Government to Bid Out 50 GW of Solar, Wind, and RTC Projects in FY24
POWER & RENEWABLE ENERGY

Government to Bid Out 50 GW of Solar, Wind, and RTC Projects in FY24

The Ministry of New and Renewable Energy (MNRE) has released a bidding calendar by agency for 50 GW of renewable energy projects for the current fiscal year (FY 2023-24).

The calendar calls for 30 GW of renewable capacity in the first two quarters and 20 GW in the last two.

SECI and NTPC will each issue tenders for 12.5 GW of solar/hybrid/round-the-clock (RTC) and 2.5 MW of wind projects. Tenders will be issued by NHPC and SJVN for 7.5 GW of solar/hybrid/RTC projects and 2.5 MW of wind projects, respectively.

The bids will be solicited in accordance with the government's standard bidding guidelines and the MNRE's instructions for renewable energy tenders.

MNRE has stated that it will issue renewable project bids worth 50 GW per year during fiscal years 2024-28, with at least 10 GW of wind tenders.

Renewable project developers have frequently petitioned the government for a predictable bidding trajectory in order to mitigate project risks, allow for more efficient financial planning and supply chain management, and provide better visibility and certainty for upcoming tenders.

They claim that the current haphazard tendering processes used by the federal and state governments make it difficult to plan finances and secure component supplies at competitive prices.

India has set ambitious renewable energy targets in order to combat climate change and reduce reliance on fossil fuels. The government has pledged to source 50% of its installed power capacity from non-fossil fuel-based energy sources by 2030 and reducing the emissions intensity of its GDP by 45% compared to 2005 levels.

Further, MNRE has been working to achieve 500 GW of installed electricity capacity from non-fossil sources by 2030, which includes 280 GW of solar. As of February 2023, India’s renewable energy installed capacity stands at nearly 169 GW, with 82.6 GW under implementation and 40.89 GW under the tendering process.

Also Read
Operations of construction waste plant in Rajarhat to begin operations
As demand for LCV rises, Mahindra & Mahindra to increase production

The Ministry of New and Renewable Energy (MNRE) has released a bidding calendar by agency for 50 GW of renewable energy projects for the current fiscal year (FY 2023-24). The calendar calls for 30 GW of renewable capacity in the first two quarters and 20 GW in the last two. SECI and NTPC will each issue tenders for 12.5 GW of solar/hybrid/round-the-clock (RTC) and 2.5 MW of wind projects. Tenders will be issued by NHPC and SJVN for 7.5 GW of solar/hybrid/RTC projects and 2.5 MW of wind projects, respectively. The bids will be solicited in accordance with the government's standard bidding guidelines and the MNRE's instructions for renewable energy tenders. MNRE has stated that it will issue renewable project bids worth 50 GW per year during fiscal years 2024-28, with at least 10 GW of wind tenders. Renewable project developers have frequently petitioned the government for a predictable bidding trajectory in order to mitigate project risks, allow for more efficient financial planning and supply chain management, and provide better visibility and certainty for upcoming tenders. They claim that the current haphazard tendering processes used by the federal and state governments make it difficult to plan finances and secure component supplies at competitive prices. India has set ambitious renewable energy targets in order to combat climate change and reduce reliance on fossil fuels. The government has pledged to source 50% of its installed power capacity from non-fossil fuel-based energy sources by 2030 and reducing the emissions intensity of its GDP by 45% compared to 2005 levels. Further, MNRE has been working to achieve 500 GW of installed electricity capacity from non-fossil sources by 2030, which includes 280 GW of solar. As of February 2023, India’s renewable energy installed capacity stands at nearly 169 GW, with 82.6 GW under implementation and 40.89 GW under the tendering process. Also Read Operations of construction waste plant in Rajarhat to begin operations As demand for LCV rises, Mahindra & Mahindra to increase production

Next Story
Resources

Jyoti Structures Launches Heat Safety Drive Across Sites

Jyoti Structures (JSL) has strengthened heat safety measures across its project sites and manufacturing facilities as temperatures rise across India. The company has implemented a Summer Safety Plan covering all transmission line projects to address risks related to heat stress, dehydration and worker fatigue.The initiative includes rescheduling work away from peak afternoon temperatures, provision of drinking water, ORS and lemon-salt solutions, and installation of rest shelters near work areas. Daily toolbox talks, worker health monitoring, first-aid preparedness, emergency transport arrange..

Next Story
Real Estate

MHADA Declares 82 Buildings Most Dangerous in Central and South Mumbai

The Maharashtra Housing and Area Development Authority (MHADA) has declared 82 buildings as most dangerous across Central and South Mumbai and has appealed to residents to vacate immediately. The list, prepared after structural assessments by the authority, identifies buildings judged to pose imminent risk to occupants and to passersby. Local civic bodies have been asked to coordinate evacuations and to make arrangements for temporary shelter and rehabilitation for displaced households. Officials said the authority prioritised buildings with visible structural distress, severe cracking, tiltin..

Next Story
Infrastructure Transport

Damage Reported At Halwara Airport Terminal After First Rains

Severe damage was reported at the terminal of Halwara Airport during the first major rain spell of the season, prompting immediate concern among aviation and local authorities. Images from the site showed water ingress and visible deterioration of the terminal interior, affecting passenger areas and ancillary services. The airport authority suspended certain operations temporarily to assess structural safety and ensure passenger wellbeing. Preliminary inspections have prioritised electrical systems and roof seals to prevent further water ingress. State aviation officials ordered a formal inqui..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement