JSW Cement Commissions 1 MTPA Unit in Rajasthan
Cement

JSW Cement Commissions 1 MTPA Unit in Rajasthan

JSW Cement has commissioned an additional 1 MTPA cement grinding unit in Nagaur, Rajasthan, taking the company’s total cement grinding capacity to 25.1 MTPA. The commissioning was announced on Tuesday, October 6.

The company said the new unit had increased the total cement grinding capacity at its Rajasthan plant to 3.50 MTPA. The expansion adds to JSW Cement’s production infrastructure as it continues to build capacity across its operating network.

The company’s total clinker manufacturing capacity, including capacity at its joint venture JSW Cement FZC, stands at 9.74 MTPA. Clinker is an intermediate material used in cement production, and its availability supports the company’s grinding operations.

JSW Cement is also pursuing a proposed merger of its listed subsidiary Shiva Cement with the company. The scheme, approved by the boards of the respective companies, involves issuing five fully paid-up JSW Cement equity shares for every 41 shares held by Shiva Cement shareholders other than JSW Cement.

The arrangement remains subject to shareholder and regulatory approvals. JSW Cement currently holds 66.23 per cent of Shiva Cement’s paid-up equity share capital, and the shares held by JSW Cement in the subsidiary will be cancelled under the proposal without any issue of JSW Cement shares against that holding.

The scheme has an appointed date of April 1, 2026, and the company has indicated that completion could take 12 to 14 months, depending on the receipt of approvals. These include clearances from stock exchanges, the Securities and Exchange Board of India, the National Company Law Tribunal and other applicable authorities, along with approvals from shareholders and creditors where required. JSW Cement shares closed at Rs. 113.15 on the BSE, up Rs. 2.05, or 1.85 per cent.

JSW Cement has commissioned an additional 1 MTPA cement grinding unit in Nagaur, Rajasthan, taking the company’s total cement grinding capacity to 25.1 MTPA. The commissioning was announced on Tuesday, October 6. The company said the new unit had increased the total cement grinding capacity at its Rajasthan plant to 3.50 MTPA. The expansion adds to JSW Cement’s production infrastructure as it continues to build capacity across its operating network. The company’s total clinker manufacturing capacity, including capacity at its joint venture JSW Cement FZC, stands at 9.74 MTPA. Clinker is an intermediate material used in cement production, and its availability supports the company’s grinding operations. JSW Cement is also pursuing a proposed merger of its listed subsidiary Shiva Cement with the company. The scheme, approved by the boards of the respective companies, involves issuing five fully paid-up JSW Cement equity shares for every 41 shares held by Shiva Cement shareholders other than JSW Cement. The arrangement remains subject to shareholder and regulatory approvals. JSW Cement currently holds 66.23 per cent of Shiva Cement’s paid-up equity share capital, and the shares held by JSW Cement in the subsidiary will be cancelled under the proposal without any issue of JSW Cement shares against that holding. The scheme has an appointed date of April 1, 2026, and the company has indicated that completion could take 12 to 14 months, depending on the receipt of approvals. These include clearances from stock exchanges, the Securities and Exchange Board of India, the National Company Law Tribunal and other applicable authorities, along with approvals from shareholders and creditors where required. JSW Cement shares closed at Rs. 113.15 on the BSE, up Rs. 2.05, or 1.85 per cent.

Related Stories

Gold Stories

Next Story
Infrastructure Transport

Supreme Infrastructure posts first post-scheme quarterly profit

Supreme Infrastructure India reported its first profitable quarter following the completion of its Composite Scheme, with a sharp increase in revenue and a significant reduction in finance costs driving its financial turnaround in Q2 FY27.Revenue from operations rose 114.8 per cent year-on-year to Rs 290.04 million in Q2 FY27, compared with Rs 135.02 million in the corresponding quarter last year. Total income increased 130.3 per cent to Rs 335.63 million from Rs 135.56 million.The company reported a profit after tax (PAT) of Rs 36.78 million in Q2 FY27, against a loss of Rs 591.43 million in ..

Next Story
Infrastructure Transport

J. Kumar Infraprojects Q2 profit rises 25 per cent to Rs 1.13 billion

J. Kumar Infraprojects reported a 25 per cent year-on-year increase in net profit to Rs 1.13 billion in Q2 FY27, while revenue from operations grew 15 per cent to Rs 15.39 billion.Profitability improved faster than revenue, with EBITDA rising 18 per cent to Rs 2.29 billion. The EBITDA margin expanded to 14.9 per cent, supported by cost control and steady project execution. Net profit margin increased to 7.4 per cent from 6.7 per cent in the corresponding quarter last year.The company's order book stood at Rs 227.11 billion, equivalent to nearly four times its annual revenue. It secured fresh o..

Next Story
Equipment

NORD India to invest Rs 4 billion in new Pune manufacturing facility

NORD Drivesystems India (NDPL) has commenced construction of a new manufacturing facility at RMK Industrial Park 3, near MIDC Talegaon Phase V, Pune, with a planned investment of Rs 4 billion. The expansion will double the company's gearbox and geared motor production capacity and introduce gear-component manufacturing.The facility will cater to domestic demand and exports to other NORD subsidiaries, including its headquarters in Germany. The company also plans to manufacture gears and related components at the new plant, supporting both the Indian market and global operations.Dhanraj Kalbhor,..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

SPECIAL OFFER
QR Code