How Afcons reduced construction time at Chhara by 9 days
Cement

How Afcons reduced construction time at Chhara by 9 days

At LNG Tanks, Chhara, the major scope of work included the construction of two LNG storage tanks (outer diameter 89.6 m and inner diameter 88 m). The tank construction entailed the construction of a prestressed concrete (PC) wall, 37.36 m high, to be constructed in 10 lifts. The team was able to reduce the cycle time of the PC wall construction for Tank 2 by 25 per cent (nine days) compared to Tank 1 by adopting LPS, 5S and waste elimination practices. PC wall activities involve multiple teams interfacing with each other: rebar fixing, H beams for compression ring support, laying prestressing ducts, VTL and HZT embedded plate installation, formwork installation, etc.

  • Minimising transportation and multiple handling by stacking rebar mats, links, vertical and horizontal inserts close to the corresponding area of the PC wall
  • Work sequence standardised and coordination meetings at the start of the day to minimise interference between multiple teams Analysis of variance in planned versus actual progress to identify root causes of delay
  • Design modification in TCP plate connections to minimise rework and improve speed of alignment.

At LNG Tanks, Chhara, the major scope of work included the construction of two LNG storage tanks (outer diameter 89.6 m and inner diameter 88 m). The tank construction entailed the construction of a prestressed concrete (PC) wall, 37.36 m high, to be constructed in 10 lifts. The team was able to reduce the cycle time of the PC wall construction for Tank 2 by 25 per cent (nine days) compared to Tank 1 by adopting LPS, 5S and waste elimination practices. PC wall activities involve multiple teams interfacing with each other: rebar fixing, H beams for compression ring support, laying prestressing ducts, VTL and HZT embedded plate installation, formwork installation, etc. Minimising transportation and multiple handling by stacking rebar mats, links, vertical and horizontal inserts close to the corresponding area of the PC wall Work sequence standardised and coordination meetings at the start of the day to minimise interference between multiple teams Analysis of variance in planned versus actual progress to identify root causes of delay Design modification in TCP plate connections to minimise rework and improve speed of alignment.

Next Story
Infrastructure Transport

Shivraj Chouhan Launches PMGSY IV and Announces Package for Madhya Pradesh

Union Minister Shivraj Singh Chouhan launched the Pradhan Mantri Gram Sadak Yojana (PMGSY) IV at Bhairunda in Sehore district during the 25 year celebrations and announced a development package for Madhya Pradesh. The programme was organised by the Union Ministry of Rural Development and attended by Chief Minister Dr Mohan Yadav, ministers of state, state ministers, legislators and senior officials from the centre and the state. The minister said the central government under the Prime Minister is committed to strengthening rural livelihoods through improved connectivity, housing and women's in..

Next Story
Infrastructure Urban

DMR Engineering Reports FY 25-26 Financial Results

DMR Engineering reported its half year results for the financial year ended 31 March 2026 and published full year figures on a standalone basis. Standalone revenue from operations decreased by 2.01 per cent year-over-year to Rs 102.58 million (mn), while profit after tax declined by 43.94 per cent to nine point five six mn, leaving a profit after tax margin of nine point zero five per cent. Earnings per share stood at Rs zero point nine two, a fall of 44.71 per cent year-over-year. The company attributed part of the decline to one-off provisioning for bad debts and additional financing charges..

Next Story
Infrastructure Urban

Atlanta Electricals Posts Strong FY26 Growth And Debt Free Finish

Atlanta Electricals reported audited consolidated results for the quarter and year ended 31 March 2026. The company recorded significant year-on-year revenue growth driven by capacity ramp-up at new facilities and higher utilisation at legacy plants. The announcement summarised operating improvements and strategic milestones achieved during the year. For Q4 the company reported revenue of Rs 7.48 bn and for FY26 revenue of Rs 18.52 bn, representing robust growth versus the prior year. EBITDA in Q4 was Rs. 1.49 bn and Rs. 3.44 bn for the full year, with margins expanding to 20 per cent in the q..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement