly to avail budget before getting it lapsed. Among the projects stalled by the corporation were the Multi-Level Car Parking (MLCP) on West Boulevard Road, Purathana Park near Rockfort, the vegetable market-cum-MLCP on Kaliammankoil Road near Chathiram bus stand, and an air-conditioned mall at Puthur. Even as the initial work on the MLCP on the West Boulevard Road began in September 2019, the urban local body could achieve only 62% of the total work. The MLCP was expected to be completed by the last quarter of 2021. The Purathana park on Butterworth Road, one of the oldest Smart cities mission proposals by the Trichy civic body, is still staggering towards completion. Launched in December 2019, only 60% of the construction work was completed. A senior official with Trichy Corporation said that they had outsourced a few artistic structures in Purathana Park from state-run Poompuhar handicrafts, and they deferred the delivery. The contractor was urged to expedite the work. Even as the MLCP project officially took off in August 2020, another MLCP project with a vegetable market on Kaliammankoil Street near the Chathiram bus stand has finished only 50% of the civil work. Only 44% of work on the Puthur commercial market cum mall has been finished. The mall was expected to be completed by December 2022. Even though the Thillai Nayagam ghats redevelopment civil work was launched in 2019, the work has not made any progress. The senior official said that the pandemic and lockdowns slowed down the work. As Smart cities mission projects of Trichy will get lapsed after March 2023, the works should be completed before the deadline. Image Source

Related Stories

Gold Stories

Next Story
Infrastructure Urban

KONE Opens India's First Digital Experience Centre in Pune

KONE, a global elevator and escalator manufacturer, has inaugurated its first Digital Experience Centre (DEC) in India, located in Pune. The facility aims to showcase how artificial intelligence (AI), connectivity and data-driven technologies can enhance customer experiences and improve building operations.The centre was inaugurated by Jussi Herlin, Executive Vice Chair, KONE Corporation; Philippe Delorme, President and CEO, KONE; and Nandan Nilekani, Co-founder and Chairman of the Board, Infosys.Designed as an interactive customer environment, the facility demonstrates digital solutions cover..

Next Story
Infrastructure Urban

CII GreenCo Launches Circularity Guidelines for Indian Industry

The Confederation of Indian Industry (CII) GreenCo Council has launched the CII GreenCo Circularity Guidelines – Pilot Version at the 17th CII GreenCo Waste & Resource Management Summit 2026 in Chennai. The initiative aims to strengthen resource efficiency, waste reduction and circular economy practices across Indian manufacturing and process industries.The guidelines introduce a structured framework with circularity indices covering raw materials, consumables, packaging and other resource inputs. These indicators will help industries assess existing practices, identify opportunities to ..

Next Story
Infrastructure Energy

Global Electronics Association Launches IPC-1783-CO2E Standard

The Global Electronics Association has introduced IPC-1783-CO2E, a new international standard aimed at improving consistency, transparency and comparability in product carbon footprint reporting across the electronics manufacturing industry.The standard, titled International Standard for Data Collection and Reporting of CO2 Equivalent (CO2e) Emissions for the Electronics Manufacturing Supply Chain, provides industry-specific guidance for collecting, estimating and reporting carbon emissions data.With increasing regulatory requirements and customer expectations, electronics manufacturers face c..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

SPECIAL OFFER
QR Code