+
CMPDI Invites Bids for 10 MW Solar Project at Mahanadi Coalfields
POWER & RENEWABLE ENERGY

CMPDI Invites Bids for 10 MW Solar Project at Mahanadi Coalfields

Central Mine Planning and Design Institute (CMPDI), a subsidiary of Coal India, has floated a tender for the design, engineering, procurement, and commissioning of a 10 MW grid-connected solar power project at Lakhanpur, Mahanadi Coalfields (MCL). The successful bidder must also operate and maintain the project for ten years. The last date for the submission of bids is December 14, 2024. Bids will open on December 16. The project’s estimated cost is Rs 585.2 million (~$6.9 million). Bidders must submit an earnest money deposit (EMD) of Rs 5 million (~$59,157). The successful bidder must provide performance security equivalent to 5% of the contract value within 21 days of receiving the letter of award. Bidders must have completed one of the following during the last seven years : • Three similar works, each costing not less than 20% of the estimated cost • Two similar works, each costing not less than 25% of the estimated cost • One similar work costing not less than 40% of the estimated cost Similar works are defined as the design, supply, installation, testing, and commissioning of grid-connected solar projects, including ground-mounted, rooftop, and floating solar installations. The average annual financial turnover over the last three years, up to March 31, 2024, must be at least 30% of the estimated tender cost. Bidders must possess working capital of at least 20% of the annualized value or estimated value, whichever is less, including access to lines of credit and the availability of other financial resources. Earlier, CMPDI invited bids for the design, supply, installation, commissioning, and testing of grid-connected solar power projects with a cumulative capacity of 13 MW.

Your next big infra connection is waiting at RAHSTA 2025 – Asia’s Biggest Roads & Highways Expo, Jio World Convention Centre, Mumbai. Don’t miss out!

Central Mine Planning and Design Institute (CMPDI), a subsidiary of Coal India, has floated a tender for the design, engineering, procurement, and commissioning of a 10 MW grid-connected solar power project at Lakhanpur, Mahanadi Coalfields (MCL). The successful bidder must also operate and maintain the project for ten years. The last date for the submission of bids is December 14, 2024. Bids will open on December 16. The project’s estimated cost is Rs 585.2 million (~$6.9 million). Bidders must submit an earnest money deposit (EMD) of Rs 5 million (~$59,157). The successful bidder must provide performance security equivalent to 5% of the contract value within 21 days of receiving the letter of award. Bidders must have completed one of the following during the last seven years : • Three similar works, each costing not less than 20% of the estimated cost • Two similar works, each costing not less than 25% of the estimated cost • One similar work costing not less than 40% of the estimated cost Similar works are defined as the design, supply, installation, testing, and commissioning of grid-connected solar projects, including ground-mounted, rooftop, and floating solar installations. The average annual financial turnover over the last three years, up to March 31, 2024, must be at least 30% of the estimated tender cost. Bidders must possess working capital of at least 20% of the annualized value or estimated value, whichever is less, including access to lines of credit and the availability of other financial resources. Earlier, CMPDI invited bids for the design, supply, installation, commissioning, and testing of grid-connected solar power projects with a cumulative capacity of 13 MW.

Next Story
Infrastructure Transport

68 Jammu-Katra Trains Cancelled Amid Rain Damage

Jammu and Katra railway services remain severely affected as Northern Railway announced the cancellation of 68 trains—both incoming and outgoing—until 30 September, due to extensive track damage caused by heavy rains and flash floods. Meanwhile, 24 trains are scheduled to resume operations gradually.The Jammu railway division has experienced a complete halt in services for the past eight days, following track misalignment and breaches at several points along the Pathankot–Jammu section. Torrential rainfall since 26 August led to widespread flooding and damage, stranding hundreds of passe..

Next Story
Infrastructure Transport

Bangalore Metro MD Reviews Reach 6 and Phase 2A Progress

Bangalore Metro Rail Corporation Limited (BMRCL) Managing Director, Dr J Ravishankar, IAS, conducted inspections of key metro corridors on 29 and 30 August, reviewing the progress of Reach 6 (Pink Line) and Phase 2A (Blue Line).On 30 August, the inspection covered Reach 6, a 21.39-km corridor stretching from Kalena Agrahara to Nagawara, with 18 stations. This stretch is part of Phase 2 of the Bangalore Metro project. Dr Ravishankar assessed the status of civil works, finishing, track laying, and system integration between Kalena Agrahara and MG Road.Earlier, on 29 August, the MD inspected Phas..

Next Story
Infrastructure Urban

Kerala Spends Rs 200 Billion During Onam Celebrations

The Kerala state government incurred expenditure totalling Rs 200 billion during the recent Onam season, covering regular financial obligations such as salaries and pensions, as well as festival-related allowances and subsidies, according to Finance Minister K N Balagopal.Of the total spend, Rs 121 billion was allocated towards salaries, pensions, bonuses, and festival allowances for government employees and pensioners. A further Rs 18 billion was disbursed as welfare pensions benefiting 6.2 million recipients, helping households manage festive costs.Food Kits and Festival AllowancesTo support..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Talk to us?