Rithwik Projects to construct Sunni Dam Hydro Project of SJVN
POWER & RENEWABLE ENERGY

Rithwik Projects to construct Sunni Dam Hydro Project of SJVN

At Rs 10.98 billion, Rithwik Projects will construct the 382 MW Sunni Dam hydropower project for the government-run SJVN Ltd. According to an SJVN statement, the company signed the Contract Agreement for the engineering, procurement, and construction of the civil and hydro-mechanical works of the 382 MW Sunni Dam Hydro Power Project.

The letter of award for the civil and hydro mechanical works was released on January 14, 2023, according to Sharma's briefing. Following the fulfilment of all prerequisites, the contract agreement for the same has been signed.

Sharma emphasised that the project's different civil components are currently undergoing full-scale construction. Infrastructure is being built at full speed to allow for timely project execution, and significant contractors are being mobilised at the project site.

This project is expected to be finished in 58 months, or by November 2027.

SJVN's General Manager S K Bhargava and Rithwik Pvt. Ltd.'s Dy General Manager V Praveen signed the contract agreement. SJVN Limited's Director (Personnel) Geeta Kapur, Director (Finance) AK Singh, Director (Electrical) Sushil Sharma, and senior SJVN & Rithwik Pvt. Ltd. officials were also present.

The 382 MW Sunni Dam Project is a run-of-the-river project on the Satluj River in Himachal Pradesh's districts of Shimla and Mandi. The project will generate 1382 million units per year at a levelized tariff of Rs. 3.90 per unit and will reduce carbon emissions by 1.1 million tons per year.

After commissioning, the government of Himachal Pradesh will receive 13 percent of the electricity generated for free, with the remaining 1 percent going to the Local Area Development Fund. This free power translates into Rs 28.3 billion in benefits to Himachal Pradesh over the project's 40-year life cycle. The project's development will result in the creation of community assets and the development of infrastructure. Around 4000 people will be employed directly or indirectly as a result of project construction activities. This will contribute to the overall socioeconomic development of Himachal Pradesh.

See also:
Cabinet approves NHPC's investment in India's largest hydro project
Power Min informs 39 hydro projects being implemented, 9 stalled


At Rs 10.98 billion, Rithwik Projects will construct the 382 MW Sunni Dam hydropower project for the government-run SJVN Ltd. According to an SJVN statement, the company signed the Contract Agreement for the engineering, procurement, and construction of the civil and hydro-mechanical works of the 382 MW Sunni Dam Hydro Power Project. The letter of award for the civil and hydro mechanical works was released on January 14, 2023, according to Sharma's briefing. Following the fulfilment of all prerequisites, the contract agreement for the same has been signed. Sharma emphasised that the project's different civil components are currently undergoing full-scale construction. Infrastructure is being built at full speed to allow for timely project execution, and significant contractors are being mobilised at the project site. This project is expected to be finished in 58 months, or by November 2027. SJVN's General Manager S K Bhargava and Rithwik Pvt. Ltd.'s Dy General Manager V Praveen signed the contract agreement. SJVN Limited's Director (Personnel) Geeta Kapur, Director (Finance) AK Singh, Director (Electrical) Sushil Sharma, and senior SJVN & Rithwik Pvt. Ltd. officials were also present. The 382 MW Sunni Dam Project is a run-of-the-river project on the Satluj River in Himachal Pradesh's districts of Shimla and Mandi. The project will generate 1382 million units per year at a levelized tariff of Rs. 3.90 per unit and will reduce carbon emissions by 1.1 million tons per year. After commissioning, the government of Himachal Pradesh will receive 13 percent of the electricity generated for free, with the remaining 1 percent going to the Local Area Development Fund. This free power translates into Rs 28.3 billion in benefits to Himachal Pradesh over the project's 40-year life cycle. The project's development will result in the creation of community assets and the development of infrastructure. Around 4000 people will be employed directly or indirectly as a result of project construction activities. This will contribute to the overall socioeconomic development of Himachal Pradesh. See also: Cabinet approves NHPC's investment in India's largest hydro projectPower Min informs 39 hydro projects being implemented, 9 stalled

Next Story
Equipment

Handling concrete better

Efficiently handling the transportation and placement of concrete is essential to help maintain the quality of construction, meet project timelines by minimising downtimes, and reduce costs – by 5 to 15 per cent, according to Sandeep Jain, Director, Arkade Developers. CW explores what the efficient handling of concrete entails.Select wellFirst, a word on choosing the right equipment, such as a mixer with a capacity aligned to the volume required onsite, from Vaibhav Kulkarni, Concrete Expert. “An overly large mixer will increase the idle time (and cost), while one that ..

Next Story
Real Estate

Elevated floors!

Raised access flooring, also called false flooring, is a less common interiors feature than false ceilings, but it has as many uses – if not more.A raised floor is a modular panel installed above the structural floor. The space beneath the raised flooring is typically used to accommodate utilities such as electrical cables, plumbing and HVAC systems. And so, raised flooring is usually associated with buildings with heavy cabling and precise air distribution needs, such as data centres.That said, CW interacted with designers and architects and discovered that false flooring can come in handy ..

Next Story
Infrastructure Urban

The Variation Challenge

A variation or change in scope clause is defined in construction contracts to take care of situations arising from change in the defined scope of work. Such changes may arise due to factors such as additions or deletions in the scope of work, modifications in the type, grade or specifications of materials, alterations in specifications or drawings, and acts or omissions of other contractors. Further, ineffective planning, inadequate investigations or surveys and requests from the employer or those within the project’s area of influence can contribute to changes in the scope of work. Ext..

Advertisement

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Advertisement

Talk to us?