Ghaziabad's PMAY Housing Projects Yet to Deliver
Real Estate

Ghaziabad's PMAY Housing Projects Yet to Deliver

Ghaziabad’s flagship Pradhan Mantri Awas Yojana (PMAY), aimed at providing affordable housing for economically weaker sections, has completed a decade without delivering a single unit to beneficiaries. Delays have plagued both private developers and government-run projects, leaving allottees in limbo. Under PMAY, the Ghaziabad Development Authority (GDA) was tasked with building 3,550 units in its colonies, while private developers were to construct 6,150 units across various projects. Despite 2,000 units being ready in GDA schemes such as Madhuban Bapudham and Dasna, essential amenities like electricity, water, sewer connections, and approach roads remain incomplete, delaying handovers. A senior GDA official stated, “We’ve sought assistance from various departments for infrastructure, but progress has stalled due to pending state government funding.” Meanwhile, none of the 6,150 units promised by private developers have been delivered. While some builders claim near-completion, others continue to lag behind. The GDA has issued notices to expedite these projects. The Confederation of Real Estate Developers' Associations of India (CREDAI) partly blames the government, citing insufficient initial incentives for builders. Although recent rule relaxations have encouraged participation, challenges persist. The GDA revised the cost of PMAY units in 2021, increasing the price from Rs 400,000 to Rs 600,000, with central and state government subsidies covering Rs 250,000 and Rs 100,000, respectively. Beneficiaries are required to pay the remaining Rs 250,000. Beyond PMAY, group housing developers are mandated to allocate 10% of their flats for economically weaker sections (EWS) and 10% for low-income groups (LIG). However, compliance has been poor, with only 1,717 EWS and 1,255 LIG flats constructed out of a combined target of 9,720 units. CREDAI-NCR secretary Gaurav Gupta highlighted rising land, construction, and labour costs as barriers to affordable housing viability, urging the government to revise the price cap of Rs 4.5 million under affordable housing schemes. GDA’s former town planner pointed out that developers receive incentives, such as additional Floor Area Ratio (FAR) and exemptions for smaller projects, in exchange for a shelter fee. However, CREDAI deemed these benefits “cosmetic,” emphasising the need for more substantial reforms to boost affordable housing delivery. (ET)

Ghaziabad’s flagship Pradhan Mantri Awas Yojana (PMAY), aimed at providing affordable housing for economically weaker sections, has completed a decade without delivering a single unit to beneficiaries. Delays have plagued both private developers and government-run projects, leaving allottees in limbo. Under PMAY, the Ghaziabad Development Authority (GDA) was tasked with building 3,550 units in its colonies, while private developers were to construct 6,150 units across various projects. Despite 2,000 units being ready in GDA schemes such as Madhuban Bapudham and Dasna, essential amenities like electricity, water, sewer connections, and approach roads remain incomplete, delaying handovers. A senior GDA official stated, “We’ve sought assistance from various departments for infrastructure, but progress has stalled due to pending state government funding.” Meanwhile, none of the 6,150 units promised by private developers have been delivered. While some builders claim near-completion, others continue to lag behind. The GDA has issued notices to expedite these projects. The Confederation of Real Estate Developers' Associations of India (CREDAI) partly blames the government, citing insufficient initial incentives for builders. Although recent rule relaxations have encouraged participation, challenges persist. The GDA revised the cost of PMAY units in 2021, increasing the price from Rs 400,000 to Rs 600,000, with central and state government subsidies covering Rs 250,000 and Rs 100,000, respectively. Beneficiaries are required to pay the remaining Rs 250,000. Beyond PMAY, group housing developers are mandated to allocate 10% of their flats for economically weaker sections (EWS) and 10% for low-income groups (LIG). However, compliance has been poor, with only 1,717 EWS and 1,255 LIG flats constructed out of a combined target of 9,720 units. CREDAI-NCR secretary Gaurav Gupta highlighted rising land, construction, and labour costs as barriers to affordable housing viability, urging the government to revise the price cap of Rs 4.5 million under affordable housing schemes. GDA’s former town planner pointed out that developers receive incentives, such as additional Floor Area Ratio (FAR) and exemptions for smaller projects, in exchange for a shelter fee. However, CREDAI deemed these benefits “cosmetic,” emphasising the need for more substantial reforms to boost affordable housing delivery. (ET)

Next Story
Real Estate

Integrated Waterproofing Strategies

Waterproofing buildings used to be an annual pre-monsoon affair but the evolution of real-estate development has changed that approach. In new developments, developers are weaving waterproofing solutions into both the design and construction phases, an approach that Nikhil Madan, Managing Director, Mahima Group, says, “is all about ensuring lasting durability [of the building] and keeping lifecycle risks including water seepage and extensive maintenance to a minimum.”Watertight by designAluminium formwork systems aren’t commonly thought of as a waterproofing tool but at the Mahima Group,..

Next Story
Infrastructure Urban

GROHE Showcases Water-Led Design At Milan

GROHE unveiled its GROHE SPA Aqua Sanctuary at Milan Design Week 2026, transforming Piccolo Teatro Studio Melato into an immersive showcase of water, design and wellbeing. Built on the philosophy of ‘Wellbeing Through Water’, the installation reimagined bathrooms as holistic spaces for relaxation, rejuvenation and self-care.The Aqua Sanctuary was presented through three interconnected sanctums. The first showcased the 3D-printed GROHE SPA AquaTree shower and faucet, highlighting bespoke innovation and biophilic design. The second featured the Atrio Private Collection and GROHE SPA x Buster..

Next Story
Infrastructure Transport

Rahee Group Expands Rail Manufacturing Capacity

Rahee Group has outlined a multi-year investment roadmap to expand its operational footprint and strengthen manufacturing capabilities for India’s growing railway and urban transit sector. The Group is expanding in Odisha with a new Track Component Casting Unit, for which the groundbreaking ceremony was held on 8 April 2026 in the presence of Odisha Chief Minister Mohan Charan Majhi.The Group’s flagship EPC arm, Rahee Infratech Ltd, continues to focus on complex rail infrastructure projects, including track systems, bridges, viaducts and ballastless infrastructure. Its wholly owned subsidi..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement