GERC Rejects Extension for 20 MW Solar Project in Gujarat
POWER & RENEWABLE ENERGY

GERC Rejects Extension for 20 MW Solar Project in Gujarat

The Gujarat Electricity Regulatory Commission (GERC) has rejected a petition by Vgrown Tech, now known as Kira Diam Tech, seeking a one-year extension for completing evacuation infrastructure linked to its 20 MW captive solar power project in Gir Somnath district. The regulator found that the developer had not established sufficient grounds or provided adequate evidence that delays were beyond its control.

The project is intended to evacuate power to the Gujarat Energy Transmission Corporation (GETCO) 66 kV Luvari Moli substation. Its original scheduled commissioning date (SCOD) was 30 January 2026, which was later extended during a general regulatory review to 31 July 2026. The developer sought a further extension until 31 January 2027.

The petition cited an initial adverse opinion from the Deputy Conservator of Forests on non-agricultural land clearances in an eco-sensitive zone. It also referred to compliance requirements under the Approved List of Models and Manufacturers (ALMM), supply chain disruptions linked to the conflict in the Middle East and heavy seasonal rainfall. The developer said these factors had affected construction and its ability to connect the project to the transmission network.

GETCO opposed the request, arguing that the developer had not shown sufficient diligence in planning and executing the project. The utility said relevant forest clearance requirements were already known when the land was selected and noted that equipment orders were placed only in January 2026, leaving limited time before the deadline. It also said general references to weather and geopolitical developments did not establish valid grounds for relief.

GERC found that the developer had not submitted concrete documentation showing that forest restrictions or external supply issues had directly prevented timely completion. The Commission said land acquisition and statutory approvals were primarily the developer’s responsibility, while seasonal rainfall could not ordinarily qualify as an unforeseeable force majeure event without supporting evidence. It also noted that pre-commissioning testing and metering remained incomplete after 31 July 2026, and dismissed the petition for an extension to 31 January 2027.

The Gujarat Electricity Regulatory Commission (GERC) has rejected a petition by Vgrown Tech, now known as Kira Diam Tech, seeking a one-year extension for completing evacuation infrastructure linked to its 20 MW captive solar power project in Gir Somnath district. The regulator found that the developer had not established sufficient grounds or provided adequate evidence that delays were beyond its control. The project is intended to evacuate power to the Gujarat Energy Transmission Corporation (GETCO) 66 kV Luvari Moli substation. Its original scheduled commissioning date (SCOD) was 30 January 2026, which was later extended during a general regulatory review to 31 July 2026. The developer sought a further extension until 31 January 2027. The petition cited an initial adverse opinion from the Deputy Conservator of Forests on non-agricultural land clearances in an eco-sensitive zone. It also referred to compliance requirements under the Approved List of Models and Manufacturers (ALMM), supply chain disruptions linked to the conflict in the Middle East and heavy seasonal rainfall. The developer said these factors had affected construction and its ability to connect the project to the transmission network. GETCO opposed the request, arguing that the developer had not shown sufficient diligence in planning and executing the project. The utility said relevant forest clearance requirements were already known when the land was selected and noted that equipment orders were placed only in January 2026, leaving limited time before the deadline. It also said general references to weather and geopolitical developments did not establish valid grounds for relief. GERC found that the developer had not submitted concrete documentation showing that forest restrictions or external supply issues had directly prevented timely completion. The Commission said land acquisition and statutory approvals were primarily the developer’s responsibility, while seasonal rainfall could not ordinarily qualify as an unforeseeable force majeure event without supporting evidence. It also noted that pre-commissioning testing and metering remained incomplete after 31 July 2026, and dismissed the petition for an extension to 31 January 2027.

Related Stories

Gold Stories

Next Story
Infrastructure Urban

DGTR Opens Anti-Dumping Probe into Aluminium Imports

The Directorate General of Trade Remedies (DGTR) has initiated a suo motu anti-dumping investigation into aluminium products imported from China, Malaysia, Vietnam and Thailand. The investigation follows concerns that increased imports from the four countries have caused injury to domestic manufacturers, particularly micro, small and medium enterprises (MSMEs). According to a DGTR notification dated November 9, the probe followed representations from the Aluminium Extrusion Manufacturers Association of India (ALEMAI). The association represents 228 manufacturers producing aluminium extrusion p..

Next Story
Infrastructure Urban

NMDC Explores Lithium Investments with Russia’s Rosatom

State-owned miner NMDC is in preliminary discussions with Russian state nuclear corporation Rosatom to explore investments in lithium mining and processing projects in Russia, according to media reports citing three people familiar with the matter. The discussions are part of India’s efforts to diversify critical mineral supply chains and secure lithium for batteries and electric vehicles. NMDC officials visited Russia last month to attend a conference and held discussions with Rosatom representatives, the reports said. The miner is examining opportunities across lithium mining and processin..

Next Story
Infrastructure Urban

HCA Global Services Pre-leases 644,000 Sq Ft at Mindspace

HCA Global Services, the Indian subsidiary and Global Capability Centre (GCC) arm of US-based healthcare services provider HCA Healthcare, has pre-leased 644,000 sq ft of office space at Mindspace IT Park in Hyderabad for 10 years. The total rental commitment is estimated at Rs. 9.45 bn, according to documents accessed by Propstack. The office park is owned by Mindspace Business Parks REIT and leased by K Raheja IT Park (Hyderabad). The agreement covers 644,000 sq ft of chargeable area and 451,000 sq ft of carpet area across seven levels in Building 8. The premises include the lower ground flo..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

SPECIAL OFFER
QR Code