Contractors as Bankers: The Good, the Bad and the Ugly
ECONOMY & POLICY

Contractors as Bankers: The Good, the Bad and the Ugly

Big-budget construction projects require general contractors that are capable of handling large-scale work with not only an effective project management team, but also a strong financial foundation.

That financial footing is required because general contractors often bankroll a project until there is a positive cash flow. This cash flow helps keep the construction ongoing and the contractual requirements fulfilled.

As projects get underway, however, problems can arise. Issuances of bulletins, unforeseen field conditions and scope changes are some of the key factors that might affect a contractor’s budget in one straight shot. In other words, they are some of the factors that take the project from good to bad—and even ugly.

The “Good”

The ability to support a project financially is considered a benefit to the client and a “positive” to the contractor. It’s one of the critical service factors on which reputations in the industry are built.

This scenario is typical. Early on in a project, the general contractor has strong leverage in the game, perhaps because all the responsibility lies upon the contractor’s company and its subcontractors’ shoulders. From this position in the beginning of a working relationship, payment processes typically go smoothly among all parties. Given this show of accountability by all, the general contractor can assume that things will run smoothly for the long haul and duration of the project.

The “Bad”

Too often, the good period lasts only until this financial strength of the general contractor is tested. At some point along the way, client payments begin to slow, dragging well behind agreed-upon schedules written into the contract. Change orders roll in, but payments for doing the work don’t keep pace.

The bad period begins to take shape, and financing a project is no longer an act of pride but one of necessity. After all, subcontractors and vendors still must be paid. So, they continue to be paid as scheduled, but the general contractor starts to take on a financial burden of the ongoing project.

Worse is in cases where late client payments are made but fall short of the amount billed, with unexpected deductions. The contractor takes on the burden of the late payment. This occurrence qualifies as a “bad” ritual. It signals that leverage on the project has begun to shift in the client’s favor. Projects and relationships can get particularly difficult at this time, and these are all warning signs that should make a contractor cautious about adding more work into the contract—work that would lead to an increase in both responsibility and liability.

A contractor might be taken for granted by the client, which has likely assessed the strong financial footing of the contractor. Work pertaining to change orders and field bulletins may be added into the scope, and expectations are still high that construction will move quickly and that payments will be made to the contractor in a timely manner. This is the best time for the contractor to take all possible proactive measures to legally protect its rights.

The “Ugly”

The situation can now easily progress from “bad” to “ugly.” The entire project is put at risk because of an over-reliance on the contractor’s financial resources. In this example scenario, payments stop completely. The words “liquidated damages” begin to appear in correspondence about the payment that fell short. The general contractor has little to no leverage because it is too late in the timeline of the project, and most of the work on the project has been completed. All change-orders have been completed, but payment on them has not been processed. Subcontractors and vendors continue to bill and drain the contractor’s reserves.

This phase can be attributed to multiple factors such as:

  • a transition in the project-management team on the client’s side;
  • a lack of project funding;
  • a change in the client’s project priorities;
  • decisions made by client’s new team players who lack knowledge pertaining to the history of a project;
  • the client’s biased opinions and manipulation of the contract; and
  • a lack of transparency between the client and the general contractor.
  • At this point, the client is in complete control of the project by holding the contractor’s expenses, and the general contractor has little recourse. If it’s a private project, the contractor might file a mechanics lien against the property if expenses go unpaid; if it’s a public project, a contractor might file a claim against the payment bond. The general contractor’s reputation is tarnished, nonetheless.

    What can be done?

    So how does a general contractor—one whose goal isn’t looking to finance a construction project from start to finish—keep the cash flow in check? How does a general contractor avoid going from good to bad and ugly? In a couple of words: risk management.

    Risk management is especially important when rush projects come out for bidding. Such projects typically lack vision for the end product and, in these cases, a contractor inherits change-order work that, while lucrative, can also turn “ugly” if the situation is not handled well by an effective project-management team.

    There is no rule of thumb on how to overcome these challenges. Every project is unique; each has its own contractual terms and conditions. However, being proactive at every phase can significantly help reduce risks at the contractor’s end.

    All projects go through different challenges but what is critical here is to avoid a project turning ugly. It happens, but it can be mitigated, if not completely avoided, using the following guidelines:

    Gather and define detailed project-scope requirements prior to bidding and ask as many questions as possible at the time of bidding. Do not assume anything.

    Understand and identify the site conditions, as well as the main project drivers.

    Familiarize yourself with the contract in detail, including general conditions. Hire an outside consultant, if needed.

    Document each and every piece of correspondence, even if it is an informal discussion.

    Know each project’s specific schedules, particularly for filing any paperwork such as claims and/or lawsuits, or for notifying the client of unforeseen field conditions. Make sure compensation for change orders includes the time involved to finish change-order work, rather than just labor and materials.

    What starts as a sound working relationship between a general contractor and a client can easily turn sour when there is an over-reliance on the contractor to fund the project. The trick lies in knowing when the tables start to turn and the leverage in the professional relationship starts to shift. At that point, best practices need to be carefully followed in order to save the project and the general contractor’s reputation.

    Written by Nitin Gulati.

    Nitin Gulati, a lead construction project manager, holds a master’s degree in construction engineering and project management from the University of Texas at Austin and a Master of Science in structural engineering from Michigan State University.

    Reprinted from Construction Executive https://constructionexec.com/, August 8, 2020, a publication of Associated Builders and Contractors, copyright 2020. All rights reserved.

    Your next big infra connection is waiting at RAHSTA 2025 – Asia’s Biggest Roads & Highways Expo, Jio World Convention Centre, Mumbai. Don’t miss out!

    Big-budget construction projects require general contractors that are capable of handling large-scale work with not only an effective project management team, but also a strong financial foundation. That financial footing is required because general contractors often bankroll a project until there is a positive cash flow. This cash flow helps keep the construction ongoing and the contractual requirements fulfilled. As projects get underway, however, problems can arise. Issuances of bulletins, unforeseen field conditions and scope changes are some of the key factors that might affect a contractor’s budget in one straight shot. In other words, they are some of the factors that take the project from good to bad—and even ugly. The “Good” The ability to support a project financially is considered a benefit to the client and a “positive” to the contractor. It’s one of the critical service factors on which reputations in the industry are built. This scenario is typical. Early on in a project, the general contractor has strong leverage in the game, perhaps because all the responsibility lies upon the contractor’s company and its subcontractors’ shoulders. From this position in the beginning of a working relationship, payment processes typically go smoothly among all parties. Given this show of accountability by all, the general contractor can assume that things will run smoothly for the long haul and duration of the project. The “Bad” Too often, the good period lasts only until this financial strength of the general contractor is tested. At some point along the way, client payments begin to slow, dragging well behind agreed-upon schedules written into the contract. Change orders roll in, but payments for doing the work don’t keep pace. The bad period begins to take shape, and financing a project is no longer an act of pride but one of necessity. After all, subcontractors and vendors still must be paid. So, they continue to be paid as scheduled, but the general contractor starts to take on a financial burden of the ongoing project. Worse is in cases where late client payments are made but fall short of the amount billed, with unexpected deductions. The contractor takes on the burden of the late payment. This occurrence qualifies as a “bad” ritual. It signals that leverage on the project has begun to shift in the client’s favor. Projects and relationships can get particularly difficult at this time, and these are all warning signs that should make a contractor cautious about adding more work into the contract—work that would lead to an increase in both responsibility and liability. A contractor might be taken for granted by the client, which has likely assessed the strong financial footing of the contractor. Work pertaining to change orders and field bulletins may be added into the scope, and expectations are still high that construction will move quickly and that payments will be made to the contractor in a timely manner. This is the best time for the contractor to take all possible proactive measures to legally protect its rights. The “Ugly” The situation can now easily progress from “bad” to “ugly.” The entire project is put at risk because of an over-reliance on the contractor’s financial resources. In this example scenario, payments stop completely. The words “liquidated damages” begin to appear in correspondence about the payment that fell short. The general contractor has little to no leverage because it is too late in the timeline of the project, and most of the work on the project has been completed. All change-orders have been completed, but payment on them has not been processed. Subcontractors and vendors continue to bill and drain the contractor’s reserves. This phase can be attributed to multiple factors such as: a transition in the project-management team on the client’s side; a lack of project funding; a change in the client’s project priorities; decisions made by client’s new team players who lack knowledge pertaining to the history of a project; the client’s biased opinions and manipulation of the contract; and a lack of transparency between the client and the general contractor. At this point, the client is in complete control of the project by holding the contractor’s expenses, and the general contractor has little recourse. If it’s a private project, the contractor might file a mechanics lien against the property if expenses go unpaid; if it’s a public project, a contractor might file a claim against the payment bond. The general contractor’s reputation is tarnished, nonetheless. What can be done? So how does a general contractor—one whose goal isn’t looking to finance a construction project from start to finish—keep the cash flow in check? How does a general contractor avoid going from good to bad and ugly? In a couple of words: risk management. Risk management is especially important when rush projects come out for bidding. Such projects typically lack vision for the end product and, in these cases, a contractor inherits change-order work that, while lucrative, can also turn “ugly” if the situation is not handled well by an effective project-management team. There is no rule of thumb on how to overcome these challenges. Every project is unique; each has its own contractual terms and conditions. However, being proactive at every phase can significantly help reduce risks at the contractor’s end. All projects go through different challenges but what is critical here is to avoid a project turning ugly. It happens, but it can be mitigated, if not completely avoided, using the following guidelines: Gather and define detailed project-scope requirements prior to bidding and ask as many questions as possible at the time of bidding. Do not assume anything. Understand and identify the site conditions, as well as the main project drivers. Familiarize yourself with the contract in detail, including general conditions. Hire an outside consultant, if needed. Document each and every piece of correspondence, even if it is an informal discussion. Know each project’s specific schedules, particularly for filing any paperwork such as claims and/or lawsuits, or for notifying the client of unforeseen field conditions. Make sure compensation for change orders includes the time involved to finish change-order work, rather than just labor and materials. What starts as a sound working relationship between a general contractor and a client can easily turn sour when there is an over-reliance on the contractor to fund the project. The trick lies in knowing when the tables start to turn and the leverage in the professional relationship starts to shift. At that point, best practices need to be carefully followed in order to save the project and the general contractor’s reputation. Written by Nitin Gulati. Nitin Gulati, a lead construction project manager, holds a master’s degree in construction engineering and project management from the University of Texas at Austin and a Master of Science in structural engineering from Michigan State University. Reprinted from Construction Executive https://constructionexec.com/, August 8, 2020, a publication of Associated Builders and Contractors, copyright 2020. All rights reserved.

    Next Story
    Real Estate

    Vitizen Hotels Signs Deal at Manyata Tech Park

    Vikram Kamats Hospitality, as part of its ongoing expansion in key metropolitan markets, announced that its material subsidiary, Vitizen Hotels, has signed a long-term lease agreement for a 45-key hotel property at Manyata Tech Park, Bengaluru.Strategically located in the city’s prominent IT hub, the property is well-positioned to serve corporate travelers, business professionals, and long-stay guests. The addition aligns with the company’s asset-light growth model, leveraging long-term leases to expand its footprint in high-demand urban markets.The hotel is expected to strengthen the comp..

    Next Story
    Infrastructure Transport

    CONCOR Signs MoU with BPIPL to Operate Container Terminal at Bhavnagar Port

    Container Corporation of India (CONCOR) has signed a Memorandum of Understanding (MoU) with Bhavnagar Port Infrastructure (BPIPL) on September 4, 2025, in New Delhi to operate and maintain the upcoming container terminal at the northside of Bhavnagar Port, Gujarat.BPIPL had earlier entered into an agreement with the Gujarat Maritime Board (GMB) in September 2024 for the port’s development. Under this arrangement, 235 hectares of land has been leased to BPIPL for 30 years, with provision for expansion by an additional 250 hectares.The new terminal is expected to significantly enhance logistic..

    Next Story
    Infrastructure Transport

    Concord Launches India’s First Indigenous Zero-Emission Rail Propulsion

    Concord Control Systems (CCSL), a leader in embedded electronics and critical rail technologies, has announced the development of India’s first fully indigenous zero-emission propulsion system, marking a significant step toward the country’s railway electrification and net-zero goals for 2030.Powered by Lithium Iron Phosphate (LFP) batteries and featuring a DC chopper-based drive, the propulsion system eliminates idling losses common in diesel engines, offering higher efficiency, lower costs, and zero emissions.What sets this innovation apart is its completely indigenous design. Except for..

    Advertisement

    Subscribe to Our Newsletter

    Get daily newsletters around different themes from Construction world.

    STAY CONNECTED

    Advertisement

    Advertisement

    Advertisement

    Talk to us?