449 infra projects’ cost overruns total Rs 4 lakh cr
ECONOMY & POLICY

449 infra projects’ cost overruns total Rs 4 lakh cr

According to a report by the Ministry of Statistics and Programme Implementation (MoSPI), as many as 449 infrastructure projects, each worth Rs 150 crore or more, have been hit by cost overruns totalling more than Rs 4.29 lakh crore (Rs 4.29 trillion).

The Ministry of Statistics and Programme Implementation (MoSPI) monitors infrastructure projects worth Rs 150 crore and above. Out of the 1,736 such projects, 449 reported cost overruns and 547 were delayed.

According to the ministry's report from February, the total original cost of implementation of the 1,736 projects was Rs 2,232,019.72 crore and their anticipated completion cost is likely to be Rs 2,661,205.74 crore. The cost overrun for completing these 449 projects works out to be Rs 429,186.02 crore.

The expenditure incurred on these projects till February 2021 is Rs 1,278,270.71 crore, which is 48.03% of the anticipated cost of the projects.

However, the report states that the number of delayed projects decreases to 409 if the delay is calculated based on the latest completion schedule.

Further, for 930 projects neither the year of commissioning nor the tentative gestation period has been reported. Out of 547 delayed projects, 109 projects have overall delay in the range of 1-12 months, 132 projects have a delay of 13-24 months, 187 projects reflect delay in the range of 25-60 months and 119 projects show delays of 61 months and above. The average time overrun in these 547 delayed projects is 44.59 months.

Reasons for time overruns as reported by various project implementing agencies include delay in land acquisition, delay in obtaining forest and environment clearances, and lack of infrastructure support and linkages.

Delay in tie-up for project financing, delay in finalisation of detailed engineering, change in scope, delay in tendering, ordering and equipment supply, and law and order problems, among others, are the other reasons, the report said.

The report also cited state-wise lockdown due to the Covid-19 pandemic as a reason for the delay in implementation of these projects.

It has also been noted that project agencies are not reporting revised cost estimates and commissioning schedules for many projects, which suggests that time and cost overrun figures are underreported, the ministry stated in its report.

Image Source


Also read: Over 400 Mumbai infra projects hit by cost and time overruns

Also read: Infra projects show huge cost overruns

According to a report by the Ministry of Statistics and Programme Implementation (MoSPI), as many as 449 infrastructure projects, each worth Rs 150 crore or more, have been hit by cost overruns totalling more than Rs 4.29 lakh crore (Rs 4.29 trillion). The Ministry of Statistics and Programme Implementation (MoSPI) monitors infrastructure projects worth Rs 150 crore and above. Out of the 1,736 such projects, 449 reported cost overruns and 547 were delayed. According to the ministry's report from February, the total original cost of implementation of the 1,736 projects was Rs 2,232,019.72 crore and their anticipated completion cost is likely to be Rs 2,661,205.74 crore. The cost overrun for completing these 449 projects works out to be Rs 429,186.02 crore. The expenditure incurred on these projects till February 2021 is Rs 1,278,270.71 crore, which is 48.03% of the anticipated cost of the projects. However, the report states that the number of delayed projects decreases to 409 if the delay is calculated based on the latest completion schedule. Further, for 930 projects neither the year of commissioning nor the tentative gestation period has been reported. Out of 547 delayed projects, 109 projects have overall delay in the range of 1-12 months, 132 projects have a delay of 13-24 months, 187 projects reflect delay in the range of 25-60 months and 119 projects show delays of 61 months and above. The average time overrun in these 547 delayed projects is 44.59 months. Reasons for time overruns as reported by various project implementing agencies include delay in land acquisition, delay in obtaining forest and environment clearances, and lack of infrastructure support and linkages. Delay in tie-up for project financing, delay in finalisation of detailed engineering, change in scope, delay in tendering, ordering and equipment supply, and law and order problems, among others, are the other reasons, the report said. The report also cited state-wise lockdown due to the Covid-19 pandemic as a reason for the delay in implementation of these projects. It has also been noted that project agencies are not reporting revised cost estimates and commissioning schedules for many projects, which suggests that time and cost overrun figures are underreported, the ministry stated in its report. Image Source Also read: Over 400 Mumbai infra projects hit by cost and time overruns Also read: Infra projects show huge cost overruns

Next Story
Infrastructure Urban

India Expands Semiconductor Training To 500 Institutions

Under the Chips to Startups programme of the India Semiconductor Mission, the Union minister responsible for Railways, Information and Broadcasting, and Electronics and IT reported notable progress in talent development. He indicated that over the past four years substantial steps have been taken towards a 10-year target of training 85,000 engineers in semiconductor design. World-class EDA tools have been deployed in 315 academic institutions across the country to provide students with practical exposure to chip design. These EDA tools are supported by leading global firms and are accessible t..

Next Story
Infrastructure Urban

Delhi Institutions Support India Semiconductor Mission

The Government of India has prioritised talent development through training, upskilling and workforce development under the Chips to Startups initiative of the India Semiconductor Mission, with officials noting progress in four years towards a 10-year target of training 85,000 engineers in semiconductor design. Electronic design automation tools provided by Synopsys, Cadence, Siemens, Renesas, Ansys and AMD have been deployed in 315 academic institutions, enabling students to gain practical chip design experience. Chips have been fabricated and tested at the Semiconductor Laboratory, Mohali, a..

Next Story
Infrastructure Urban

NHA Announces Winners Of NHCX Hackathon At IIT Hyderabad

The National Health Authority (NHA) has concluded the NHCX Hackathon under the Ayushman Bharat Digital Mission (ABDM) to stimulate innovation around the National Health Claims Exchange (NHCX). The winning teams presented their solutions at the NHCX Innovation Meet held at IIT Hyderabad during a two-day event in March 2026 that also served as the hackathon grand finale. The hackathon itself ran from 22 to 28 February 2026 and aimed to accelerate paperless, transparent claims processing across India. The event was organised with a range of ecosystem partners, including the Insurance Regulatory a..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement