BMC Cement Concretisation Cuts Pothole Repairs By 70 Per Cent
Cement

BMC Cement Concretisation Cuts Pothole Repairs By 70 Per Cent

The Brihanmumbai Municipal Corporation's cement concretisation project, valued at Rs 170 billion (Rs 170 bn), has reduced expenditure on pothole repairs by 70 per cent over three years. Spending on repairs fell from Rs 2.02 billion in 2023–24 to Rs 1.56 billion in 2024–25 and then to Rs 890 million (Rs 890 mn) in 2025–26. The current tender is expected to be about Rs 440 million, representing a further 50 per cent reduction.

The project is being executed in two phases, with Phase I covering 307 km from October 2023 and Phase II covering 370 km from October 2024. The Indian Institute of Technology is auditing Phase II and will now also audit Phase I to ensure quality and accountability. Mumbai's total road network spans approximately 2,050 km, of which about 1,200 km had been converted to cement concrete before 2022.

Since 2022 an additional 677 km were taken up for concretisation and nearly 71 per cent of that work, amounting to 481 km, has been completed. Municipal officials indicated that 10–15 per cent of the remaining work is expected to be completed by May 2026 and another 10 per cent by December 2026. The entire programme is scheduled for completion by May 2027, by which time nearly 1,900 km of Mumbai's roads are expected to be fully concretised.

The administration has also developed a real time dashboard that displays detailed information about contracts, contractors and progress and citizens can access the latest updates online. The dashboard includes contact details for the civic officials and contractors responsible for particular roads to enhance transparency and accountability. The commissioner directed that ongoing works be completed by 31 May ahead of the monsoon to safeguard completion targets and minimise disruption.

The Brihanmumbai Municipal Corporation's cement concretisation project, valued at Rs 170 billion (Rs 170 bn), has reduced expenditure on pothole repairs by 70 per cent over three years. Spending on repairs fell from Rs 2.02 billion in 2023–24 to Rs 1.56 billion in 2024–25 and then to Rs 890 million (Rs 890 mn) in 2025–26. The current tender is expected to be about Rs 440 million, representing a further 50 per cent reduction. The project is being executed in two phases, with Phase I covering 307 km from October 2023 and Phase II covering 370 km from October 2024. The Indian Institute of Technology is auditing Phase II and will now also audit Phase I to ensure quality and accountability. Mumbai's total road network spans approximately 2,050 km, of which about 1,200 km had been converted to cement concrete before 2022. Since 2022 an additional 677 km were taken up for concretisation and nearly 71 per cent of that work, amounting to 481 km, has been completed. Municipal officials indicated that 10–15 per cent of the remaining work is expected to be completed by May 2026 and another 10 per cent by December 2026. The entire programme is scheduled for completion by May 2027, by which time nearly 1,900 km of Mumbai's roads are expected to be fully concretised. The administration has also developed a real time dashboard that displays detailed information about contracts, contractors and progress and citizens can access the latest updates online. The dashboard includes contact details for the civic officials and contractors responsible for particular roads to enhance transparency and accountability. The commissioner directed that ongoing works be completed by 31 May ahead of the monsoon to safeguard completion targets and minimise disruption.

Next Story
Equipment

Kirloskar Brothers supports INS Taragiri with pump systems

Kirloskar Brothers (KBL) has contributed to INS Taragiri, the Indian Navy’s stealth-guided missile frigate, supporting India’s indigenous defence manufacturing programme. KBL has supplied precision-engineered Canned Motor Pumps (CMPs), critical to the vessel’s onboard systems. These pumps are designed for leak-proof operation, high reliability and low maintenance, with compact, low-noise and low-vibration performance suited for naval environments. INS Taragiri is part of India’s indigenisation drive in defence, representing advanced naval engineering and self-reliance in shipbui..

Next Story
Infrastructure Energy

Power Mech Secures Mumbai Monorail Operations Contract

Power Mech Projects Limited (Power Mech) has secured an order from Maha Mumbai Metro Operation Corporation Limited (MMMOC) to undertake the operations and maintenance of the Mumbai Monorail. The contract pertains to a corridor of 19.54 km featuring 17 stations and will connect Sant Gadge Maharaj Chowk to Chembur. The award was disclosed to stock exchanges in a filing that conforms to SEBI master circular requirements. Under the terms the scope comprises routine operations, system upkeep, signalling and traction oversight, station management and other allied services necessary for continuous se..

Next Story
Infrastructure Urban

UK Awards Rs380 Mn To Tata's Agratas For Somerset Gigafactory

The UK government has awarded Rs380 mn in funding to Agratas Energy Storage Solutions Private Limited (Agratas), the battery arm of the Tata Group, to support a planned electric vehicle battery gigafactory in Somerset. The Advanced Propulsion Centre (APC) said the grant forms part of a broader Rs470 mn government package intended to bolster domestic manufacture of batteries and strengthen supply chains for zero emission transport. The funding allocation was announced as part of efforts to accelerate the transition to zero emission vehicles and attract industrial investment. Agratas is developi..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement