+
PGCIL & DRAIPL Secure 3.5 GW Renewable Project in Rajasthan
POWER & RENEWABLE ENERGY

PGCIL & DRAIPL Secure 3.5 GW Renewable Project in Rajasthan

The Power Grid Corporation of India (PGCIL) and Dineshchandra R Agarwal Infracon (DRAIPL) have secured Parts A and B of the transmission project initiated by REC Power Development and Consultancy (RECPDCL) to facilitate the evacuation of 3.5 GW of power from Rajasthan's renewable energy zone. This project was awarded under tariff-based competitive bidding on a build, own, operate, and transfer (BOOT) basis.

The tender for the project was issued in July 2024.

PGCIL emerged as the successful bidder among competitors such as Sterlite Grid 32 and Adani Energy Solutions. The project involves setting up a 765/400 kV substation near Ghiror in Mainpuri district, Uttar Pradesh, constructing 765 kV and 400 kV transmission lines across Rajasthan and Uttar Pradesh, and enhancing existing substations in both states.

DRAIPL won Part B, competing with PGCIL, Sterlite Grid 32, and Adani Energy Solutions. This segment involves establishing a 765/400 kV, 2×1500 MVA substation near Merta (Merta-II Substation) with 2×240 MVAr (765 kV) and 2×125 MVAr (420 kV) bus reactors.

For both Parts A and B, the project includes tasks such as planning, financing, obtaining permits, land acquisition, designing, engineering, procuring materials, construction, testing, commissioning, and maintaining the transmission system.

The Ministry of New and Renewable Energy, in collaboration with the Solar Energy Corporation of India, has identified renewable energy zones with a total capacity of 181.5 GW across eight states for implementation by 2030. Rajasthan alone has a renewable energy potential of 75 GW, comprising 15 GW of wind energy and 60 GW of solar energy.

The Power Grid Corporation of India (PGCIL) and Dineshchandra R Agarwal Infracon (DRAIPL) have secured Parts A and B of the transmission project initiated by REC Power Development and Consultancy (RECPDCL) to facilitate the evacuation of 3.5 GW of power from Rajasthan's renewable energy zone. This project was awarded under tariff-based competitive bidding on a build, own, operate, and transfer (BOOT) basis. The tender for the project was issued in July 2024. PGCIL emerged as the successful bidder among competitors such as Sterlite Grid 32 and Adani Energy Solutions. The project involves setting up a 765/400 kV substation near Ghiror in Mainpuri district, Uttar Pradesh, constructing 765 kV and 400 kV transmission lines across Rajasthan and Uttar Pradesh, and enhancing existing substations in both states. DRAIPL won Part B, competing with PGCIL, Sterlite Grid 32, and Adani Energy Solutions. This segment involves establishing a 765/400 kV, 2×1500 MVA substation near Merta (Merta-II Substation) with 2×240 MVAr (765 kV) and 2×125 MVAr (420 kV) bus reactors. For both Parts A and B, the project includes tasks such as planning, financing, obtaining permits, land acquisition, designing, engineering, procuring materials, construction, testing, commissioning, and maintaining the transmission system. The Ministry of New and Renewable Energy, in collaboration with the Solar Energy Corporation of India, has identified renewable energy zones with a total capacity of 181.5 GW across eight states for implementation by 2030. Rajasthan alone has a renewable energy potential of 75 GW, comprising 15 GW of wind energy and 60 GW of solar energy.

Next Story
Infrastructure Transport

MMRDA Installs 325-Tonne Steel Spans on Mumbai Metro Line 4

The Mumbai Metropolitan Region Development Authority (MMRDA) has achieved a key construction milestone on Metro Line 4 with the successful installation of three large steel spans at Bhandup West during overnight operations.The spans, together weighing 325 metric tonnes, were launched using eight heavy-duty cranes and 12 multi-axle vehicles. The operation required precise engineering and meticulous planning to minimise disruption in the densely populated suburban area.Due to effective inter-agency coordination, the work—originally scheduled across four nights—was completed within just two n..

Next Story
Infrastructure Transport

CMRL Targets March 2027 Opening for Vadapalani–Panagal Park

Chennai Metro Rail Limited (CMRL) is progressing as scheduled to open the Vadapalani–Panagal Park section of Phase II’s Corridor 4 by March 2027. The 3.5 km underground stretch is part of the 26.1 km Corridor 4 connecting Lighthouse with Poonamallee Bypass.Construction activities are advancing steadily, with tunnelling works between Vadapalani and Panagal Park already completed. Track-laying operations are expected to commence shortly. At Panagal Park station, structural works have reached the concourse and platform levels, while excavation continues at the lowest level.CMRL is also consid..

Next Story
Infrastructure Transport

Maha-Metro Invites Pune Metro Civil Maintenance Bids

Maharashtra Metro Rail Corporation Limited (Maha-Metro) has invited bids for the annual civil maintenance contract of the Pune Metro Rail Project. The tender, bearing ID and number P1-O&M-20/2025, is scheduled to close on 23 February 2026, with a pre-bid meeting slated for 10 February 2026. The earnest money deposit (EMD) for the contract is Rs 3,50,500, and the duration of the contract is one year.The scope of work includes annual civil maintenance of 28 elevated and underground stations, 28.079 km of elevated viaduct including steel bridges, 12.15 km of tunnels, and two depots under the ..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Open In App