Ghaziabad's PMAY Housing Projects Yet to Deliver
Real Estate

Ghaziabad's PMAY Housing Projects Yet to Deliver

Ghaziabad’s flagship Pradhan Mantri Awas Yojana (PMAY), aimed at providing affordable housing for economically weaker sections, has completed a decade without delivering a single unit to beneficiaries. Delays have plagued both private developers and government-run projects, leaving allottees in limbo. Under PMAY, the Ghaziabad Development Authority (GDA) was tasked with building 3,550 units in its colonies, while private developers were to construct 6,150 units across various projects. Despite 2,000 units being ready in GDA schemes such as Madhuban Bapudham and Dasna, essential amenities like electricity, water, sewer connections, and approach roads remain incomplete, delaying handovers. A senior GDA official stated, “We’ve sought assistance from various departments for infrastructure, but progress has stalled due to pending state government funding.” Meanwhile, none of the 6,150 units promised by private developers have been delivered. While some builders claim near-completion, others continue to lag behind. The GDA has issued notices to expedite these projects. The Confederation of Real Estate Developers' Associations of India (CREDAI) partly blames the government, citing insufficient initial incentives for builders. Although recent rule relaxations have encouraged participation, challenges persist. The GDA revised the cost of PMAY units in 2021, increasing the price from Rs 400,000 to Rs 600,000, with central and state government subsidies covering Rs 250,000 and Rs 100,000, respectively. Beneficiaries are required to pay the remaining Rs 250,000. Beyond PMAY, group housing developers are mandated to allocate 10% of their flats for economically weaker sections (EWS) and 10% for low-income groups (LIG). However, compliance has been poor, with only 1,717 EWS and 1,255 LIG flats constructed out of a combined target of 9,720 units. CREDAI-NCR secretary Gaurav Gupta highlighted rising land, construction, and labour costs as barriers to affordable housing viability, urging the government to revise the price cap of Rs 4.5 million under affordable housing schemes. GDA’s former town planner pointed out that developers receive incentives, such as additional Floor Area Ratio (FAR) and exemptions for smaller projects, in exchange for a shelter fee. However, CREDAI deemed these benefits “cosmetic,” emphasising the need for more substantial reforms to boost affordable housing delivery. (ET)

Ghaziabad’s flagship Pradhan Mantri Awas Yojana (PMAY), aimed at providing affordable housing for economically weaker sections, has completed a decade without delivering a single unit to beneficiaries. Delays have plagued both private developers and government-run projects, leaving allottees in limbo. Under PMAY, the Ghaziabad Development Authority (GDA) was tasked with building 3,550 units in its colonies, while private developers were to construct 6,150 units across various projects. Despite 2,000 units being ready in GDA schemes such as Madhuban Bapudham and Dasna, essential amenities like electricity, water, sewer connections, and approach roads remain incomplete, delaying handovers. A senior GDA official stated, “We’ve sought assistance from various departments for infrastructure, but progress has stalled due to pending state government funding.” Meanwhile, none of the 6,150 units promised by private developers have been delivered. While some builders claim near-completion, others continue to lag behind. The GDA has issued notices to expedite these projects. The Confederation of Real Estate Developers' Associations of India (CREDAI) partly blames the government, citing insufficient initial incentives for builders. Although recent rule relaxations have encouraged participation, challenges persist. The GDA revised the cost of PMAY units in 2021, increasing the price from Rs 400,000 to Rs 600,000, with central and state government subsidies covering Rs 250,000 and Rs 100,000, respectively. Beneficiaries are required to pay the remaining Rs 250,000. Beyond PMAY, group housing developers are mandated to allocate 10% of their flats for economically weaker sections (EWS) and 10% for low-income groups (LIG). However, compliance has been poor, with only 1,717 EWS and 1,255 LIG flats constructed out of a combined target of 9,720 units. CREDAI-NCR secretary Gaurav Gupta highlighted rising land, construction, and labour costs as barriers to affordable housing viability, urging the government to revise the price cap of Rs 4.5 million under affordable housing schemes. GDA’s former town planner pointed out that developers receive incentives, such as additional Floor Area Ratio (FAR) and exemptions for smaller projects, in exchange for a shelter fee. However, CREDAI deemed these benefits “cosmetic,” emphasising the need for more substantial reforms to boost affordable housing delivery. (ET)

Next Story
Infrastructure Urban

Panasonic Showcases Connected Display Solutions

Panasonic Life Solutions India showcased its integrated display, projection, broadcast and communication technologies at Panasonic Tech Summit 2026 in New Delhi. Hosted through its System Solutions Division, the two-day event highlighted connected technology solutions for education, healthcare, retail, transportation, corporate offices and entertainment.The summit, themed ‘Turning Technology into Value’, featured experience-led zones covering QSR, retail, transit, corporate offices, healthcare, education, security, projection, home theatre and professional displays. Panasonic also introduc..

Next Story
Infrastructure Transport

Kapsch to Deliver India’s First C-ITS Project

"Kapsch TrafficCom will deliver India’s first Cooperative Intelligent Transport Systems project on a key expressway near New Delhi. The project will be implemented with Superwave Communication And Infrasolution Limited to demonstrate how connected mobility can improve road safety and traffic efficiency.The pilot will use real-time connectivity and AI-enabled situational awareness to support road users, especially in high-risk areas such as temporary work zones. Drivers will receive alerts on roadworks, maintenance vehicles, hazardous locations, traffic queues and temporary virtual signage di..

Next Story
Infrastructure Urban

Eurobond Net Profit Rises 44 Per Cent

Euro Panel Products, the parent company of Eurobond, reported a 44.13 per cent year-on-year rise in net profit for FY25–26. The company’s revenue from operations grew 18.91 per cent to Rs 503.20 crore, compared to Rs 423.18 crore in the previous financial year.The company’s full-year EBITDA stood at Rs 56.67 crore, marking a 31.82 per cent increase. Profit after tax rose to Rs 26.56 crore, while net worth increased 20.15 per cent to Rs 160.07 crore. Earnings per share for the year stood at Rs 10.84.Divyam Rajesh Shah, Whole Time Director and CFO, Euro Panel Products, said the company’s..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

-->