How Afcons reduced construction time at Chhara by 9 days
Cement

How Afcons reduced construction time at Chhara by 9 days

At LNG Tanks, Chhara, the major scope of work included the construction of two LNG storage tanks (outer diameter 89.6 m and inner diameter 88 m). The tank construction entailed the construction of a prestressed concrete (PC) wall, 37.36 m high, to be constructed in 10 lifts. The team was able to reduce the cycle time of the PC wall construction for Tank 2 by 25 per cent (nine days) compared to Tank 1 by adopting LPS, 5S and waste elimination practices. PC wall activities involve multiple teams interfacing with each other: rebar fixing, H beams for compression ring support, laying prestressing ducts, VTL and HZT embedded plate installation, formwork installation, etc.

  • Minimising transportation and multiple handling by stacking rebar mats, links, vertical and horizontal inserts close to the corresponding area of the PC wall
  • Work sequence standardised and coordination meetings at the start of the day to minimise interference between multiple teams Analysis of variance in planned versus actual progress to identify root causes of delay
  • Design modification in TCP plate connections to minimise rework and improve speed of alignment.

At LNG Tanks, Chhara, the major scope of work included the construction of two LNG storage tanks (outer diameter 89.6 m and inner diameter 88 m). The tank construction entailed the construction of a prestressed concrete (PC) wall, 37.36 m high, to be constructed in 10 lifts. The team was able to reduce the cycle time of the PC wall construction for Tank 2 by 25 per cent (nine days) compared to Tank 1 by adopting LPS, 5S and waste elimination practices. PC wall activities involve multiple teams interfacing with each other: rebar fixing, H beams for compression ring support, laying prestressing ducts, VTL and HZT embedded plate installation, formwork installation, etc. Minimising transportation and multiple handling by stacking rebar mats, links, vertical and horizontal inserts close to the corresponding area of the PC wall Work sequence standardised and coordination meetings at the start of the day to minimise interference between multiple teams Analysis of variance in planned versus actual progress to identify root causes of delay Design modification in TCP plate connections to minimise rework and improve speed of alignment.

Next Story
Infrastructure Energy

Vedanta Aluminium Uses 1.57 bn Units of Green Energy in FY25

Vedanta Aluminium, India’s largest aluminium producer, recently reported consumption of 1.57 billion units of renewable energy in FY25, marking a significant milestone in its 2030 decarbonisation roadmap. The company also achieved an 8.96 per cent reduction in greenhouse gas (GHG) emissions intensity compared to FY21, reinforcing its leadership in India’s low-carbon manufacturing transition. During FY25, Vedanta Aluminium expanded its renewable energy portfolio through long-term power purchase agreements, strengthening its strategy to source nearly 1,500 MW of renewable power over the lon..

Next Story
Real Estate

Oberoi Group to Develop Luxury Resort at Makaibari Tea Estate

EIH Limited, the flagship company of The Oberoi Group, has announced the signing of a management agreement to develop an Oberoi luxury resort at the iconic Makaibari Tea Estate in Darjeeling. The project marks a key milestone in the Group’s long-term strategy of creating distinctive hospitality experiences in rare and environmentally significant locations. Established in 1859, Makaibari is one of the world’s oldest tea estates and is globally recognised for its Himalayan landscape, primary forests and exceptional biodiversity. Spread across 1,236 acres, the estate houses one of the world..

Next Story
Real Estate

GHV Infra Secures Rs 1.09 Bn EPC Order in Jamshedpur

GHV Infra Projects Ltd, a fast-growing EPC company in India’s infrastructure and construction sector, has recently secured a Rs 1.09 billion work order in Jamshedpur, Jharkhand. Awarded by a reputed group entity, the contract covers end-to-end civil construction, mechanical, electrical and plumbing (MEP) systems, along with high-quality finishing works for a large building development. The project will be executed over a 30-month period, with defined benchmarks for quality, safety and timely delivery. The order strengthens GHV Infra’s footprint in Jamshedpur, a key industrial hub known fo..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Advertisement

Open In App