GERC Rejects Extension for 20 MW Solar Project in Gujarat
POWER & RENEWABLE ENERGY

GERC Rejects Extension for 20 MW Solar Project in Gujarat

The Gujarat Electricity Regulatory Commission (GERC) has rejected a petition by Vgrown Tech, now known as Kira Diam Tech, seeking a one-year extension for completing evacuation infrastructure linked to its 20 MW captive solar power project in Gir Somnath district. The regulator found that the developer had not established sufficient grounds or provided adequate evidence that delays were beyond its control.

The project is intended to evacuate power to the Gujarat Energy Transmission Corporation (GETCO) 66 kV Luvari Moli substation. Its original scheduled commissioning date (SCOD) was 30 January 2026, which was later extended during a general regulatory review to 31 July 2026. The developer sought a further extension until 31 January 2027.

The petition cited an initial adverse opinion from the Deputy Conservator of Forests on non-agricultural land clearances in an eco-sensitive zone. It also referred to compliance requirements under the Approved List of Models and Manufacturers (ALMM), supply chain disruptions linked to the conflict in the Middle East and heavy seasonal rainfall. The developer said these factors had affected construction and its ability to connect the project to the transmission network.

GETCO opposed the request, arguing that the developer had not shown sufficient diligence in planning and executing the project. The utility said relevant forest clearance requirements were already known when the land was selected and noted that equipment orders were placed only in January 2026, leaving limited time before the deadline. It also said general references to weather and geopolitical developments did not establish valid grounds for relief.

GERC found that the developer had not submitted concrete documentation showing that forest restrictions or external supply issues had directly prevented timely completion. The Commission said land acquisition and statutory approvals were primarily the developer’s responsibility, while seasonal rainfall could not ordinarily qualify as an unforeseeable force majeure event without supporting evidence. It also noted that pre-commissioning testing and metering remained incomplete after 31 July 2026, and dismissed the petition for an extension to 31 January 2027.

The Gujarat Electricity Regulatory Commission (GERC) has rejected a petition by Vgrown Tech, now known as Kira Diam Tech, seeking a one-year extension for completing evacuation infrastructure linked to its 20 MW captive solar power project in Gir Somnath district. The regulator found that the developer had not established sufficient grounds or provided adequate evidence that delays were beyond its control. The project is intended to evacuate power to the Gujarat Energy Transmission Corporation (GETCO) 66 kV Luvari Moli substation. Its original scheduled commissioning date (SCOD) was 30 January 2026, which was later extended during a general regulatory review to 31 July 2026. The developer sought a further extension until 31 January 2027. The petition cited an initial adverse opinion from the Deputy Conservator of Forests on non-agricultural land clearances in an eco-sensitive zone. It also referred to compliance requirements under the Approved List of Models and Manufacturers (ALMM), supply chain disruptions linked to the conflict in the Middle East and heavy seasonal rainfall. The developer said these factors had affected construction and its ability to connect the project to the transmission network. GETCO opposed the request, arguing that the developer had not shown sufficient diligence in planning and executing the project. The utility said relevant forest clearance requirements were already known when the land was selected and noted that equipment orders were placed only in January 2026, leaving limited time before the deadline. It also said general references to weather and geopolitical developments did not establish valid grounds for relief. GERC found that the developer had not submitted concrete documentation showing that forest restrictions or external supply issues had directly prevented timely completion. The Commission said land acquisition and statutory approvals were primarily the developer’s responsibility, while seasonal rainfall could not ordinarily qualify as an unforeseeable force majeure event without supporting evidence. It also noted that pre-commissioning testing and metering remained incomplete after 31 July 2026, and dismissed the petition for an extension to 31 January 2027.

Related Stories

Gold Stories

Next Story
Real Estate

Shree Naman Group acquires JW Marriott Bengaluru, Crowne Plaza Pune

Shree Naman Group has completed the acquisition of JW Marriott Bengaluru for Rs 16.11 billion and Crowne Plaza Pune for Rs 1.89 billion, taking its hospitality portfolio beyond Mumbai into two key business and hospitality markets.The Rs 18 billion transaction was completed on 1 October 2026, within 30 days of approval by the National Company Law Tribunal (NCLT) on 3 September 2026, following a competitive bidding process.The two hotels join the Group’s existing properties in Mumbai: Sofitel Mumbai BKC, Lemon Tree Hotel, Kalina BKC, and ibis Mumbai BKC. The portfolio now comprises five operat..

Next Story
Real Estate

Sobha Realty marks fourth year of IIFA partnership

Sobha Realty has reaffirmed its association with the International Indian Film Academy (IIFA) for the fourth consecutive year, returning as Title Sponsor of IIFA Weekend and Co-Presenting Sponsor of the IIFA Awards 2027. At a press conference in Mumbai, the UAE-based developer also highlighted its expansion into Abu Dhabi and its growing international presence.The upcoming IIFA Weekend and Awards will be held on 22 and 23 January 2027 at Etihad Arena, Yas Island, Abu Dhabi. The partnership, which began in Abu Dhabi in 2023, provides the developer with a platform to engage with Indian audiences..

Next Story
Technology

Powerplay Records 4X Growth in Platform Spend with AI Adoption

Construction technology platform Powerplay has reported up to fourfold growth in platform spending among customers adopting its artificial intelligence (AI) agents over approximately 18 months. The growth reflects increased adoption of AI-driven procurement and financing solutions among contractors and builders across India.The Bengaluru-based company has introduced an AI workforce designed to automate procurement coordination, supplier comparisons, material tracking and financing documentation. Its AI Purchase Executive enables contractors to compare supplier prices, monitor material requirem..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

SPECIAL OFFER
QR Code