Rithwik Projects to construct Sunni Dam Hydro Project of SJVN
POWER & RENEWABLE ENERGY

Rithwik Projects to construct Sunni Dam Hydro Project of SJVN

At Rs 10.98 billion, Rithwik Projects will construct the 382 MW Sunni Dam hydropower project for the government-run SJVN Ltd. According to an SJVN statement, the company signed the Contract Agreement for the engineering, procurement, and construction of the civil and hydro-mechanical works of the 382 MW Sunni Dam Hydro Power Project.

The letter of award for the civil and hydro mechanical works was released on January 14, 2023, according to Sharma's briefing. Following the fulfilment of all prerequisites, the contract agreement for the same has been signed.

Sharma emphasised that the project's different civil components are currently undergoing full-scale construction. Infrastructure is being built at full speed to allow for timely project execution, and significant contractors are being mobilised at the project site.

This project is expected to be finished in 58 months, or by November 2027.

SJVN's General Manager S K Bhargava and Rithwik Pvt. Ltd.'s Dy General Manager V Praveen signed the contract agreement. SJVN Limited's Director (Personnel) Geeta Kapur, Director (Finance) AK Singh, Director (Electrical) Sushil Sharma, and senior SJVN & Rithwik Pvt. Ltd. officials were also present.

The 382 MW Sunni Dam Project is a run-of-the-river project on the Satluj River in Himachal Pradesh's districts of Shimla and Mandi. The project will generate 1382 million units per year at a levelized tariff of Rs. 3.90 per unit and will reduce carbon emissions by 1.1 million tons per year.

After commissioning, the government of Himachal Pradesh will receive 13 percent of the electricity generated for free, with the remaining 1 percent going to the Local Area Development Fund. This free power translates into Rs 28.3 billion in benefits to Himachal Pradesh over the project's 40-year life cycle. The project's development will result in the creation of community assets and the development of infrastructure. Around 4000 people will be employed directly or indirectly as a result of project construction activities. This will contribute to the overall socioeconomic development of Himachal Pradesh.

See also:
Cabinet approves NHPC's investment in India's largest hydro project
Power Min informs 39 hydro projects being implemented, 9 stalled


At Rs 10.98 billion, Rithwik Projects will construct the 382 MW Sunni Dam hydropower project for the government-run SJVN Ltd. According to an SJVN statement, the company signed the Contract Agreement for the engineering, procurement, and construction of the civil and hydro-mechanical works of the 382 MW Sunni Dam Hydro Power Project. The letter of award for the civil and hydro mechanical works was released on January 14, 2023, according to Sharma's briefing. Following the fulfilment of all prerequisites, the contract agreement for the same has been signed. Sharma emphasised that the project's different civil components are currently undergoing full-scale construction. Infrastructure is being built at full speed to allow for timely project execution, and significant contractors are being mobilised at the project site. This project is expected to be finished in 58 months, or by November 2027. SJVN's General Manager S K Bhargava and Rithwik Pvt. Ltd.'s Dy General Manager V Praveen signed the contract agreement. SJVN Limited's Director (Personnel) Geeta Kapur, Director (Finance) AK Singh, Director (Electrical) Sushil Sharma, and senior SJVN & Rithwik Pvt. Ltd. officials were also present. The 382 MW Sunni Dam Project is a run-of-the-river project on the Satluj River in Himachal Pradesh's districts of Shimla and Mandi. The project will generate 1382 million units per year at a levelized tariff of Rs. 3.90 per unit and will reduce carbon emissions by 1.1 million tons per year. After commissioning, the government of Himachal Pradesh will receive 13 percent of the electricity generated for free, with the remaining 1 percent going to the Local Area Development Fund. This free power translates into Rs 28.3 billion in benefits to Himachal Pradesh over the project's 40-year life cycle. The project's development will result in the creation of community assets and the development of infrastructure. Around 4000 people will be employed directly or indirectly as a result of project construction activities. This will contribute to the overall socioeconomic development of Himachal Pradesh. See also: Cabinet approves NHPC's investment in India's largest hydro projectPower Min informs 39 hydro projects being implemented, 9 stalled

Next Story
Technology

AI-Enabled Workflows Lift Profitability and Productivity

Organisations modernising frontline workflows with artificial intelligence, automation and real-time data are reporting stronger financial performance, higher productivity and improved employee engagement, according to a global study by Zebra Technologies and Oxford Economics.The research covered 1,000 senior leaders across retail, manufacturing, transportation and logistics in the US, Mexico, the UK, Germany, India, Japan, Australia and New Zealand.In transportation and logistics, 54 per cent of companies that improved picking and packing operations reported faster operational performance, wh..

Next Story
Real Estate

India Leads Global AI Readiness but Implementation Lags

Indian companies lead global averages across all eight artificial intelligence readiness indicators tracked by JLL, but only 19 per cent have started making changes to their workplaces, according to the JLL 2026 Future of Work Survey.The study found that 77 per cent of Indian business leaders expect AI to change their office requirements, creating a 58-percentage-point gap between awareness and implementation. The survey covered more than 2,200 CEOs, CFOs and real estate leaders across 21 countries during the first quarter of 2026.Despite concerns over automation, 58 per cent of Indian leaders..

Next Story
Equipment

Three WOLFF Cranes Build Riyadh Cable-Stayed Bridges

Three WOLFF 180 B luffing jib cranes are supporting the construction of two cable-stayed bridges alongside the existing Wadi Laban Bridge in Riyadh, Saudi Arabia. The project is being developed for the Royal Commission for Riyadh City and executed by the ICRC joint venture comprising IC Ictas and Al Rashid Trading & Contracting Company.The cranes are handling lifting operations including formwork, reinforcement, concrete placement, work platforms, surveying equipment and other construction materials. Each crane is fitted with a 40 m jib, reaches a hook height of 157 m and offers a maximum ..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement