BMC Ropes in New Contractors to Speed Up Mithi River Desilting Work
WATER & WASTE

BMC Ropes in New Contractors to Speed Up Mithi River Desilting Work

The BMC has appointed two new contractors to complete the Mithi River desilting project after missing the deadline twice. The project had experienced significant delays due to an ongoing police investigation into alleged irregularities with previous contractors. The Mithi River, a key stormwater drain in Mumbai, plays a crucial role in mitigating urban flooding. Desilting began in April as part of the city's pre-monsoon disaster preparedness.

Following the 2005 floods, the BMC prioritised regular maintenance of the river as part of its flood mitigation strategy. The desilting project is divided into three phases, with a total estimated cost of Rs 1 billion between 2025 and 2027.

The project, however, faced substantial setbacks due to the police probe into a contractor scam and the blacklisting of another firm for malpractice. Additionally, heavy rainfall on May 26 further delayed progress as machinery could not access water bodies for several days. Consequently, the BMC extended the deadline to June 7 and appointed two new contractors to accelerate the completion within the next 15 days.

Out of the 2.14 lakh metric tonnes (MT) of silt targeted for removal from the Mithi River, 1.36 lakh MT has been cleared so far. In total, 8.24 lakh MT has been removed from a target of 9.69 lakh MT. Desilting in the island city and the eastern and western suburbs is 100 per cent complete, while work on minor drains is 75.97 per cent complete, with 3.01 lakh MT removed out of a target of 3.96 lakh MT.


News source: The Free Press Journal

The BMC has appointed two new contractors to complete the Mithi River desilting project after missing the deadline twice. The project had experienced significant delays due to an ongoing police investigation into alleged irregularities with previous contractors. The Mithi River, a key stormwater drain in Mumbai, plays a crucial role in mitigating urban flooding. Desilting began in April as part of the city's pre-monsoon disaster preparedness.Following the 2005 floods, the BMC prioritised regular maintenance of the river as part of its flood mitigation strategy. The desilting project is divided into three phases, with a total estimated cost of Rs 1 billion between 2025 and 2027.The project, however, faced substantial setbacks due to the police probe into a contractor scam and the blacklisting of another firm for malpractice. Additionally, heavy rainfall on May 26 further delayed progress as machinery could not access water bodies for several days. Consequently, the BMC extended the deadline to June 7 and appointed two new contractors to accelerate the completion within the next 15 days.Out of the 2.14 lakh metric tonnes (MT) of silt targeted for removal from the Mithi River, 1.36 lakh MT has been cleared so far. In total, 8.24 lakh MT has been removed from a target of 9.69 lakh MT. Desilting in the island city and the eastern and western suburbs is 100 per cent complete, while work on minor drains is 75.97 per cent complete, with 3.01 lakh MT removed out of a target of 3.96 lakh MT.News source: The Free Press Journal

Related Stories

Gold Stories

Next Story
Resources

Schindler named among Forbes’ World’s Best Employers 2026

Schindler has been named among Forbes’ World’s Best Employers 2026, a global ranking recognising companies for their workplace environments.Compiled by Forbes in partnership with Statista, the ranking is based on independent employee feedback, including whether employees would recommend their organisation to friends and family.The company said the recognition reflected its focus on creating a workplace where employees can develop their expertise and build careers. ..

Next Story
Infrastructure Urban

India needs an export-execution mindset: Vishesh Jain

Interview with Vishesh Jain, Founder & CEO, EximpleWhat gaps in India’s global trade ecosystem led you to build Eximple, and what problem did you see businesses struggling with most?Eximple came out of a problem that all three founders had seen from different choke points in the trade ecosystem. India has millions of MSMEs and manufacturers, and many of them can make products that are genuinely competitive on quality. Yet only a small fraction is able to build meaningful international businesses. In our experience, the gap is usually not manufacturing capability; it is the ability to exe..

Next Story
Building Material

Nuvoco reports 13.5% revenue growth in Q2 FY27

Nuvoco Vistas Corp. Ltd. reported consolidated revenue of Rs 27.9 billion for Q2 FY27, up 13.5% year on year. Cement sales volume rose 9% to 4.7 million tonnes (MMT), while EBITDA increased 11% to Rs 4.11 billion.The company said it began its cement operations in 2014 with a 2.3 MMT per annum (MMTPA) operation at Nimbol. It now aims to reach 35 MMTPA of cement capacity by FY28, nearly 15 times its initial capacity. Its portfolio spans cement, ready-mix concrete and modern building materials.On sustainability and cost efficiency, Nuvoco partnered with CleanMax for a 46.4 MW wind-solar hybrid re..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

SPECIAL OFFER
QR Code