Bridge of highs
ROADS & HIGHWAYS

Bridge of highs

The 1.1-km bridge over Roopnarayan River, completed amid multiple challenges, boasts of several technological marvels.

The bridge on NH-6 over the river Roopnarayan near Kolaghat is a major landmark in Ashoka Buildcon Ltd's list of achievements. The 1.1-km bridge is part of the six-laning NHAI project of Kolkata-Kharagpur. The proposal to build a new bridge was first presented in 2000, which failed miserably. The contractors were quite reluctant to take up the project despite several tenders issued by the Ministry of Road Transport and Highways (MORTH) and the National Highways Authority of India (NHAI). In such a scenario, Ashoka Buildcon Ltd (ABL) rose to the challenge and undertook the project in 2011.

Delineating the structure

The project mainly involved the construction of two major bridges: one 323-m bridge left incomplete by NHAI and the state government, and another new, three-lane bridge of 1.1 km and six-laning of the highway stretch between Dhankuni and Kharagpur on BOT basis. These toll bridges were expected to offer relief from the long traffic jams that had become an everyday affair causing a loss of precious man hours. "We commissioned the project in an impressive time period: 18 months ahead of schedule," reveals Sanjay Londhe, Director.

Techno-marvel

The project boasts several technical achievements such as launching of a huge steel girder assembly comprising spans as long as 80 m, totalling a length of 323 m and weighing over 1,700 metric tonne. The steel assembly was constructed at the fabrication yard and assembled at site. It was mounted on a trolley arrangement and placed into position using a state-of-the-art hydraulic mechanism.

"To execute such a complex project, we employed the segmental construction method that involves the use of repetitive elements progressively connected together to form a completed structure. Construction load cases are particularly critical considerations in developing design and construction methods for such bridges. The tilted well foundation extends deep inside the riverbed to attract the necessary soil resistance against overturning, heavy scour, rolling boulders and floating debris," Londhe informs.

Material boost

Besides steel and concrete of M45 grade, the project uses anti-corrosive paints that prevent the piles from corrosion and rusting owing to long submergence in water. "To enable smooth mobilisation of all materials and machineries to the project site, we constructed a 6,800 tonne temporary steel platform across the riverbed," he notes.

The obstacles

The project faced numerous technical and geographical hindrances during the initial phase of its implementation. The original bridge built in 1965 had started deteriorating. The vehicles passing over the bridge had already increased manifold and traffic jams were becoming a major problem. "A major damage on the bridge would have paralysed the entire road traffic movement between Kolkata and a major part of the rest of the country. The half-complete bridge had already incurred a lot of investment, time and effort. Abandoning it completely would have implied a huge national waste," avers Londhe. The previous contractor left the site without completing 323 m in between P8 to P14 owing to technical failure at well foundation P9, P11 and P12 in 2005. A second contractor was appointed in 2009, who also quit the project.

When ABL took up the project, the heavy monsoons too played havoc, leading them to suspend work for several days. The high moisture content in the soil complicated matters, making project execution difficult. "Additionally, we faced a huge time crunch. To overcome this, we commenced the construction of the new bridge with a span of 360 precast segments completing simultaneously the work on the incomplete bridge," he beams.

The challenge of producing a 3D model of the box girder bridge and calibrating necessary stiffness parameters to create a simpler 2D grillage model to use at a later stage was solved through the use of advanced software such as STAAD Pro that not only accelerated the processing capabilities but reduced design and analysis time from an average of 400 man hours to 250 man hours.

Lending a hand

The project was well-supported by the Central and the state governments who monitored work progress on a regular basis, enabling completion in such a short timeframe. "The bridges will soon be installed with electronic surveillance system and security cameras to monitor vehicle movements and any criminal activity," Londhe elucidates.

Infra boost

These bridges will give a positive boost to business by reducing travel time significantly, saving precious fuel and cutting down on gas emissions. "There will be an easing of traffic snarls of 5-6 km on both sides of the bridges," he observes. "Further, these bridges will provide additional estimated toll revenue of Rs 80 crore, besides helping the government to deliver its obligation to the public by providing long-delayed infrastructure. And this will increase the level of safety on the highway, providing pleasant and safe travel across the river.

Project details

Size: 1.1 km Completion: 2013
Developer: Government of West Bengal. Tel: 033-2282 1952/54. Website: westbengal.gov.in
Contractor: Ashoka Buildcon Ltd. Tel: 0253-301 1705. Fax: 0253-223 6704.

The 1.1-km bridge over Roopnarayan River, completed amid multiple challenges, boasts of several technological marvels. The bridge on NH-6 over the river Roopnarayan near Kolaghat is a major landmark in Ashoka Buildcon Ltd's list of achievements. The 1.1-km bridge is part of the six-laning NHAI project of Kolkata-Kharagpur. The proposal to build a new bridge was first presented in 2000, which failed miserably. The contractors were quite reluctant to take up the project despite several tenders issued by the Ministry of Road Transport and Highways (MORTH) and the National Highways Authority of India (NHAI). In such a scenario, Ashoka Buildcon Ltd (ABL) rose to the challenge and undertook the project in 2011. Delineating the structure The project mainly involved the construction of two major bridges: one 323-m bridge left incomplete by NHAI and the state government, and another new, three-lane bridge of 1.1 km and six-laning of the highway stretch between Dhankuni and Kharagpur on BOT basis. These toll bridges were expected to offer relief from the long traffic jams that had become an everyday affair causing a loss of precious man hours. "We commissioned the project in an impressive time period: 18 months ahead of schedule," reveals Sanjay Londhe, Director. Techno-marvel The project boasts several technical achievements such as launching of a huge steel girder assembly comprising spans as long as 80 m, totalling a length of 323 m and weighing over 1,700 metric tonne. The steel assembly was constructed at the fabrication yard and assembled at site. It was mounted on a trolley arrangement and placed into position using a state-of-the-art hydraulic mechanism. "To execute such a complex project, we employed the segmental construction method that involves the use of repetitive elements progressively connected together to form a completed structure. Construction load cases are particularly critical considerations in developing design and construction methods for such bridges. The tilted well foundation extends deep inside the riverbed to attract the necessary soil resistance against overturning, heavy scour, rolling boulders and floating debris," Londhe informs. Material boost Besides steel and concrete of M45 grade, the project uses anti-corrosive paints that prevent the piles from corrosion and rusting owing to long submergence in water. "To enable smooth mobilisation of all materials and machineries to the project site, we constructed a 6,800 tonne temporary steel platform across the riverbed," he notes. The obstacles The project faced numerous technical and geographical hindrances during the initial phase of its implementation. The original bridge built in 1965 had started deteriorating. The vehicles passing over the bridge had already increased manifold and traffic jams were becoming a major problem. "A major damage on the bridge would have paralysed the entire road traffic movement between Kolkata and a major part of the rest of the country. The half-complete bridge had already incurred a lot of investment, time and effort. Abandoning it completely would have implied a huge national waste," avers Londhe. The previous contractor left the site without completing 323 m in between P8 to P14 owing to technical failure at well foundation P9, P11 and P12 in 2005. A second contractor was appointed in 2009, who also quit the project. When ABL took up the project, the heavy monsoons too played havoc, leading them to suspend work for several days. The high moisture content in the soil complicated matters, making project execution difficult. "Additionally, we faced a huge time crunch. To overcome this, we commenced the construction of the new bridge with a span of 360 precast segments completing simultaneously the work on the incomplete bridge," he beams. The challenge of producing a 3D model of the box girder bridge and calibrating necessary stiffness parameters to create a simpler 2D grillage model to use at a later stage was solved through the use of advanced software such as STAAD Pro that not only accelerated the processing capabilities but reduced design and analysis time from an average of 400 man hours to 250 man hours. Lending a hand The project was well-supported by the Central and the state governments who monitored work progress on a regular basis, enabling completion in such a short timeframe. "The bridges will soon be installed with electronic surveillance system and security cameras to monitor vehicle movements and any criminal activity," Londhe elucidates. Infra boost These bridges will give a positive boost to business by reducing travel time significantly, saving precious fuel and cutting down on gas emissions. "There will be an easing of traffic snarls of 5-6 km on both sides of the bridges," he observes. "Further, these bridges will provide additional estimated toll revenue of Rs 80 crore, besides helping the government to deliver its obligation to the public by providing long-delayed infrastructure. And this will increase the level of safety on the highway, providing pleasant and safe travel across the river. Project details Size: 1.1 km Completion: 2013 Developer: Government of West Bengal. Tel: 033-2282 1952/54. Website: westbengal.gov.in Contractor: Ashoka Buildcon Ltd. Tel: 0253-301 1705. Fax: 0253-223 6704.

Next Story
Infrastructure Transport

Does India have the 2nd largest road network in the world?

Here are some truths…Pratap Padode, President, FIRST Construction Council unravels some disturbing facts…

Recently there was a lot of chest thumping around India having the second longest road network in the world. Union Minister Nitin Gadkari informed the Lok Sabha that India had the second largest road network in the world, with about 63.32 lakh km of roads as of March 2019. I dug further and found an update from the Ministry of Road Transport & Highways that India has about 66.71 lakh km of road network, which is the second largest in the world. True. But the categories..

Next Story
Infrastructure Transport

RAHSTA Expo 2024 launched

“The Ministry of Road Transport & Highways has constructed 12,349 km of national highways in 2023-24 - the second highest achievement! In 2020-21 a record 13,327 kms were constructed, the highest so far. The experience of a well-constructed road is no accident but a badly constructed one can cause many,” said Pratap Padode, Founder, FIRST Construction Council (FCC), at the launch of a road show - 14th Roads and Highways Sustainable Technologies and Advancement [RAHSTA] Expo, which will be held from 9-10 October 2024 at Jio Convention Ce..

Next Story
Infrastructure Transport

RAHSTA to showcase cutting-edge road construction tech, says NCC Director

April 10, 2024, Delhi

“The RAHSTA expo will offer extensive information about the latest technology and methods for constructing high-quality roads. Currently, the challenge facing the roads industry is to uphold road quality and execute projects efficiently. RAHSTA will provide opportunities for everyone to learn about the latest worldwide technologies and equipment available, undoubtedly offering valuable insights to those involved in the roads sector,” said Vinod Kumar Yadav, Director – Transport, NCC, and former Chairman,..

Next Story
Infrastructure Transport

GMC Invests Rs.580 Mn in Road Dust Machines

The Guwahati Municipal Corporation (GMC) has allocated ?580 million to acquire two additional machines aimed at sweeping road dust. This investment underscores GMC's commitment to improving cleanliness and air quality in the city.

The newly procured machines are part of GMC's efforts to enhance its fleet of equipment dedicated to road cleaning activities. With the purchase of these machines, GMC aims to intensify its efforts in addressing dust pollution, a significant concern for residents and commuters in Guwahati.

The machines are equipped with advanced technology designed to e..

Next Story
Infrastructure Transport

GMC Invests Rs.580 Mn in Road Dust Machines

Residents in Dehradun have raised questions and expressed scepticism regarding the proposed widening project for Sahastradhara Road. The project, aimed at widening the road to accommodate increased traffic, has faced criticism and scrutiny from local residents concerned about its potential impact on the environment and surrounding areas.

The Sahastradhara Road widening project has sparked debate among residents, with some questioning the necessity and feasibility of the initiative. Critics argue that widening the road may lead to the loss of trees, green spaces, and heritage structures ..

Hi There!

Now get regular updates from CW Magazine on WhatsApp!

Click on link below, message us with a simple hi, and SAVE our number

You will have subscribed to our Construction News on Whatsapp! Enjoy

+91 81086 03000

Join us Telegram