How Afcons reduced construction time at Chhara by 9 days
Cement

How Afcons reduced construction time at Chhara by 9 days

At LNG Tanks, Chhara, the major scope of work included the construction of two LNG storage tanks (outer diameter 89.6 m and inner diameter 88 m). The tank construction entailed the construction of a prestressed concrete (PC) wall, 37.36 m high, to be constructed in 10 lifts. The team was able to reduce the cycle time of the PC wall construction for Tank 2 by 25 per cent (nine days) compared to Tank 1 by adopting LPS, 5S and waste elimination practices. PC wall activities involve multiple teams interfacing with each other: rebar fixing, H beams for compression ring support, laying prestressing ducts, VTL and HZT embedded plate installation, formwork installation, etc.

  • Minimising transportation and multiple handling by stacking rebar mats, links, vertical and horizontal inserts close to the corresponding area of the PC wall
  • Work sequence standardised and coordination meetings at the start of the day to minimise interference between multiple teams Analysis of variance in planned versus actual progress to identify root causes of delay
  • Design modification in TCP plate connections to minimise rework and improve speed of alignment.

At LNG Tanks, Chhara, the major scope of work included the construction of two LNG storage tanks (outer diameter 89.6 m and inner diameter 88 m). The tank construction entailed the construction of a prestressed concrete (PC) wall, 37.36 m high, to be constructed in 10 lifts. The team was able to reduce the cycle time of the PC wall construction for Tank 2 by 25 per cent (nine days) compared to Tank 1 by adopting LPS, 5S and waste elimination practices. PC wall activities involve multiple teams interfacing with each other: rebar fixing, H beams for compression ring support, laying prestressing ducts, VTL and HZT embedded plate installation, formwork installation, etc. Minimising transportation and multiple handling by stacking rebar mats, links, vertical and horizontal inserts close to the corresponding area of the PC wall Work sequence standardised and coordination meetings at the start of the day to minimise interference between multiple teams Analysis of variance in planned versus actual progress to identify root causes of delay Design modification in TCP plate connections to minimise rework and improve speed of alignment.

Next Story
Technology

Building Faster, Smarter, and Greener!

Backed by ULCCS’s century-old legacy, U-Sphere combines technology, modular design and sustainable practices to deliver faster and more efficient projects. In an interaction with CW, Rohit Prabhakar, Director - Business Development, shares how the company’s integrated model of ‘Speed-Build’, ‘Smart-Build’ and ‘Sustain-Build’ is redefining construction efficiency, quality and environmental responsibility in India.U-Sphere positions itself at the intersection of speed, sustainability and smart design. How does this translate into measurable efficiency on the ground?At U..

Next Story
Infrastructure Transport

Smart Roads, Smarter India

India’s infrastructure boom is not only about laying more kilometres of highways – it’s about building them smarter, safer and more sustainably. From drones mapping fragile Himalayan slopes to 3D machine-controlled graders reducing human error, technology is steadily reshaping the way projects are planned and executed. Yet, the journey towards digitisation remains complex, demanding not just capital but also coordination, training and vision.Until recently, engineers largely depended on Survey of India toposheets and traditional survey methods like total stations or DGPS to prepare detai..

Next Story
Real Estate

What Does DCPR 2034 Mean?

The Maharashtra government has eased approval norms for high-rise buildings under DCPR 2034, enabling the municipal commissioner to sanction projects up to 180 m on large plots. This change is expected to streamline approvals, reduce procedural delays and accelerate redevelopment, drawing reactions from developers, planners and industry experts about its implications for Mumbai’s vertical growth.Under the revised DCPR 2034 rules, buildings on plots of 2,000 sq m or more can now be approved up to 180 m by the municipal commissioner, provided structural and geotechnical reports are certified b..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Talk to us?