BMC Ropes in New Contractors to Speed Up Mithi River Desilting Work
WATER & WASTE

BMC Ropes in New Contractors to Speed Up Mithi River Desilting Work

The BMC has appointed two new contractors to complete the Mithi River desilting project after missing the deadline twice. The project had experienced significant delays due to an ongoing police investigation into alleged irregularities with previous contractors. The Mithi River, a key stormwater drain in Mumbai, plays a crucial role in mitigating urban flooding. Desilting began in April as part of the city's pre-monsoon disaster preparedness.

Following the 2005 floods, the BMC prioritised regular maintenance of the river as part of its flood mitigation strategy. The desilting project is divided into three phases, with a total estimated cost of Rs 1 billion between 2025 and 2027.

The project, however, faced substantial setbacks due to the police probe into a contractor scam and the blacklisting of another firm for malpractice. Additionally, heavy rainfall on May 26 further delayed progress as machinery could not access water bodies for several days. Consequently, the BMC extended the deadline to June 7 and appointed two new contractors to accelerate the completion within the next 15 days.

Out of the 2.14 lakh metric tonnes (MT) of silt targeted for removal from the Mithi River, 1.36 lakh MT has been cleared so far. In total, 8.24 lakh MT has been removed from a target of 9.69 lakh MT. Desilting in the island city and the eastern and western suburbs is 100 per cent complete, while work on minor drains is 75.97 per cent complete, with 3.01 lakh MT removed out of a target of 3.96 lakh MT.


News source: The Free Press Journal

The BMC has appointed two new contractors to complete the Mithi River desilting project after missing the deadline twice. The project had experienced significant delays due to an ongoing police investigation into alleged irregularities with previous contractors. The Mithi River, a key stormwater drain in Mumbai, plays a crucial role in mitigating urban flooding. Desilting began in April as part of the city's pre-monsoon disaster preparedness.Following the 2005 floods, the BMC prioritised regular maintenance of the river as part of its flood mitigation strategy. The desilting project is divided into three phases, with a total estimated cost of Rs 1 billion between 2025 and 2027.The project, however, faced substantial setbacks due to the police probe into a contractor scam and the blacklisting of another firm for malpractice. Additionally, heavy rainfall on May 26 further delayed progress as machinery could not access water bodies for several days. Consequently, the BMC extended the deadline to June 7 and appointed two new contractors to accelerate the completion within the next 15 days.Out of the 2.14 lakh metric tonnes (MT) of silt targeted for removal from the Mithi River, 1.36 lakh MT has been cleared so far. In total, 8.24 lakh MT has been removed from a target of 9.69 lakh MT. Desilting in the island city and the eastern and western suburbs is 100 per cent complete, while work on minor drains is 75.97 per cent complete, with 3.01 lakh MT removed out of a target of 3.96 lakh MT.News source: The Free Press Journal

Next Story
Infrastructure Energy

KEC Secures Rs 10, 380 Mn Substation Order in Saudi Arabia

KEC International Ltd., a global infrastructure EPC major, and an RPG Group company, has secured a new order worth Rs 10,380 million for the Design, Supply and Installation of a 380 kV GIS Substation in Saudi Arabia.Vimal Kejriwal, MD & CEO, KEC International Ltd., commented, “We are delighted with the successive order wins in our T&D business. In a landmark achievement, we have secured our largest ever substation order. This prestigious order in the Middle East has widened our portfolio and strengthened our presence in the region. With this strategic win, our year-to-date or..

Next Story
Infrastructure Urban

Central Bank of India executes first fully digital SCF deal on PSB Xchange

In a major advancement for India’s banking sector, Central Bank of India (CBI) has successfully completed the country’s first fully digital supply chain finance (SCF) transaction on PSB Xchange—a unified multi-lender platform launched by PSB Alliance. PSB Xchange is designed to connect public and private sector banks, NBFCs, and fintechs with corporates and their channel partners to facilitate supply chain finance and small business loans. The transaction marks the first time a fintech-originated corporate lead has been seamlessly processed through the PSB Xchange ecosystem. The lead fl..

Next Story
Infrastructure Energy

Atlanta Electricals secures Rs 1,835 Mn transformer order from BNC Power

Atlanta Electricals Limited (“Atlanta”) has secured an order worth Rs 1,835 million from BNC Power Projects Ltd for the supply of extra high voltage (EHV) transformers and a bus reactor for its Pugal site. The contract includes a mix of 315 MVA, 400 KV and 100 MVA, 132 KV transformers along with a 400 KV bus reactor. The project scope encompasses design, manufacturing, testing, and supply to the project site. Deliveries will be sequenced following engineering and drawing approvals, offering multi-quarter execution visibility and ensuring a steady production run-rate. The order will be ex..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Talk to us?