CERC rejects Avaada Energy plea for MTOA extension
POWER & RENEWABLE ENERGY

CERC rejects Avaada Energy plea for MTOA extension

The Central Electricity Regulatory Commission (CERC) recently rejected a solar generator’s plea seeking an extension of the start date of medium-term open access (MTOA). It said that the transmission charges towards MTOA should be billed to the buyer only after the generating station’s commercial operation date.

The Commission added that the bills corresponding to the capacity not commissioned, raised to the Haryana Power Purchase Centre (HPPC) by the Central Transmission Utility (CTU), were contrary to the provision of the ‘Sharing Regulations.’ Accordingly, it directed CTU to revise the bills and raise them on the petitioner.

Avaada Energy and Avaada RJHN had filed a petition seeking an extension of the start date of MTOA and restraining the CTU from taking any coercive measures for the non-operationalisation of 114.25 MW out of the total 240 MW on the premise that the start date of MTOA was February 1, 2022.

Since the solar generator achieved the commercial operation of only 125.75 MW by the end of January 2022, it requested CTU for an extension of time for the part operationalization of MTOA for the balance of 114.25 MW up to May 23, 2022.

Avaada Energy submitted that the MTOA of the contracted capacity being 240 MW (out of which 125.75 MW capacity has already been commissioned), had been delayed due to the outbreak of Covid-19 and resultant lockdown, which were considered ‘force majeure’ events.

See also:
JSL seeking partners to build 300 MW solar & wind capacities
Indore forced to drop solar plants from VCS programme


The Central Electricity Regulatory Commission (CERC) recently rejected a solar generator’s plea seeking an extension of the start date of medium-term open access (MTOA). It said that the transmission charges towards MTOA should be billed to the buyer only after the generating station’s commercial operation date. The Commission added that the bills corresponding to the capacity not commissioned, raised to the Haryana Power Purchase Centre (HPPC) by the Central Transmission Utility (CTU), were contrary to the provision of the ‘Sharing Regulations.’ Accordingly, it directed CTU to revise the bills and raise them on the petitioner. Avaada Energy and Avaada RJHN had filed a petition seeking an extension of the start date of MTOA and restraining the CTU from taking any coercive measures for the non-operationalisation of 114.25 MW out of the total 240 MW on the premise that the start date of MTOA was February 1, 2022. Since the solar generator achieved the commercial operation of only 125.75 MW by the end of January 2022, it requested CTU for an extension of time for the part operationalization of MTOA for the balance of 114.25 MW up to May 23, 2022. Avaada Energy submitted that the MTOA of the contracted capacity being 240 MW (out of which 125.75 MW capacity has already been commissioned), had been delayed due to the outbreak of Covid-19 and resultant lockdown, which were considered ‘force majeure’ events. See also: JSL seeking partners to build 300 MW solar & wind capacitiesIndore forced to drop solar plants from VCS programme

Next Story
Infrastructure Transport

BMC Gets CRZ Nod For Rs 40 Million Gorai Bridge Rebuild

The Brihanmumbai Municipal Corporation (BMC) has secured Coastal Regulation Zone (CRZ) clearance for the reconstruction of the Poisar River bridge in Gorai, located in Mumbai’s western suburbs. However, the proposed demolition of the existing 100-metre bridge has sparked opposition from local residents, who claim it serves as the only direct access route between the Lower and Upper Koliwada areas. The three-decade-old bridge, situated within the CRZ buffer zone, was recently declared structurally unsafe following a civic audit. The BMC has sanctioned its reconstruction at an estimated cost ..

Next Story
Infrastructure Transport

NHAI Completes Rs 15.9 Billion Four-Lane Stretch On ECR

The National Highways Authority of India (NHAI) has completed the four-laning of the 38 km Puducherry–Poondiyankuppam stretch, ending near Cuddalore, in a development that will cut travel time by up to two hours, according to a report by The New Indian Express. The upgraded section, built at a cost of Rs 15.9 billion under the Bharatmala Pariyojana Phase I, marks a major milestone in the ongoing East Coast Road (ECR) widening programme. The project promises a smoother, faster drive for motorists travelling towards Cuddalore, Chidambaram, Sirkazhi, and Nagapattinam. With this completion, 22..

Next Story
Infrastructure Transport

Encroachments Delay Rs 1 Billion Ghatkopar Bridge Project

The construction of a new cable-stayed rail overbridge at Ghatkopar and the widening of the Andheri–Ghatkopar Link Road (AGLR) have been delayed due to the presence of nearly 250 encroached structures on both sides of the road. In response, Municipal Commissioner Bhushan Gagrani has directed officials to carry out a structural audit of the existing bridge over the railway line and enforce temporary restrictions on heavy vehicles to ensure public safety. The bridge, which starts at the Golibar Road junction near LBS Marg and extends up to the Eastern Express Highway (EEH), serves as a critic..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Talk to us?