449 infra projects’ cost overruns total Rs 4 lakh cr
ECONOMY & POLICY

449 infra projects’ cost overruns total Rs 4 lakh cr

According to a report by the Ministry of Statistics and Programme Implementation (MoSPI), as many as 449 infrastructure projects, each worth Rs 150 crore or more, have been hit by cost overruns totalling more than Rs 4.29 lakh crore (Rs 4.29 trillion).

The Ministry of Statistics and Programme Implementation (MoSPI) monitors infrastructure projects worth Rs 150 crore and above. Out of the 1,736 such projects, 449 reported cost overruns and 547 were delayed.

According to the ministry's report from February, the total original cost of implementation of the 1,736 projects was Rs 2,232,019.72 crore and their anticipated completion cost is likely to be Rs 2,661,205.74 crore. The cost overrun for completing these 449 projects works out to be Rs 429,186.02 crore.

The expenditure incurred on these projects till February 2021 is Rs 1,278,270.71 crore, which is 48.03% of the anticipated cost of the projects.

However, the report states that the number of delayed projects decreases to 409 if the delay is calculated based on the latest completion schedule.

Further, for 930 projects neither the year of commissioning nor the tentative gestation period has been reported. Out of 547 delayed projects, 109 projects have overall delay in the range of 1-12 months, 132 projects have a delay of 13-24 months, 187 projects reflect delay in the range of 25-60 months and 119 projects show delays of 61 months and above. The average time overrun in these 547 delayed projects is 44.59 months.

Reasons for time overruns as reported by various project implementing agencies include delay in land acquisition, delay in obtaining forest and environment clearances, and lack of infrastructure support and linkages.

Delay in tie-up for project financing, delay in finalisation of detailed engineering, change in scope, delay in tendering, ordering and equipment supply, and law and order problems, among others, are the other reasons, the report said.

The report also cited state-wise lockdown due to the Covid-19 pandemic as a reason for the delay in implementation of these projects.

It has also been noted that project agencies are not reporting revised cost estimates and commissioning schedules for many projects, which suggests that time and cost overrun figures are underreported, the ministry stated in its report.

Image Source


Also read: Over 400 Mumbai infra projects hit by cost and time overruns

Also read: Infra projects show huge cost overruns

According to a report by the Ministry of Statistics and Programme Implementation (MoSPI), as many as 449 infrastructure projects, each worth Rs 150 crore or more, have been hit by cost overruns totalling more than Rs 4.29 lakh crore (Rs 4.29 trillion). The Ministry of Statistics and Programme Implementation (MoSPI) monitors infrastructure projects worth Rs 150 crore and above. Out of the 1,736 such projects, 449 reported cost overruns and 547 were delayed. According to the ministry's report from February, the total original cost of implementation of the 1,736 projects was Rs 2,232,019.72 crore and their anticipated completion cost is likely to be Rs 2,661,205.74 crore. The cost overrun for completing these 449 projects works out to be Rs 429,186.02 crore. The expenditure incurred on these projects till February 2021 is Rs 1,278,270.71 crore, which is 48.03% of the anticipated cost of the projects. However, the report states that the number of delayed projects decreases to 409 if the delay is calculated based on the latest completion schedule. Further, for 930 projects neither the year of commissioning nor the tentative gestation period has been reported. Out of 547 delayed projects, 109 projects have overall delay in the range of 1-12 months, 132 projects have a delay of 13-24 months, 187 projects reflect delay in the range of 25-60 months and 119 projects show delays of 61 months and above. The average time overrun in these 547 delayed projects is 44.59 months. Reasons for time overruns as reported by various project implementing agencies include delay in land acquisition, delay in obtaining forest and environment clearances, and lack of infrastructure support and linkages. Delay in tie-up for project financing, delay in finalisation of detailed engineering, change in scope, delay in tendering, ordering and equipment supply, and law and order problems, among others, are the other reasons, the report said. The report also cited state-wise lockdown due to the Covid-19 pandemic as a reason for the delay in implementation of these projects. It has also been noted that project agencies are not reporting revised cost estimates and commissioning schedules for many projects, which suggests that time and cost overrun figures are underreported, the ministry stated in its report. Image Source Also read: Over 400 Mumbai infra projects hit by cost and time overruns Also read: Infra projects show huge cost overruns

Next Story
Infrastructure Transport

Metro Line 2B Phase 1 to Boost Realty in Mumbai’s Eastern Suburbs

Mumbai’s real estate sector is set for a major boost as Phase 1 of Metro Line 2B, between Mandale and Diamond Garden, nears completion. The Mumbai Metropolitan Region Development Authority (MMRDA) has confirmed that mandatory rectifications are done, and inspections by the Commissioner of Metro Railway Safety (CMRS) have been carried out. The 5.39-km stretch with five stations forms part of the larger DN Nagar–Mandale corridor, designed to ease congestion and improve east–west connectivity. Passenger operations are expected by December 2025, with the full line slated for 2027. ..

Next Story
Resources

WattPower wins Best Inverter award at Global Solar Expo 2025

WattPower, a leading renewable energy solutions provider, has won the award for “Best Inverter in the Utility Segment” at the Global Solar Expo 2025. The recognition underscores the company’s commitment to delivering reliable, high-performance and future-ready solar solutions for large-scale projects. At the forefront of utility-scale solar, WattPower manufactures advanced string inverters that directly feed power into the Indian grid. With robust technology, high-quality components and comprehensive product lifecycle support, its solutions stand among the most sophisticated in the ..

Next Story
Real Estate

Awfis delivers 67,000 sq. ft. innovation hub for eBay in Bengaluru

Awfis Space Solutions, India’s largest flexible workspace provider and the first publicly listed workspace solutions platform, has partnered with eBay to establish a 67,000 sq. ft. innovation hub at Embassy Tech Village, Bengaluru. The mandate covers design, build and management of the new office, which will act as a strategic hub supporting diverse functions and accelerating eBay’s AI-first commerce strategy. The centre will focus on artificial intelligence, engineering, product development and applied research, strengthening eBay’s growth in India. Embassy Tech Village, North Beng..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Talk to us?