+
Haryana seeks bids to procure 500 MW of solar power
POWER & RENEWABLE ENERGY

Haryana seeks bids to procure 500 MW of solar power

In order to deliver 500 MW of solar electricity from grid-connected solar projects in Haryana, the Haryana electricity Purchase Center (HPPC), a joint forum of the Uttar Haryana Bijli Vitran Nigam (UHBVN) and Dakshin Haryana Bijli Vitran Nigam (DHBVN), has issued an invitation for bids.

The deadline for submitting online bids is May 24, 2023. The following day, the bids will be opened. As a bid processing cost, bidders must deposit Rs 10 million ($121.87)/MW plus 18% GST. They must additionally provide an earnest money deposit of Rs 80 billions ($9,749/MW).

After issuing the Letter of Intent and prior to signing the power purchase agreement (PPA), the successful bidder will be required to provide a bank guarantee in the amount of $2 million (or $24,373/MW).

For the tender, HPPC has set a ceiling rate of 3.38 ($0.041)/kWh.

With the winning bids, HPPC will sign PPAs that will last 25 years from the solar projects' start of commercial operation.

After the PPA is signed, the solar developer has 18 months to complete the project.

According to the terms of the PPA that will be signed between the solar power developer and HPPC, the developer will be in charge of the design, financing, acquisition of land, engineering, acquisition, construction, operation, and maintenance of the projects. The 500 MW total capacity of the projects that will be chosen under this contract may be put anywhere in Haryana with a maximum of 10 MW coming from a single developer. To reduce technology risk and complete project commissioning on schedule, only commercially viable and operational technologies can be chosen.

The net worth of bidders should not be less than Rs 10 million ($121,866)/MW of the quoted capacity for the most recent fiscal year. Either bidders must have internal resource generation capability in the form of profit before depreciation, interest, and taxes for at least Rs 1 million (or $12,187)/MW of the quoted capacity during the previous financial year, or bidders must have a minimum annual turnover of at least Rs 5 million (or $60,933)/MW of the quoted capacity.

Alternatively, bidders must obtain a letter of in-principle approval from a lender committing a Line of Credit for at least $1.25 million (about $15,233) per MW of the specified capacity toward the project's need for working capital.

The winning bidder will be solely responsible for obtaining grid connectivity and ongoing access from the distribution firms. There should be a minimum declared yearly capacity utilization factor of 21%.

The solar modules that will be utilized for the projects must have a warranty for their peak output wattage, which cannot be less than 90% after ten years and 80% after 25 years from the planned start of commercial operation.

The Ministry of New and Renewable Energy's Approved List of Models and Manufacturers should be used to source the solar modules for the project.

To develop and commission 121 MW of grid-connected solar power projects at Faridabad (78 MW), Panipat (25 MW), and Yamuna Nagar (18 MW), the Haryana Power Generation Corporation issued a bid invitation in June of last year.

See also:
MSEDCL releases tender for 615 MW Solar Power Projects
Maharashtra seeks Bids for a 62 MW Solar Project

In order to deliver 500 MW of solar electricity from grid-connected solar projects in Haryana, the Haryana electricity Purchase Center (HPPC), a joint forum of the Uttar Haryana Bijli Vitran Nigam (UHBVN) and Dakshin Haryana Bijli Vitran Nigam (DHBVN), has issued an invitation for bids.The deadline for submitting online bids is May 24, 2023. The following day, the bids will be opened. As a bid processing cost, bidders must deposit Rs 10 million ($121.87)/MW plus 18% GST. They must additionally provide an earnest money deposit of Rs 80 billions ($9,749/MW). After issuing the Letter of Intent and prior to signing the power purchase agreement (PPA), the successful bidder will be required to provide a bank guarantee in the amount of $2 million (or $24,373/MW). For the tender, HPPC has set a ceiling rate of 3.38 ($0.041)/kWh. With the winning bids, HPPC will sign PPAs that will last 25 years from the solar projects' start of commercial operation. After the PPA is signed, the solar developer has 18 months to complete the project. According to the terms of the PPA that will be signed between the solar power developer and HPPC, the developer will be in charge of the design, financing, acquisition of land, engineering, acquisition, construction, operation, and maintenance of the projects. The 500 MW total capacity of the projects that will be chosen under this contract may be put anywhere in Haryana with a maximum of 10 MW coming from a single developer. To reduce technology risk and complete project commissioning on schedule, only commercially viable and operational technologies can be chosen. The net worth of bidders should not be less than Rs 10 million ($121,866)/MW of the quoted capacity for the most recent fiscal year. Either bidders must have internal resource generation capability in the form of profit before depreciation, interest, and taxes for at least Rs 1 million (or $12,187)/MW of the quoted capacity during the previous financial year, or bidders must have a minimum annual turnover of at least Rs 5 million (or $60,933)/MW of the quoted capacity. Alternatively, bidders must obtain a letter of in-principle approval from a lender committing a Line of Credit for at least $1.25 million (about $15,233) per MW of the specified capacity toward the project's need for working capital. The winning bidder will be solely responsible for obtaining grid connectivity and ongoing access from the distribution firms. There should be a minimum declared yearly capacity utilization factor of 21%. The solar modules that will be utilized for the projects must have a warranty for their peak output wattage, which cannot be less than 90% after ten years and 80% after 25 years from the planned start of commercial operation. The Ministry of New and Renewable Energy's Approved List of Models and Manufacturers should be used to source the solar modules for the project. To develop and commission 121 MW of grid-connected solar power projects at Faridabad (78 MW), Panipat (25 MW), and Yamuna Nagar (18 MW), the Haryana Power Generation Corporation issued a bid invitation in June of last year. See also: MSEDCL releases tender for 615 MW Solar Power ProjectsMaharashtra seeks Bids for a 62 MW Solar Project

Next Story
Infrastructure Urban

Naidu Seeks Rs 563 Crore For AP Sports Infrastructure

Andhra Pradesh Chief Minister N Chandrababu Naidu has sought Rs 563 crore from the Centre to boost sports infrastructure in the state, including Rs 538 crore for stadium development and Rs 25 crore to host the Khelo India Martial Arts Games 2025. Naidu made the request during a meeting with Union Youth Services and Sports Minister Mansukh Mandaviya in New Delhi on Wednesday.The CM urged early completion of Khelo India infrastructure projects in Tirupati, Rajahmundry, Kakinada, and Narasaraopeta, and called for an international-standard badminton training centre and a national aquatic sports hu..

Next Story
Infrastructure Transport

Tough Bidding Norms Slow NHAI Road Project Awards

Stringent bidding rules imposed by the Ministry of Road Transport & Highways (MoRTH) have led to a slowdown in project awards by the National Highways Authority of India (NHAI), despite a robust Rs 3.5 trillion pipeline. According to an HDFC Securities report, the shift to more cautious developer models now favours firms with strong balance sheets, as tighter qualification norms limit aggressive bidders.The revised norms mandate additional performance security, targeting the exclusion of players that previously submitted low bids—often 25 to 40 per cent below NHAI cost estimates—raisin..

Next Story
Infrastructure Transport

Mumbai Gets Coastal Nod for Next Promenade Phase

As Mumbai prepares to open two major sections of its expansive seafront promenade this week, the city’s civic authority has secured a key coastal clearance to advance further construction. The Maharashtra Coastal Zone Management Authority (MCZMA) has approved the commencement of work on the segment between Haji Ali and Baroda Palace, with tendering expected soon after project cost assessments.The promenade, stretching 7.5 km in length and 20 metres wide, is being designed as a flagship open space for walkers, joggers, and cyclists. Two critical stretches—2.75 km from Tata Garden to Haji Al..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Talk to us?