Bombay HC to monitor Aurangabad water supply project progress
WATER & WASTE

Bombay HC to monitor Aurangabad water supply project progress

The Aurangabad bench of Bombay high court will now be monitoring the progress of the upcoming Aurangabad water supply project.

While listening to a plea filed by affected residents, the two-member bench of Justice Ravindra Ghuge and Justice SG Dighe said that the petition concerned would be taken up for hearing once in two weeks to monitor the progress of the new pipeline.

The court observed in an order dated April 20 that there is no dispute that in most of the Aurangabad localities, drinking water is supplied once in seven days and in some areas, once in eight days.

The bench said there is an acute shortage in water supply, mainly during summer, though there is adequate water storage in the Jayakwadi irrigation project due to the lack of a proper water distribution system.

While only the Aurangabad Municipal Corporation (AMC) was made a party in the case earlier, the court asked for making the ministry of environment, forest and climate change (MoEFCC), Maharashtra Jeevan Pradhikaran (MJP), state urban development department, state forest department, and National Highway Authority of India (NHAI), among others as.

To begin with, the court has directed the ministry of environment to approve the pump house construction at the Jayakwadi project, which also houses a bird sanctuary, before May 31.

Immediately the MJP would begin the pump house construction, the court said, asking the MJP to create a team of officers who would oversee the progress being made under the water supply project and record the daily progress details for production before the court as and when directed.

The Rs 1,680 crore new water pipeline scheme for Aurangabad has still not achieved the expected momentum despite one-third of the specified period being over.

Advocate Sambhaji Tope while representing the AMC before the court, said the work order for the new water supply project was issued in February 2021, and the expected time within which the project would be finished is about three years.

Image Source

Also read: SPML Infra receives Rs 1157.08 cr of Isarda water supply project

The Aurangabad bench of Bombay high court will now be monitoring the progress of the upcoming Aurangabad water supply project. While listening to a plea filed by affected residents, the two-member bench of Justice Ravindra Ghuge and Justice SG Dighe said that the petition concerned would be taken up for hearing once in two weeks to monitor the progress of the new pipeline. The court observed in an order dated April 20 that there is no dispute that in most of the Aurangabad localities, drinking water is supplied once in seven days and in some areas, once in eight days. The bench said there is an acute shortage in water supply, mainly during summer, though there is adequate water storage in the Jayakwadi irrigation project due to the lack of a proper water distribution system. While only the Aurangabad Municipal Corporation (AMC) was made a party in the case earlier, the court asked for making the ministry of environment, forest and climate change (MoEFCC), Maharashtra Jeevan Pradhikaran (MJP), state urban development department, state forest department, and National Highway Authority of India (NHAI), among others as. To begin with, the court has directed the ministry of environment to approve the pump house construction at the Jayakwadi project, which also houses a bird sanctuary, before May 31. Immediately the MJP would begin the pump house construction, the court said, asking the MJP to create a team of officers who would oversee the progress being made under the water supply project and record the daily progress details for production before the court as and when directed. The Rs 1,680 crore new water pipeline scheme for Aurangabad has still not achieved the expected momentum despite one-third of the specified period being over. Advocate Sambhaji Tope while representing the AMC before the court, said the work order for the new water supply project was issued in February 2021, and the expected time within which the project would be finished is about three years. Image Source Also read: SPML Infra receives Rs 1157.08 cr of Isarda water supply project

Next Story
Infrastructure Urban

TBO Tek Q2 Profit Climbs 12%, Revenue Surges 26% YoY

TBO Tek Limited one of the world’s largest travel distribution platforms, reported a solid performance for Q2 FY26 with a 26 per cent year-on-year increase in revenue to Rs 5.68 billion, reflecting broad-based growth and improving profitability.The company recorded a Gross Transaction Value (GTV) of Rs 8,901 crore, up 12 per cent YoY, driven by strong performance across Europe, MEA, and APAC regions. Adjusted EBITDA before acquisition-related costs stood at Rs 1.04 billion, up 16 per cent YoY, translating into an 18.32 per cent margin compared to 16.56 per cent in Q1 FY26. Profit after tax r..

Next Story
Infrastructure Energy

Northern Graphite, Rain Carbon Secure R&D Grant for Greener Battery Materials

Northern Graphite Corporation and Rain Carbon Canada Inc, a subsidiary of Rain Carbon Inc, have jointly received up to C$860,000 (€530,000) in funding under the Canada–Germany Collaborative Industrial Research and Development Programme to develop sustainable battery anode materials.The two-year, C$2.2 million project aims to transform natural graphite processing by-products into high-performance, battery-grade anode material (BAM). Supported by the National Research Council of Canada Industrial Research Assistance Programme (NRC IRAP) and Germany’s Federal Ministry for Economic Affairs a..

Next Story
Infrastructure Urban

Antony Waste Q2 Revenue Jumps 16%; Subsidiary Wins Rs 3,200 Cr WtE Projects

Antony Waste Handling Cell Limited (AWHCL), a leading player in India’s municipal solid waste management sector, announced a 16 per cent year-on-year increase in total operating revenue to Rs 2.33 billion for Q2 FY26. The growth was driven by higher waste volumes, escalated contracts, and strong operational execution.EBITDA rose 18 per cent to Rs 570 million, with margins steady at 21.6 per cent, while profit after tax stood at Rs 173 million, up 13 per cent YoY. Revenue from Municipal Solid Waste Collection and Transportation (MSW C&T) reached Rs 1.605 billion, and MSW Processing re..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement