MahaREAT Orders Sale Agreements for Thane Homebuyers
Real Estate

MahaREAT Orders Sale Agreements for Thane Homebuyers

In a landmark ruling, the Maharashtra Real Estate Appellate Tribunal (MahaREAT) has set aside a MahaRERA order that dismissed the complaints of eight homebuyers against the ‘One Park Avenue’ project in Thane. The Tribunal directed the current promoter, Purva Oak, to execute agreements for sale with the complainants, recognizing their rights as allottees.

The project, originally launched by Man Global in 2012, faced delays, with buyers paying 30% of the flat cost in advance but never receiving allotment letters or sale agreements. The project was later transferred to Man Realty Ltd and eventually taken over by Purva Oak under SARFAESI provisions.

MahaREAT underscored that under Section 15 of the RERA Act, all pending obligations of the previous promoters transfer to the new one. “The accrued rights of the complainants remain unaffected and are subsisting, valid, as well as binding on parties,” the Tribunal stated.

Advocate Omkar Khanvilkar, representing the homebuyers, highlighted that Man Global issued receipts acknowledging payments, which constituted booking confirmation. However, despite issuing refund cheques, the previous promoter instructed buyers not to deposit them.

The Tribunal noted that payments exceeding the permissible threshold were taken by Man Global, violating RERA norms. Purva Oak, as the successor promoter, is now bound to fulfill these agreements.

This decision reinforces the accountability of developers and offers relief to homebuyers facing long-standing disputes.

Your next big infra connection is waiting at RAHSTA 2025 – Asia’s Biggest Roads & Highways Expo, Jio World Convention Centre, Mumbai. Don’t miss out!

In a landmark ruling, the Maharashtra Real Estate Appellate Tribunal (MahaREAT) has set aside a MahaRERA order that dismissed the complaints of eight homebuyers against the ‘One Park Avenue’ project in Thane. The Tribunal directed the current promoter, Purva Oak, to execute agreements for sale with the complainants, recognizing their rights as allottees. The project, originally launched by Man Global in 2012, faced delays, with buyers paying 30% of the flat cost in advance but never receiving allotment letters or sale agreements. The project was later transferred to Man Realty Ltd and eventually taken over by Purva Oak under SARFAESI provisions. MahaREAT underscored that under Section 15 of the RERA Act, all pending obligations of the previous promoters transfer to the new one. “The accrued rights of the complainants remain unaffected and are subsisting, valid, as well as binding on parties,” the Tribunal stated. Advocate Omkar Khanvilkar, representing the homebuyers, highlighted that Man Global issued receipts acknowledging payments, which constituted booking confirmation. However, despite issuing refund cheques, the previous promoter instructed buyers not to deposit them. The Tribunal noted that payments exceeding the permissible threshold were taken by Man Global, violating RERA norms. Purva Oak, as the successor promoter, is now bound to fulfill these agreements. This decision reinforces the accountability of developers and offers relief to homebuyers facing long-standing disputes.

Next Story
Infrastructure Urban

India Achieves TEC Certification for Indigenous Telecom System

India’s semiconductor ambitions received a major boost as a telecom system built with indigenously manufactured chips secured Telecommunication Engineering Center (TEC) certification.Union IT Minister Ashwini Vaishnaw announced the achievement on X, calling it a “big leap for India’s semiconductor story.” For the first time, a telecom system powered by Indian-made chips has successfully cleared all standards and quality tests.TEC certification, issued by the Department of Telecommunications, confirms that the product meets stringent benchmarks for performance and quality. This mileston..

Next Story
Infrastructure Transport

Mumbai Metro Line 4 Trial Runs Set to Begin This Month

Trial runs on Mumbai Metro Line 4 are expected to commence this month, with passenger services on its initial phase likely to start by the end of 2025. The Green Line will operate between Kasarvadavali and Wadala, covering 32.3 km with 32 stations, providing much-needed relief to commuters in eastern and central Mumbai and Thane.Mumbai Metropolitan Region Development Authority (MMRDA) officials stated that work is advancing rapidly on a 10.5-km section between Gaimukh and Cadbury Junction, which includes 10 stations. This stretch will open first, followed by the remainder of the line.Approxima..

Next Story
Infrastructure Transport

Mumbai Metro Line 11 Approved, Extending Corridor to Gateway

The Maharashtra Cabinet has approved the Mumbai Metro Line 11 project, extending Line 4 along the Wadala–Thane–Kasarvadavli route to the Gateway of India. The 17.5 km corridor, comprising 13 km underground and 4.3 km elevated sections, is estimated to cost Rs 23,488 crore and will feature 14 stations. The Mumbai Metropolitan Region Development Authority (MMRDA) will implement the project, with central government support provided through equity and interest-free subordinate debt, while the state government will manage the loan component.The original alignment from Wadala to CSMT, which trav..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Talk to us?