449 infra projects’ cost overruns total Rs 4 lakh cr
ECONOMY & POLICY

449 infra projects’ cost overruns total Rs 4 lakh cr

According to a report by the Ministry of Statistics and Programme Implementation (MoSPI), as many as 449 infrastructure projects, each worth Rs 150 crore or more, have been hit by cost overruns totalling more than Rs 4.29 lakh crore (Rs 4.29 trillion).

The Ministry of Statistics and Programme Implementation (MoSPI) monitors infrastructure projects worth Rs 150 crore and above. Out of the 1,736 such projects, 449 reported cost overruns and 547 were delayed.

According to the ministry's report from February, the total original cost of implementation of the 1,736 projects was Rs 2,232,019.72 crore and their anticipated completion cost is likely to be Rs 2,661,205.74 crore. The cost overrun for completing these 449 projects works out to be Rs 429,186.02 crore.

The expenditure incurred on these projects till February 2021 is Rs 1,278,270.71 crore, which is 48.03% of the anticipated cost of the projects.

However, the report states that the number of delayed projects decreases to 409 if the delay is calculated based on the latest completion schedule.

Further, for 930 projects neither the year of commissioning nor the tentative gestation period has been reported. Out of 547 delayed projects, 109 projects have overall delay in the range of 1-12 months, 132 projects have a delay of 13-24 months, 187 projects reflect delay in the range of 25-60 months and 119 projects show delays of 61 months and above. The average time overrun in these 547 delayed projects is 44.59 months.

Reasons for time overruns as reported by various project implementing agencies include delay in land acquisition, delay in obtaining forest and environment clearances, and lack of infrastructure support and linkages.

Delay in tie-up for project financing, delay in finalisation of detailed engineering, change in scope, delay in tendering, ordering and equipment supply, and law and order problems, among others, are the other reasons, the report said.

The report also cited state-wise lockdown due to the Covid-19 pandemic as a reason for the delay in implementation of these projects.

It has also been noted that project agencies are not reporting revised cost estimates and commissioning schedules for many projects, which suggests that time and cost overrun figures are underreported, the ministry stated in its report.

Image Source


Also read: Over 400 Mumbai infra projects hit by cost and time overruns

Also read: Infra projects show huge cost overruns

According to a report by the Ministry of Statistics and Programme Implementation (MoSPI), as many as 449 infrastructure projects, each worth Rs 150 crore or more, have been hit by cost overruns totalling more than Rs 4.29 lakh crore (Rs 4.29 trillion). The Ministry of Statistics and Programme Implementation (MoSPI) monitors infrastructure projects worth Rs 150 crore and above. Out of the 1,736 such projects, 449 reported cost overruns and 547 were delayed. According to the ministry's report from February, the total original cost of implementation of the 1,736 projects was Rs 2,232,019.72 crore and their anticipated completion cost is likely to be Rs 2,661,205.74 crore. The cost overrun for completing these 449 projects works out to be Rs 429,186.02 crore. The expenditure incurred on these projects till February 2021 is Rs 1,278,270.71 crore, which is 48.03% of the anticipated cost of the projects. However, the report states that the number of delayed projects decreases to 409 if the delay is calculated based on the latest completion schedule. Further, for 930 projects neither the year of commissioning nor the tentative gestation period has been reported. Out of 547 delayed projects, 109 projects have overall delay in the range of 1-12 months, 132 projects have a delay of 13-24 months, 187 projects reflect delay in the range of 25-60 months and 119 projects show delays of 61 months and above. The average time overrun in these 547 delayed projects is 44.59 months. Reasons for time overruns as reported by various project implementing agencies include delay in land acquisition, delay in obtaining forest and environment clearances, and lack of infrastructure support and linkages. Delay in tie-up for project financing, delay in finalisation of detailed engineering, change in scope, delay in tendering, ordering and equipment supply, and law and order problems, among others, are the other reasons, the report said. The report also cited state-wise lockdown due to the Covid-19 pandemic as a reason for the delay in implementation of these projects. It has also been noted that project agencies are not reporting revised cost estimates and commissioning schedules for many projects, which suggests that time and cost overrun figures are underreported, the ministry stated in its report. Image Source Also read: Over 400 Mumbai infra projects hit by cost and time overruns Also read: Infra projects show huge cost overruns

Related Stories

Gold Stories

Next Story
Resources

Schindler named among Forbes’ World’s Best Employers 2026

Schindler has been named among Forbes’ World’s Best Employers 2026, a global ranking recognising companies for their workplace environments.Compiled by Forbes in partnership with Statista, the ranking is based on independent employee feedback, including whether employees would recommend their organisation to friends and family.The company said the recognition reflected its focus on creating a workplace where employees can develop their expertise and build careers. ..

Next Story
Infrastructure Urban

India needs an export-execution mindset: Vishesh Jain

Interview with Vishesh Jain, Founder & CEO, EximpleWhat gaps in India’s global trade ecosystem led you to build Eximple, and what problem did you see businesses struggling with most?Eximple came out of a problem that all three founders had seen from different choke points in the trade ecosystem. India has millions of MSMEs and manufacturers, and many of them can make products that are genuinely competitive on quality. Yet only a small fraction is able to build meaningful international businesses. In our experience, the gap is usually not manufacturing capability; it is the ability to exe..

Next Story
Building Material

Nuvoco reports 13.5% revenue growth in Q2 FY27

Nuvoco Vistas Corp. Ltd. reported consolidated revenue of Rs 27.9 billion for Q2 FY27, up 13.5% year on year. Cement sales volume rose 9% to 4.7 million tonnes (MMT), while EBITDA increased 11% to Rs 4.11 billion.The company said it began its cement operations in 2014 with a 2.3 MMT per annum (MMTPA) operation at Nimbol. It now aims to reach 35 MMTPA of cement capacity by FY28, nearly 15 times its initial capacity. Its portfolio spans cement, ready-mix concrete and modern building materials.On sustainability and cost efficiency, Nuvoco partnered with CleanMax for a 46.4 MW wind-solar hybrid re..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

SPECIAL OFFER
QR Code