BMC Ropes in New Contractors to Speed Up Mithi River Desilting Work
WATER & WASTE

BMC Ropes in New Contractors to Speed Up Mithi River Desilting Work

The BMC has appointed two new contractors to complete the Mithi River desilting project after missing the deadline twice. The project had experienced significant delays due to an ongoing police investigation into alleged irregularities with previous contractors. The Mithi River, a key stormwater drain in Mumbai, plays a crucial role in mitigating urban flooding. Desilting began in April as part of the city's pre-monsoon disaster preparedness.

Following the 2005 floods, the BMC prioritised regular maintenance of the river as part of its flood mitigation strategy. The desilting project is divided into three phases, with a total estimated cost of Rs 1 billion between 2025 and 2027.

The project, however, faced substantial setbacks due to the police probe into a contractor scam and the blacklisting of another firm for malpractice. Additionally, heavy rainfall on May 26 further delayed progress as machinery could not access water bodies for several days. Consequently, the BMC extended the deadline to June 7 and appointed two new contractors to accelerate the completion within the next 15 days.

Out of the 2.14 lakh metric tonnes (MT) of silt targeted for removal from the Mithi River, 1.36 lakh MT has been cleared so far. In total, 8.24 lakh MT has been removed from a target of 9.69 lakh MT. Desilting in the island city and the eastern and western suburbs is 100 per cent complete, while work on minor drains is 75.97 per cent complete, with 3.01 lakh MT removed out of a target of 3.96 lakh MT.


News source: The Free Press Journal

The BMC has appointed two new contractors to complete the Mithi River desilting project after missing the deadline twice. The project had experienced significant delays due to an ongoing police investigation into alleged irregularities with previous contractors. The Mithi River, a key stormwater drain in Mumbai, plays a crucial role in mitigating urban flooding. Desilting began in April as part of the city's pre-monsoon disaster preparedness.Following the 2005 floods, the BMC prioritised regular maintenance of the river as part of its flood mitigation strategy. The desilting project is divided into three phases, with a total estimated cost of Rs 1 billion between 2025 and 2027.The project, however, faced substantial setbacks due to the police probe into a contractor scam and the blacklisting of another firm for malpractice. Additionally, heavy rainfall on May 26 further delayed progress as machinery could not access water bodies for several days. Consequently, the BMC extended the deadline to June 7 and appointed two new contractors to accelerate the completion within the next 15 days.Out of the 2.14 lakh metric tonnes (MT) of silt targeted for removal from the Mithi River, 1.36 lakh MT has been cleared so far. In total, 8.24 lakh MT has been removed from a target of 9.69 lakh MT. Desilting in the island city and the eastern and western suburbs is 100 per cent complete, while work on minor drains is 75.97 per cent complete, with 3.01 lakh MT removed out of a target of 3.96 lakh MT.News source: The Free Press Journal

Next Story
Infrastructure Urban

Continental Expands Assistive ‘OnBoard’ Tech to 100+ BMTC Buses

Continental India, in partnership with the Indian Institute of Technology Delhi, Raised Lines Foundation, and Bangalore Metropolitan Transport Corporation (BMTC), has expanded its smart assistive mobility solution ‘OnBoard’ across more than 100 BMTC buses in Bengaluru. Initially piloted on 25 buses, the solution is now set to be installed in 500 buses by year-end.The expansion was officially announced at the BMTC Central Office during a press conference attended by Shri Ramalinga Reddy, Hon’ble Transport Minister of Karnataka.‘OnBoard’ is a bus-mounted assistive technology designed t..

Next Story
Infrastructure Energy

Himadri PAT Rises 48% in Q1 Amid Global Battery Push

Himadri Speciality Chemical Ltd reported its highest-ever quarterly EBITDA of Rs 234 crore and PAT of Rs 183 crore for Q1 FY26, with profitability up 48% YoY. Revenue stood at Rs 1,100 crore.CMD Anurag Choudhary attributed the gains to operational efficiencies, improved yields, and focus on high-value battery materials. Himadri also revived Birla Tyres with a new brand identity and plans a multi-platform marketing campaign.The firm signed a licensing deal with Australia’s Sicona for SiCx® anode tech, enabling localisation and commercialisation in India. Himadri also invested USD 4.43 millio..

Next Story
Infrastructure Urban

Covestro Develops Fire-Safe Foam for EV Battery Safety

Covestro has introduced Baysafe® BEF, a new flame-retardant polyurethane foam designed to enhance battery safety in EVs and energy storage systems. The foam minimises thermal propagation between cells, reducing fire risk.The launch aligns with China’s GB 38031-2025 battery regulation, effective from July 2026, which sets stringent safety standards. "This innovation represents a significant step toward enabling sustainable mobility through enhanced safety," said Akhil Singhania, Global Head of PU Specialties at Covestro.The foam's lightweight structure and fire resistance meet the needs of g..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Talk to us?