Rithwik Projects to construct Sunni Dam Hydro Project of SJVN
POWER & RENEWABLE ENERGY

Rithwik Projects to construct Sunni Dam Hydro Project of SJVN

At Rs 10.98 billion, Rithwik Projects will construct the 382 MW Sunni Dam hydropower project for the government-run SJVN Ltd. According to an SJVN statement, the company signed the Contract Agreement for the engineering, procurement, and construction of the civil and hydro-mechanical works of the 382 MW Sunni Dam Hydro Power Project.

The letter of award for the civil and hydro mechanical works was released on January 14, 2023, according to Sharma's briefing. Following the fulfilment of all prerequisites, the contract agreement for the same has been signed.

Sharma emphasised that the project's different civil components are currently undergoing full-scale construction. Infrastructure is being built at full speed to allow for timely project execution, and significant contractors are being mobilised at the project site.

This project is expected to be finished in 58 months, or by November 2027.

SJVN's General Manager S K Bhargava and Rithwik Pvt. Ltd.'s Dy General Manager V Praveen signed the contract agreement. SJVN Limited's Director (Personnel) Geeta Kapur, Director (Finance) AK Singh, Director (Electrical) Sushil Sharma, and senior SJVN & Rithwik Pvt. Ltd. officials were also present.

The 382 MW Sunni Dam Project is a run-of-the-river project on the Satluj River in Himachal Pradesh's districts of Shimla and Mandi. The project will generate 1382 million units per year at a levelized tariff of Rs. 3.90 per unit and will reduce carbon emissions by 1.1 million tons per year.

After commissioning, the government of Himachal Pradesh will receive 13 percent of the electricity generated for free, with the remaining 1 percent going to the Local Area Development Fund. This free power translates into Rs 28.3 billion in benefits to Himachal Pradesh over the project's 40-year life cycle. The project's development will result in the creation of community assets and the development of infrastructure. Around 4000 people will be employed directly or indirectly as a result of project construction activities. This will contribute to the overall socioeconomic development of Himachal Pradesh.

See also:
Cabinet approves NHPC's investment in India's largest hydro project
Power Min informs 39 hydro projects being implemented, 9 stalled


At Rs 10.98 billion, Rithwik Projects will construct the 382 MW Sunni Dam hydropower project for the government-run SJVN Ltd. According to an SJVN statement, the company signed the Contract Agreement for the engineering, procurement, and construction of the civil and hydro-mechanical works of the 382 MW Sunni Dam Hydro Power Project. The letter of award for the civil and hydro mechanical works was released on January 14, 2023, according to Sharma's briefing. Following the fulfilment of all prerequisites, the contract agreement for the same has been signed. Sharma emphasised that the project's different civil components are currently undergoing full-scale construction. Infrastructure is being built at full speed to allow for timely project execution, and significant contractors are being mobilised at the project site. This project is expected to be finished in 58 months, or by November 2027. SJVN's General Manager S K Bhargava and Rithwik Pvt. Ltd.'s Dy General Manager V Praveen signed the contract agreement. SJVN Limited's Director (Personnel) Geeta Kapur, Director (Finance) AK Singh, Director (Electrical) Sushil Sharma, and senior SJVN & Rithwik Pvt. Ltd. officials were also present. The 382 MW Sunni Dam Project is a run-of-the-river project on the Satluj River in Himachal Pradesh's districts of Shimla and Mandi. The project will generate 1382 million units per year at a levelized tariff of Rs. 3.90 per unit and will reduce carbon emissions by 1.1 million tons per year. After commissioning, the government of Himachal Pradesh will receive 13 percent of the electricity generated for free, with the remaining 1 percent going to the Local Area Development Fund. This free power translates into Rs 28.3 billion in benefits to Himachal Pradesh over the project's 40-year life cycle. The project's development will result in the creation of community assets and the development of infrastructure. Around 4000 people will be employed directly or indirectly as a result of project construction activities. This will contribute to the overall socioeconomic development of Himachal Pradesh. See also: Cabinet approves NHPC's investment in India's largest hydro projectPower Min informs 39 hydro projects being implemented, 9 stalled

Related Stories

Gold Stories

Next Story
Products

Koemmerling opens Navi Mumbai experience centre

Koemmerling, a brand of the profine Group, has expanded its presence in the Mumbai metropolitan region with the opening of a new experience centre in Navi Mumbai and launched its Allure S46 minimal sliding door system for the Indian market.Located in CBD Belapur, the facility was inaugurated by Peter Mrosik, Owner and CEO, profine Group, along with Farid Khan, Chairman and Managing Director, profine India, and Kamal Bajaj, CEO, profine India.The company said the new centre will showcase its portfolio of uPVC and aluminium window and door systems to architects, developers and homeowners.The ina..

Next Story
Products

India's waterproofing market nears Rs 150 bn milestone

India's waterproofing industry is approaching a market size of Rs 150 billion and is expected to surpass the $2 billion milestone, according to speakers at the 2nd India International Waterproofers Conference & Expo 2026 organised by the Waterproofers Association of India (WAI) in New Delhi.The two-day event brought together more than 20 speakers, 55 international delegates and 53 exhibition booths, with discussions focusing on climate-resilient construction, advanced waterproofing technologies and international collaboration.Inaugurating the event, Durga Shanker Mishra, former Secretary, ..

Next Story
Real Estate

Dilip Buildcon Q1 FY27 Revenue at Rs 23.78 billion

Dilip Buildcon Limited reported consolidated revenue from operations of Rs 2,378 crore in Q1 FY27, along with EBITDA of Rs 429 crore and profit after tax of Rs 128 crore.Consolidated EBITDA margin stood at 18.1%, improving from 17.1% in Q4 FY26. On a standalone basis, revenue from operations was Rs 1,930 crore, EBITDA stood at Rs 199 crore and PAT was Rs 39 crore, with an EBITDA margin of 10.3%.The company’s order book stood at Rs 27,691 crore as of 30 June 2026, compared with Rs 28,830 crore as of 31 March 2026. Roads and highways accounted for 17.1% of the order book, irrigation and water ..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement