CERC Proposes Auctioning Connectivity To Ease Grid Congestion
POWER & RENEWABLE ENERGY

CERC Proposes Auctioning Connectivity To Ease Grid Congestion

The Central Electricity Regulatory Commission (CERC) has proposed major reforms to streamline India’s congested transmission network, calling Connectivity a “scarce resource” that should be auctioned for future applications. It also recommended that power purchase agreements (PPAs) replace letters of award (LoAs) as the valid document for granting Connectivity.

The recommendations are part of a consultation paper examining large volumes of renewable energy (RE) capacity for which developers have secured Connectivity under General Network Access (GNA) Regulations by submitting LoAs issued by renewable energy implementing agencies (REIAs), but have yet to sign PPAs.

CERC said there is an urgent need to free up Connectivity granted via the LoA route where PPA or power sale agreement (PSA) signing has been delayed. Stakeholders have been asked to submit responses by 15 December 2025.

The paper comes as the Ministry of New & Renewable Energy (MNRE) undertakes a comprehensive review of 43.9 gigawatts (GW) of RE projects stuck due to poor Discom interest in PSAs. As of June 2025, Connectivity has been granted to 31.802 GW of projects while another 13.541 GW of requests are still pending — a total of 45.343 GW for which PPAs have not been signed.

“This is a very significant quantum of Connectivity, as the corresponding transmission systems are either implemented or under implementation,” the regulator said.

To manage future requests, CERC has suggested that only an auction mechanism be used for granting Connectivity, ensuring firm project commitments by specified deadlines. Alternatively, it proposed removing the LoA route entirely and allowing Connectivity only on the basis of PPAs signed under the Centre’s competitive bidding guidelines — acknowledging that developers typically begin substantive work only after signing a PPA.

CERC has also proposed mechanisms to ensure optimal and timely utilisation of the transmission network. For instance, if a project with LoA-based Connectivity has not secured a PPA within 12 months, developers may substitute the initial LoA with a PPA linked to another LoA, provided the Connectivity start date under the second LoA is at least six months later than the first.

Developers may also choose to surrender Connectivity within one month. In such cases, the Central Transmission Utility of India (CTUIL) will encash Connectivity Bank Guarantee-1 (Conn-BG1) and return Conn-BG2 and Conn-BG3. The developer must continue to pay applicable transmission charges until CTUIL accepts the surrender.

The Central Electricity Regulatory Commission (CERC) has proposed major reforms to streamline India’s congested transmission network, calling Connectivity a “scarce resource” that should be auctioned for future applications. It also recommended that power purchase agreements (PPAs) replace letters of award (LoAs) as the valid document for granting Connectivity. The recommendations are part of a consultation paper examining large volumes of renewable energy (RE) capacity for which developers have secured Connectivity under General Network Access (GNA) Regulations by submitting LoAs issued by renewable energy implementing agencies (REIAs), but have yet to sign PPAs. CERC said there is an urgent need to free up Connectivity granted via the LoA route where PPA or power sale agreement (PSA) signing has been delayed. Stakeholders have been asked to submit responses by 15 December 2025. The paper comes as the Ministry of New & Renewable Energy (MNRE) undertakes a comprehensive review of 43.9 gigawatts (GW) of RE projects stuck due to poor Discom interest in PSAs. As of June 2025, Connectivity has been granted to 31.802 GW of projects while another 13.541 GW of requests are still pending — a total of 45.343 GW for which PPAs have not been signed. “This is a very significant quantum of Connectivity, as the corresponding transmission systems are either implemented or under implementation,” the regulator said. To manage future requests, CERC has suggested that only an auction mechanism be used for granting Connectivity, ensuring firm project commitments by specified deadlines. Alternatively, it proposed removing the LoA route entirely and allowing Connectivity only on the basis of PPAs signed under the Centre’s competitive bidding guidelines — acknowledging that developers typically begin substantive work only after signing a PPA. CERC has also proposed mechanisms to ensure optimal and timely utilisation of the transmission network. For instance, if a project with LoA-based Connectivity has not secured a PPA within 12 months, developers may substitute the initial LoA with a PPA linked to another LoA, provided the Connectivity start date under the second LoA is at least six months later than the first. Developers may also choose to surrender Connectivity within one month. In such cases, the Central Transmission Utility of India (CTUIL) will encash Connectivity Bank Guarantee-1 (Conn-BG1) and return Conn-BG2 and Conn-BG3. The developer must continue to pay applicable transmission charges until CTUIL accepts the surrender.

Next Story
Infrastructure Transport

Dhalbhumgarh Airport Faces 150-km Rule Hurdle

The issue has resurfaced following a recent statement by Union Civil Aviation Minister Ram Mohan Naidu, who said that under existing aviation policy, a new greenfield airport is generally not permitted within an aerial distance of 150 kilometres of an operational civilian airport. He added, however, that if a formal proposal is submitted, its impact on the existing airport can be examined and relaxations may be considered on a case-by-case basis. While the clarification has revived some hope for Dhalbhumgarh, it has also underlined the scale of the technical challenge facing the project. Unde..

Next Story
Infrastructure Transport

Stakeholders Seek Parallel Ops For Vizag Airports

With road and metro rail links to Bhogapuram still several years away, stakeholders in north Andhra Pradesh have renewed demands to continue civil operations at INS Dega even after the commissioning of Bhogapuram International Airport. The new airport is expected to begin commercial operations from June. Officials said close to 80 per cent of the airport infrastructure at Bhogapuram, including the terminal building and internal approach roads, has already been completed. However, inadequate external connectivity remains a key concern. Making a case for parallel operations, Andhra Pradesh Air ..

Next Story
Infrastructure Transport

Govt To Roll Out V2V Tech To Cut Road Crashes

In an effort to curb road accidents, particularly in low-visibility conditions such as dense fog, the government is set to roll out vehicle-to-vehicle (V2V) communication technology that will allow cars to exchange real-time data and alert drivers to potential dangers. The announcement was made by Union Road Transport and Highways Minister Nitin Gadkari after the 43rd meeting of the Transport Development Council. The technology involves installing an on-board unit (OBU) in vehicles, enabling wireless data exchange between nearby cars. This will allow vehicles to share information such as spee..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Advertisement

Open In App