+
Haryana seeks bids to procure 500 MW of solar power
POWER & RENEWABLE ENERGY

Haryana seeks bids to procure 500 MW of solar power

In order to deliver 500 MW of solar electricity from grid-connected solar projects in Haryana, the Haryana electricity Purchase Center (HPPC), a joint forum of the Uttar Haryana Bijli Vitran Nigam (UHBVN) and Dakshin Haryana Bijli Vitran Nigam (DHBVN), has issued an invitation for bids.

The deadline for submitting online bids is May 24, 2023. The following day, the bids will be opened. As a bid processing cost, bidders must deposit Rs 10 million ($121.87)/MW plus 18% GST. They must additionally provide an earnest money deposit of Rs 80 billions ($9,749/MW).

After issuing the Letter of Intent and prior to signing the power purchase agreement (PPA), the successful bidder will be required to provide a bank guarantee in the amount of $2 million (or $24,373/MW).

For the tender, HPPC has set a ceiling rate of 3.38 ($0.041)/kWh.

With the winning bids, HPPC will sign PPAs that will last 25 years from the solar projects' start of commercial operation.

After the PPA is signed, the solar developer has 18 months to complete the project.

According to the terms of the PPA that will be signed between the solar power developer and HPPC, the developer will be in charge of the design, financing, acquisition of land, engineering, acquisition, construction, operation, and maintenance of the projects. The 500 MW total capacity of the projects that will be chosen under this contract may be put anywhere in Haryana with a maximum of 10 MW coming from a single developer. To reduce technology risk and complete project commissioning on schedule, only commercially viable and operational technologies can be chosen.

The net worth of bidders should not be less than Rs 10 million ($121,866)/MW of the quoted capacity for the most recent fiscal year. Either bidders must have internal resource generation capability in the form of profit before depreciation, interest, and taxes for at least Rs 1 million (or $12,187)/MW of the quoted capacity during the previous financial year, or bidders must have a minimum annual turnover of at least Rs 5 million (or $60,933)/MW of the quoted capacity.

Alternatively, bidders must obtain a letter of in-principle approval from a lender committing a Line of Credit for at least $1.25 million (about $15,233) per MW of the specified capacity toward the project's need for working capital.

The winning bidder will be solely responsible for obtaining grid connectivity and ongoing access from the distribution firms. There should be a minimum declared yearly capacity utilization factor of 21%.

The solar modules that will be utilized for the projects must have a warranty for their peak output wattage, which cannot be less than 90% after ten years and 80% after 25 years from the planned start of commercial operation.

The Ministry of New and Renewable Energy's Approved List of Models and Manufacturers should be used to source the solar modules for the project.

To develop and commission 121 MW of grid-connected solar power projects at Faridabad (78 MW), Panipat (25 MW), and Yamuna Nagar (18 MW), the Haryana Power Generation Corporation issued a bid invitation in June of last year.

See also:
MSEDCL releases tender for 615 MW Solar Power Projects
Maharashtra seeks Bids for a 62 MW Solar Project

Your next big infra connection is waiting at RAHSTA 2025 – Asia’s Biggest Roads & Highways Expo, Jio World Convention Centre, Mumbai. Don’t miss out!

In order to deliver 500 MW of solar electricity from grid-connected solar projects in Haryana, the Haryana electricity Purchase Center (HPPC), a joint forum of the Uttar Haryana Bijli Vitran Nigam (UHBVN) and Dakshin Haryana Bijli Vitran Nigam (DHBVN), has issued an invitation for bids.The deadline for submitting online bids is May 24, 2023. The following day, the bids will be opened. As a bid processing cost, bidders must deposit Rs 10 million ($121.87)/MW plus 18% GST. They must additionally provide an earnest money deposit of Rs 80 billions ($9,749/MW). After issuing the Letter of Intent and prior to signing the power purchase agreement (PPA), the successful bidder will be required to provide a bank guarantee in the amount of $2 million (or $24,373/MW). For the tender, HPPC has set a ceiling rate of 3.38 ($0.041)/kWh. With the winning bids, HPPC will sign PPAs that will last 25 years from the solar projects' start of commercial operation. After the PPA is signed, the solar developer has 18 months to complete the project. According to the terms of the PPA that will be signed between the solar power developer and HPPC, the developer will be in charge of the design, financing, acquisition of land, engineering, acquisition, construction, operation, and maintenance of the projects. The 500 MW total capacity of the projects that will be chosen under this contract may be put anywhere in Haryana with a maximum of 10 MW coming from a single developer. To reduce technology risk and complete project commissioning on schedule, only commercially viable and operational technologies can be chosen. The net worth of bidders should not be less than Rs 10 million ($121,866)/MW of the quoted capacity for the most recent fiscal year. Either bidders must have internal resource generation capability in the form of profit before depreciation, interest, and taxes for at least Rs 1 million (or $12,187)/MW of the quoted capacity during the previous financial year, or bidders must have a minimum annual turnover of at least Rs 5 million (or $60,933)/MW of the quoted capacity. Alternatively, bidders must obtain a letter of in-principle approval from a lender committing a Line of Credit for at least $1.25 million (about $15,233) per MW of the specified capacity toward the project's need for working capital. The winning bidder will be solely responsible for obtaining grid connectivity and ongoing access from the distribution firms. There should be a minimum declared yearly capacity utilization factor of 21%. The solar modules that will be utilized for the projects must have a warranty for their peak output wattage, which cannot be less than 90% after ten years and 80% after 25 years from the planned start of commercial operation. The Ministry of New and Renewable Energy's Approved List of Models and Manufacturers should be used to source the solar modules for the project. To develop and commission 121 MW of grid-connected solar power projects at Faridabad (78 MW), Panipat (25 MW), and Yamuna Nagar (18 MW), the Haryana Power Generation Corporation issued a bid invitation in June of last year. See also: MSEDCL releases tender for 615 MW Solar Power ProjectsMaharashtra seeks Bids for a 62 MW Solar Project

Next Story
Infrastructure Transport

Rs 2.82 Billion Approved for NH-48 Flyovers, Footbridges

Gurugram’s section of National Highway 48 is set for a significant infrastructure upgrade, with the Central Government approving Rs 2.82 billion for the construction of four flyovers and nine foot overbridges along the Gurgaon–Kotputli–Jaipur corridor. This initiative aims to ease congestion, improve commuter safety, and boost regional connectivity, according to officials.The planned flyovers will be built at Panchgaon Chowk, Rathiwas, near the Hero Company, and Sahlawas. The nine foot overbridges will be constructed at Shikhopur, Manesar, Binola, Rathiwas, Malpura, Jaisinghpurkhera, Sid..

Next Story
Infrastructure Energy

VSL Wins Rs 810-Cr O&M Deal for 810 MWp NGEL Solar Assets

VSL Renewable Services has secured a Rs 810 crore operation and maintenance (O&M) contract for 810 MWp of NTPC Green Energy’s (NGEL) solar power projects spread across Andhra Pradesh, Madhya Pradesh, and Rajasthan. The contract duration is 36 months.The tender, issued in January 2025, was divided into two lots: Lot 1 for 1,054 MWp and Lot 2 for 810 MWp. VSL emerged as the lowest bidder in both categories, but was awarded only Lot 2 in accordance with NTPC’s tender guidelines.Advanced Monitoring and Tailored StrategiesThe O&M scope will employ artificial intelligence and Internet of..

Next Story
Infrastructure Energy

AP Issues Bid for Rs 34.9 Billion Battery Storage Project

The Transmission Corporation of Andhra Pradesh (APTRANSCO) has invited bids for the development of 1,000 MW/2,000 MWh battery energy storage systems (BESS) across seven substations in the state. The project, with an estimated viability gap funding of up to Rs 34.9 billion, will be executed under a build, own, and operate (BOO) model through tariff-based competitive bidding.Bid Timeline and StructureBids must be submitted by 29 September 2025 and will be opened on 6 October. The VGF support per project is capped at Rs 1.8 million per MWh and will be released in three instalments—20 per cent u..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Talk to us?