Monsoon management plan being developed to secure coal at power plants
COAL & MINING

Monsoon management plan being developed to secure coal at power plants

In order to maintain sufficient fuel availability at power plants during the rainy season, when both coal output and evacuation are hindered, the coal ministry is working on a "monsoon management plan."

According to the strategy, coal companies would concentrate on delivering more from shallow locations, evacuating coal via first-mile connectivity, and building cement roads for truck traffic.

With these, the ministry is optimistic that coal availability at power plants would be adequate and accurate.

The second quarter is now the focus of planning as there is currently less coal stock depletion due to favourable weather conditions, but supply may become constrained due to rains impacting operations.

In order to meet anticipated increased demand in April, the government concentrated on delivering big volumes in the first quarter.

First-mile connection describes the movement of coal from mine pitheads to dispatch terminals without the need of roads. It consists of railway sidings close to coal mines as well as a mechanised coal transportation and loading system that sizes and crushes coal while offering quick computer-assisted loading.

Also read:
MCL to provide 35 lakh extra tonnes of coal
Numerous incentives likely to be available for underground coal mining


In order to maintain sufficient fuel availability at power plants during the rainy season, when both coal output and evacuation are hindered, the coal ministry is working on a monsoon management plan. According to the strategy, coal companies would concentrate on delivering more from shallow locations, evacuating coal via first-mile connectivity, and building cement roads for truck traffic. With these, the ministry is optimistic that coal availability at power plants would be adequate and accurate. The second quarter is now the focus of planning as there is currently less coal stock depletion due to favourable weather conditions, but supply may become constrained due to rains impacting operations. In order to meet anticipated increased demand in April, the government concentrated on delivering big volumes in the first quarter. First-mile connection describes the movement of coal from mine pitheads to dispatch terminals without the need of roads. It consists of railway sidings close to coal mines as well as a mechanised coal transportation and loading system that sizes and crushes coal while offering quick computer-assisted loading. Also read: MCL to provide 35 lakh extra tonnes of coal Numerous incentives likely to be available for underground coal mining

Next Story
Technology

Six ways a smarter workflow leads to faster, more accurate bids

In today’s fast-paced civil construction environment, estimators need more than just solid numbers. They need smart, streamlined processes. This article explores six key ways connected workflows can transform the estimated approach, help in minimising risk, move faster, and improve accuracy. By integrating tools, data, and teams, one can produce stronger bids with less rework, fewer surprises, and more confidence. As an estimator, the job goes beyond producing numbers. They are responsible for delivering bids that are fast, accurate, and built to win. In today’s civil construction ind..

Next Story
Real Estate

Experion Launches Women-Only Co-Living Project in Greater Noida

Experion, part of Singapore-based AT Capital Group, has launched its first co-living space under its managed rental housing brand, VLIV, in Greater Noida. The all-women residence features 730 twin-sharing beds with a strong focus on safety, comfort, and well-being. VLIV has committed a $300 million investment to create a structured, service-led rental housing ecosystem in India. The brand aims to scale up to 20,000 beds in the next few years, with a long-term target of 100,000 beds nationwide. “India’s rental housing is fragmented. VLIV is our way of building long-term, dependabl..

Next Story
Infrastructure Urban

Officine Maccaferri Acquires CPT to Bolster Tunnelling Tech

Ambienta’s platform company, Officine Maccaferri S.p.A., has acquired CPT Group, a leading Italian developer of robotic prefabrication systems and digital control technologies for mechanised tunnelling. The move positions Maccaferri as a global player in integrated tunnelling solutions, blending traditional and advanced mechanised systems. Based in Nova Milanese, CPT serves major global contractors across Europe, Southeast Asia, and Australia. The company offers robotic prefabrication (Robofactory), productivity-monitoring software for Tunnel Boring Machines (TBMs), and eco-designed spa..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Talk to us?