GERC Reserves Plea on Force Majeure for 280 MW Solar Project
POWER & RENEWABLE ENERGY

GERC Reserves Plea on Force Majeure for 280 MW Solar Project

The Gujarat Electricity Regulatory Commission (GERC) has reserved orders on two interlocutory applications filed by HR Sabarmati against Gujarat Urja Vikas Nigam (GUVNL) and Gujarat Energy Transmission Corporation (GETCO) over delays to a 280 MW solar project in Chharodi, Ahmedabad. The developer has sought protection from bank guarantee encashment and permission to add further force majeure grounds to its original petition.

HR Sabarmati signed a power purchase agreement with GUVNL on April 5, 2024, to supply 280 MW of solar power. The scheduled commencement of supply date was April 4, 2026. The developer attributed the delay to circumstances beyond its control and requested interim protection against contract termination, blacklisting and other coercive action while its extension petition remains pending.

Under Interim Application No. 79 of 2026, the company sought protection from the proposed encashment of performance bank guarantees worth Rs. 649.6 mn by GUVNL and connectivity bank guarantees worth Rs. 280 mn by GETCO. It cited nine force majeure events, including delays in land acquisition, right-of-way clearances and statutory approvals under Sections 68 and 164 of the Electricity Act, 2003. Unseasonal rainfall and flooding in Patan, Junagadh and Kheda during 2024 and 2025 were also cited.

The other grounds included security restrictions and labour migration during Operation Sindoor, uncertainty caused by changes to Gujarat’s stamp duty framework, alterations to district and taluka boundaries, and difficulties securing transmission connectivity. The developer also pointed to delays in finalising feeder bay locations and drawings at GETCO’s Bhesan substation, as well as supply chain disruption, raw material shortages and fuel price volatility linked to the West Asia conflict.

Through Interim Application No. 80 of 2026, HR Sabarmati sought to add the West Asia conflict as a force majeure event, referring to advisories from the Ministry of Finance and the Ministry of New and Renewable Energy. At the October 6 hearing, it said more than Rs. 5.93 bn had been invested and 35 MW had become operational. GUVNL and GETCO opposed relief, stating that bank guarantees were independent contractual obligations. Following Gujarat High Court directions, the GERC bench maintained the interim status quo and directed written submissions by October 13.

The Gujarat Electricity Regulatory Commission (GERC) has reserved orders on two interlocutory applications filed by HR Sabarmati against Gujarat Urja Vikas Nigam (GUVNL) and Gujarat Energy Transmission Corporation (GETCO) over delays to a 280 MW solar project in Chharodi, Ahmedabad. The developer has sought protection from bank guarantee encashment and permission to add further force majeure grounds to its original petition. HR Sabarmati signed a power purchase agreement with GUVNL on April 5, 2024, to supply 280 MW of solar power. The scheduled commencement of supply date was April 4, 2026. The developer attributed the delay to circumstances beyond its control and requested interim protection against contract termination, blacklisting and other coercive action while its extension petition remains pending. Under Interim Application No. 79 of 2026, the company sought protection from the proposed encashment of performance bank guarantees worth Rs. 649.6 mn by GUVNL and connectivity bank guarantees worth Rs. 280 mn by GETCO. It cited nine force majeure events, including delays in land acquisition, right-of-way clearances and statutory approvals under Sections 68 and 164 of the Electricity Act, 2003. Unseasonal rainfall and flooding in Patan, Junagadh and Kheda during 2024 and 2025 were also cited. The other grounds included security restrictions and labour migration during Operation Sindoor, uncertainty caused by changes to Gujarat’s stamp duty framework, alterations to district and taluka boundaries, and difficulties securing transmission connectivity. The developer also pointed to delays in finalising feeder bay locations and drawings at GETCO’s Bhesan substation, as well as supply chain disruption, raw material shortages and fuel price volatility linked to the West Asia conflict. Through Interim Application No. 80 of 2026, HR Sabarmati sought to add the West Asia conflict as a force majeure event, referring to advisories from the Ministry of Finance and the Ministry of New and Renewable Energy. At the October 6 hearing, it said more than Rs. 5.93 bn had been invested and 35 MW had become operational. GUVNL and GETCO opposed relief, stating that bank guarantees were independent contractual obligations. Following Gujarat High Court directions, the GERC bench maintained the interim status quo and directed written submissions by October 13.

Related Stories

Gold Stories

Next Story
Infrastructure Urban

DGTR Opens Anti-Dumping Probe into Aluminium Imports

The Directorate General of Trade Remedies (DGTR) has initiated a suo motu anti-dumping investigation into aluminium products imported from China, Malaysia, Vietnam and Thailand. The investigation follows concerns that increased imports from the four countries have caused injury to domestic manufacturers, particularly micro, small and medium enterprises (MSMEs). According to a DGTR notification dated November 9, the probe followed representations from the Aluminium Extrusion Manufacturers Association of India (ALEMAI). The association represents 228 manufacturers producing aluminium extrusion p..

Next Story
Infrastructure Urban

NMDC Explores Lithium Investments with Russia’s Rosatom

State-owned miner NMDC is in preliminary discussions with Russian state nuclear corporation Rosatom to explore investments in lithium mining and processing projects in Russia, according to media reports citing three people familiar with the matter. The discussions are part of India’s efforts to diversify critical mineral supply chains and secure lithium for batteries and electric vehicles. NMDC officials visited Russia last month to attend a conference and held discussions with Rosatom representatives, the reports said. The miner is examining opportunities across lithium mining and processin..

Next Story
Infrastructure Urban

HCA Global Services Pre-leases 644,000 Sq Ft at Mindspace

HCA Global Services, the Indian subsidiary and Global Capability Centre (GCC) arm of US-based healthcare services provider HCA Healthcare, has pre-leased 644,000 sq ft of office space at Mindspace IT Park in Hyderabad for 10 years. The total rental commitment is estimated at Rs. 9.45 bn, according to documents accessed by Propstack. The office park is owned by Mindspace Business Parks REIT and leased by K Raheja IT Park (Hyderabad). The agreement covers 644,000 sq ft of chargeable area and 451,000 sq ft of carpet area across seven levels in Building 8. The premises include the lower ground flo..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

SPECIAL OFFER
QR Code