Khar project builder probed by EOW for financial irregularities
Real Estate

Khar project builder probed by EOW for financial irregularities

Following a complaint from the Maharashtra Real Estate Regulatory Authority (MahaRera), the city police's economic offences wing (EOW) has started an investigation against Highstreet Paramvir Developers for financial irregularities. The project on the 6,525 square foot property in Khar is the focal point of the anomalies, and MahaRera complained about it after conducting a forensic audit of the project. The real estate monitor is taking action against a financial irregularity for the first time.

"From the (forensic) audit report, it appears there is prima facie evidence of misuse/diversion of funds of the allottees as well as the funds borrowed from lenders. We have initiated a preliminary probe against the developer,'' a senior EOW official said.

Builder of the Khar project declined to provide information requested for audit nine instances of both financial and regulatory breaches were found during the forensic audit of Highstreet Paramvir Developers' Khar project by the MahaRera organization, which is run by veteran administrator Ajoy Mehta. ?MahaRera has reasonable grounds to believe the funds with respect to the project, Highstreet, have been dealt with in a manner which is detrimental to the interest of the allottees and the promoter has violated the Rera Act,? a senior official said.

The list of irregularities includes failure to deposit funds into a separate project bank account, misuse of funds, including lender funds, loans and advances from dubious parties, loss from land sales, failure to submit project progress reports, building of unapproved floors, a delay in project completion, and failure to provide information needed for forensic audit. ?During the course of the audit, the auditors had multiple follow-up visits, sent emails and held multiple rounds of discussion, requesting the data required for audit, but the information was not provided for review,? said a senior official.

Since its establishment in 2016, MahaRera has initiated action for violation of rules, but it?s the first time it has sought action for financial irregularities. It was found that Rs 13.7 crore was collected from the allottees, of which Rs 2.3 crore was not deposited in a separate bank account, resulting in contravention of the MahaRera Act.

Additionally, there is a shortage in depositing the entire amount because funds were gathered in accounts other than the specified account. ?It was found there was misuse of Rs 76 crore for making non-project-related payments. Majority of loans and advance transactions were with related parties, there was an absence of documentation.

These loans and advances resulted in potential diversion of funds,? said the official. Additionally, it was against MahaRera law to build unapproved floors without the approval of two-thirds of the allottees. The project was supposed to be finished on December 23, 2022, however as of March 23, 2023, just 31% of the work has been finished. According to the audit report, the promoter collected payments from allottees totaling Rs. 2.7 crore, or more than 70% of the agreement's worth.

Following a complaint from the Maharashtra Real Estate Regulatory Authority (MahaRera), the city police's economic offences wing (EOW) has started an investigation against Highstreet Paramvir Developers for financial irregularities. The project on the 6,525 square foot property in Khar is the focal point of the anomalies, and MahaRera complained about it after conducting a forensic audit of the project. The real estate monitor is taking action against a financial irregularity for the first time. From the (forensic) audit report, it appears there is prima facie evidence of misuse/diversion of funds of the allottees as well as the funds borrowed from lenders. We have initiated a preliminary probe against the developer,'' a senior EOW official said. Builder of the Khar project declined to provide information requested for audit nine instances of both financial and regulatory breaches were found during the forensic audit of Highstreet Paramvir Developers' Khar project by the MahaRera organization, which is run by veteran administrator Ajoy Mehta. ?MahaRera has reasonable grounds to believe the funds with respect to the project, Highstreet, have been dealt with in a manner which is detrimental to the interest of the allottees and the promoter has violated the Rera Act,? a senior official said. The list of irregularities includes failure to deposit funds into a separate project bank account, misuse of funds, including lender funds, loans and advances from dubious parties, loss from land sales, failure to submit project progress reports, building of unapproved floors, a delay in project completion, and failure to provide information needed for forensic audit. ?During the course of the audit, the auditors had multiple follow-up visits, sent emails and held multiple rounds of discussion, requesting the data required for audit, but the information was not provided for review,? said a senior official. Since its establishment in 2016, MahaRera has initiated action for violation of rules, but it?s the first time it has sought action for financial irregularities. It was found that Rs 13.7 crore was collected from the allottees, of which Rs 2.3 crore was not deposited in a separate bank account, resulting in contravention of the MahaRera Act. Additionally, there is a shortage in depositing the entire amount because funds were gathered in accounts other than the specified account. ?It was found there was misuse of Rs 76 crore for making non-project-related payments. Majority of loans and advance transactions were with related parties, there was an absence of documentation. These loans and advances resulted in potential diversion of funds,? said the official. Additionally, it was against MahaRera law to build unapproved floors without the approval of two-thirds of the allottees. The project was supposed to be finished on December 23, 2022, however as of March 23, 2023, just 31% of the work has been finished. According to the audit report, the promoter collected payments from allottees totaling Rs. 2.7 crore, or more than 70% of the agreement's worth.

Related Stories

Gold Stories

Next Story
Products

Koemmerling opens Navi Mumbai experience centre

Koemmerling, a brand of the profine Group, has expanded its presence in the Mumbai metropolitan region with the opening of a new experience centre in Navi Mumbai and launched its Allure S46 minimal sliding door system for the Indian market.Located in CBD Belapur, the facility was inaugurated by Peter Mrosik, Owner and CEO, profine Group, along with Farid Khan, Chairman and Managing Director, profine India, and Kamal Bajaj, CEO, profine India.The company said the new centre will showcase its portfolio of uPVC and aluminium window and door systems to architects, developers and homeowners.The ina..

Next Story
Products

India's waterproofing market nears Rs 150 bn milestone

India's waterproofing industry is approaching a market size of Rs 150 billion and is expected to surpass the $2 billion milestone, according to speakers at the 2nd India International Waterproofers Conference & Expo 2026 organised by the Waterproofers Association of India (WAI) in New Delhi.The two-day event brought together more than 20 speakers, 55 international delegates and 53 exhibition booths, with discussions focusing on climate-resilient construction, advanced waterproofing technologies and international collaboration.Inaugurating the event, Durga Shanker Mishra, former Secretary, ..

Next Story
Real Estate

Dilip Buildcon Q1 FY27 Revenue at Rs 23.78 billion

Dilip Buildcon Limited reported consolidated revenue from operations of Rs 2,378 crore in Q1 FY27, along with EBITDA of Rs 429 crore and profit after tax of Rs 128 crore.Consolidated EBITDA margin stood at 18.1%, improving from 17.1% in Q4 FY26. On a standalone basis, revenue from operations was Rs 1,930 crore, EBITDA stood at Rs 199 crore and PAT was Rs 39 crore, with an EBITDA margin of 10.3%.The company’s order book stood at Rs 27,691 crore as of 30 June 2026, compared with Rs 28,830 crore as of 31 March 2026. Roads and highways accounted for 17.1% of the order book, irrigation and water ..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement