+
Asia's largest underwater hydrocarbon pipeline across Brahmaputra
OIL & GAS

Asia's largest underwater hydrocarbon pipeline across Brahmaputra

The Indradhanush Gas Grid (IGGL) has completed Asia's largest underwater hydro-carbon pipeline beneath the Brahmaputra, connecting Jorhat and Majuli in Assam, according to the company's CEO Ajit Kumar Thakur.

The challenging endeavour of laying a 24-inch diameter hydrocarbon pipeline beneath the mighty Brahmaputra river using the Horizontal Directional Drilling (HDD) method was completed on Friday, marking a major milestone in the construction of the North East Gas Grid (NEGG), which connects North East India to the National Gas Grid.

The total length of the pipeline in this single HDD crossing is 4,080 metres across the Brahmaputra river's main water channel. According to him, this is the longest river crossing by any hydrocarbon pipeline of 24-inch diameter or greater in Asia and the second longest in the world. This one-of-a-kind HDD river crossing was completed using the intersection method, in which two HDD rigs simultaneously began drilling from opposite sides of the Brahmaputra, with the two drilling heads intersecting in the middle at 30 metres beneath the river bed.

The laying of a 4,080-metre pipeline section was completed after overcoming numerous challenges, primarily caused by monsoon rains and flooding, he said. The total length of the HDD crossing the Brahmaputra river, including all major and minor water channels, is 5,780 metres.

The pipeline was constructed in three separate HDD sections of 1000 M, 4080 M, and 700 M lengths, with the first and third sections completed earlier. The next step will be to connect the three sections at two points, 15 M and 8 M below Natural Ground Level (NGL).

"With the completion of the Brahmaputra HDD, IGGL has achieved more than 71% physical progress on the NEGG Project and will be able to complete the Guwahati-Numaligarh section by February 2024," Thakur said. He thanked the Assam government for its assistance in carrying out the project.

Indradhanush Gas Grid Limited is a joint venture between five major oil public sector enterprises: IOCL, ONGC, GAIL, OIL, and ONGC. It is implementing the North East Gas Grid Project connecting the major cities and demand centres of North East India with the National Gas Grid. The 1656 km long natural gas pipeline is constructed at a project cost of Rs 9,265 crore.

Also Read
Pune outer ring road is likely to be delayed due to land rates
PM to inaugurate Kochi water metro, CM calls it ‘dream project’

The Indradhanush Gas Grid (IGGL) has completed Asia's largest underwater hydro-carbon pipeline beneath the Brahmaputra, connecting Jorhat and Majuli in Assam, according to the company's CEO Ajit Kumar Thakur. The challenging endeavour of laying a 24-inch diameter hydrocarbon pipeline beneath the mighty Brahmaputra river using the Horizontal Directional Drilling (HDD) method was completed on Friday, marking a major milestone in the construction of the North East Gas Grid (NEGG), which connects North East India to the National Gas Grid. The total length of the pipeline in this single HDD crossing is 4,080 metres across the Brahmaputra river's main water channel. According to him, this is the longest river crossing by any hydrocarbon pipeline of 24-inch diameter or greater in Asia and the second longest in the world. This one-of-a-kind HDD river crossing was completed using the intersection method, in which two HDD rigs simultaneously began drilling from opposite sides of the Brahmaputra, with the two drilling heads intersecting in the middle at 30 metres beneath the river bed. The laying of a 4,080-metre pipeline section was completed after overcoming numerous challenges, primarily caused by monsoon rains and flooding, he said. The total length of the HDD crossing the Brahmaputra river, including all major and minor water channels, is 5,780 metres. The pipeline was constructed in three separate HDD sections of 1000 M, 4080 M, and 700 M lengths, with the first and third sections completed earlier. The next step will be to connect the three sections at two points, 15 M and 8 M below Natural Ground Level (NGL). With the completion of the Brahmaputra HDD, IGGL has achieved more than 71% physical progress on the NEGG Project and will be able to complete the Guwahati-Numaligarh section by February 2024, Thakur said. He thanked the Assam government for its assistance in carrying out the project. Indradhanush Gas Grid Limited is a joint venture between five major oil public sector enterprises: IOCL, ONGC, GAIL, OIL, and ONGC. It is implementing the North East Gas Grid Project connecting the major cities and demand centres of North East India with the National Gas Grid. The 1656 km long natural gas pipeline is constructed at a project cost of Rs 9,265 crore. Also Read Pune outer ring road is likely to be delayed due to land rates PM to inaugurate Kochi water metro, CM calls it ‘dream project’

Next Story
Infrastructure Transport

Lucknow Metro East-West Corridor Consultancy Contract Awarded

The Uttar Pradesh Metro Rail Corporation has awarded the first construction-related consultancy contract for the Lucknow Metro East West Corridor to a joint venture of AYESA Ingenieria Arquitectura SAU and AYESA India Pvt Ltd. The firm was declared the lowest bidder for the Detailed Design Consultant contract for Lucknow Metro Line-2 under Phase 1B and the contract was recommended following the financial bid. The contract is valued at Rs 159.0 million (mn), covering design services for the corridor. Lucknow Metro Line-2 envisages the construction of an 11.165 kilometre corridor connecting Cha..

Next Story
Infrastructure Urban

Div Com Kashmir Urges Fast Tracking Of Jhelum Water Transport Project

The Divisional Commissioner of Kashmir has called for the fast-tracking of the Jhelum water transport project, urging district administrations and relevant agencies to accelerate planning and clearances. In a meeting convened at the divisional headquarters, the commissioner instructed officials from irrigation, public health engineering and municipal departments to prioritise the project and coordinate survey and design work. The directive emphasised removal of administrative bottlenecks and close monitoring to ensure timely mobilisation of resources and contractors. Officials were told to in..

Next Story
Infrastructure Urban

Interarch Reports Strong Q3 And Nine Month Results

Interarch Building Solutions Limited reported unaudited results for the third quarter and nine months ended 31 December 2025, recording strong revenue growth driven by execution and a robust order book. Net revenue for the third quarter rose by 43.7 per cent to Rs 5.225 billion (bn), compared with Rs 3.636 bn a year earlier, reflecting heightened demand in pre-engineered building projects. The company’s total order book as at 31 January 2026 stood at Rs 16.85 bn, supporting near-term visibility. EBITDA excluding other income for the quarter increased by 43.2 per cent to Rs 503 million (mn),..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Open In App