+
Ghaziabad's PMAY Housing Projects Yet to Deliver
Real Estate

Ghaziabad's PMAY Housing Projects Yet to Deliver

Ghaziabad’s flagship Pradhan Mantri Awas Yojana (PMAY), aimed at providing affordable housing for economically weaker sections, has completed a decade without delivering a single unit to beneficiaries. Delays have plagued both private developers and government-run projects, leaving allottees in limbo. Under PMAY, the Ghaziabad Development Authority (GDA) was tasked with building 3,550 units in its colonies, while private developers were to construct 6,150 units across various projects. Despite 2,000 units being ready in GDA schemes such as Madhuban Bapudham and Dasna, essential amenities like electricity, water, sewer connections, and approach roads remain incomplete, delaying handovers. A senior GDA official stated, “We’ve sought assistance from various departments for infrastructure, but progress has stalled due to pending state government funding.” Meanwhile, none of the 6,150 units promised by private developers have been delivered. While some builders claim near-completion, others continue to lag behind. The GDA has issued notices to expedite these projects. The Confederation of Real Estate Developers' Associations of India (CREDAI) partly blames the government, citing insufficient initial incentives for builders. Although recent rule relaxations have encouraged participation, challenges persist. The GDA revised the cost of PMAY units in 2021, increasing the price from Rs 400,000 to Rs 600,000, with central and state government subsidies covering Rs 250,000 and Rs 100,000, respectively. Beneficiaries are required to pay the remaining Rs 250,000. Beyond PMAY, group housing developers are mandated to allocate 10% of their flats for economically weaker sections (EWS) and 10% for low-income groups (LIG). However, compliance has been poor, with only 1,717 EWS and 1,255 LIG flats constructed out of a combined target of 9,720 units. CREDAI-NCR secretary Gaurav Gupta highlighted rising land, construction, and labour costs as barriers to affordable housing viability, urging the government to revise the price cap of Rs 4.5 million under affordable housing schemes. GDA’s former town planner pointed out that developers receive incentives, such as additional Floor Area Ratio (FAR) and exemptions for smaller projects, in exchange for a shelter fee. However, CREDAI deemed these benefits “cosmetic,” emphasising the need for more substantial reforms to boost affordable housing delivery. (ET)

Ghaziabad’s flagship Pradhan Mantri Awas Yojana (PMAY), aimed at providing affordable housing for economically weaker sections, has completed a decade without delivering a single unit to beneficiaries. Delays have plagued both private developers and government-run projects, leaving allottees in limbo. Under PMAY, the Ghaziabad Development Authority (GDA) was tasked with building 3,550 units in its colonies, while private developers were to construct 6,150 units across various projects. Despite 2,000 units being ready in GDA schemes such as Madhuban Bapudham and Dasna, essential amenities like electricity, water, sewer connections, and approach roads remain incomplete, delaying handovers. A senior GDA official stated, “We’ve sought assistance from various departments for infrastructure, but progress has stalled due to pending state government funding.” Meanwhile, none of the 6,150 units promised by private developers have been delivered. While some builders claim near-completion, others continue to lag behind. The GDA has issued notices to expedite these projects. The Confederation of Real Estate Developers' Associations of India (CREDAI) partly blames the government, citing insufficient initial incentives for builders. Although recent rule relaxations have encouraged participation, challenges persist. The GDA revised the cost of PMAY units in 2021, increasing the price from Rs 400,000 to Rs 600,000, with central and state government subsidies covering Rs 250,000 and Rs 100,000, respectively. Beneficiaries are required to pay the remaining Rs 250,000. Beyond PMAY, group housing developers are mandated to allocate 10% of their flats for economically weaker sections (EWS) and 10% for low-income groups (LIG). However, compliance has been poor, with only 1,717 EWS and 1,255 LIG flats constructed out of a combined target of 9,720 units. CREDAI-NCR secretary Gaurav Gupta highlighted rising land, construction, and labour costs as barriers to affordable housing viability, urging the government to revise the price cap of Rs 4.5 million under affordable housing schemes. GDA’s former town planner pointed out that developers receive incentives, such as additional Floor Area Ratio (FAR) and exemptions for smaller projects, in exchange for a shelter fee. However, CREDAI deemed these benefits “cosmetic,” emphasising the need for more substantial reforms to boost affordable housing delivery. (ET)

Next Story
Infrastructure Transport

Lucknow Metro East-West Corridor Consultancy Contract Awarded

The Uttar Pradesh Metro Rail Corporation has awarded the first construction-related consultancy contract for the Lucknow Metro East West Corridor to a joint venture of AYESA Ingenieria Arquitectura SAU and AYESA India Pvt Ltd. The firm was declared the lowest bidder for the Detailed Design Consultant contract for Lucknow Metro Line-2 under Phase 1B and the contract was recommended following the financial bid. The contract is valued at Rs 159.0 million (mn), covering design services for the corridor. Lucknow Metro Line-2 envisages the construction of an 11.165 kilometre corridor connecting Cha..

Next Story
Infrastructure Urban

Div Com Kashmir Urges Fast Tracking Of Jhelum Water Transport Project

The Divisional Commissioner of Kashmir has called for the fast-tracking of the Jhelum water transport project, urging district administrations and relevant agencies to accelerate planning and clearances. In a meeting convened at the divisional headquarters, the commissioner instructed officials from irrigation, public health engineering and municipal departments to prioritise the project and coordinate survey and design work. The directive emphasised removal of administrative bottlenecks and close monitoring to ensure timely mobilisation of resources and contractors. Officials were told to in..

Next Story
Infrastructure Urban

Interarch Reports Strong Q3 And Nine Month Results

Interarch Building Solutions Limited reported unaudited results for the third quarter and nine months ended 31 December 2025, recording strong revenue growth driven by execution and a robust order book. Net revenue for the third quarter rose by 43.7 per cent to Rs 5.225 billion (bn), compared with Rs 3.636 bn a year earlier, reflecting heightened demand in pre-engineered building projects. The company’s total order book as at 31 January 2026 stood at Rs 16.85 bn, supporting near-term visibility. EBITDA excluding other income for the quarter increased by 43.2 per cent to Rs 503 million (mn),..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Open In App