Over 400 Mumbai infra projects hit by cost and time overruns
SMART CITIES

Over 400 Mumbai infra projects hit by cost and time overruns

As many as 442 infrastructure projects in Mumbai, each worth Rs 150 crore or more, have taken a hit due to cost overruns of more than Rs 4.34 lakh crore.

All infrastructure projects that are worth Rs 150 crore or more are monitored by the Ministry of Statistics and Programme Implementation. Of a total of 1,671 projects, nearly 442 witnessed cost overruns and 536 have suffered postponement.

The total original cost of implementation of nearly 1,671 projects was calculated as Rs 21.21 lakh crore. The expected completion cost is Rs 25.56 lakh crore. It reflects the overall cost overruns of nearly Rs 4.34 lakh crore. It is 20.49% of its original cost.

During November 2020, the expenditure incurred on these projects was Rs 11.94 lakh crore, which is 46.71% of the anticipated costs.

If a delay is calculated based on the latest schedule of completion, then the number of delayed projects gets reduced to 412. For 942 projects, neither the year of commissioning nor the tentative gestation period has been reported.

Of 536 delayed projects, close to 120 have an overall delta of 1-12 months. Whereas, 13 projects are likely to see 13-24 months. Also, 162 indicate delay for 25-60 months and nearly 120 reflect a delay of 61 months and more. Hence, the average time overrun for 536 delayed projects is 44.15 months.

The reasons behind the time overruns:

  • Delay in tie-up for project financing
  • Delays in finalisation of detailed engineering
  • Change in scope
  • Delay in tendering
  • Ordering and equipment supply
  • Law and order issues
  • Delays in land acquisition
  • Delays in obtaining forest and environmental clearances
  • Lockdown in various states in the country

Various project agencies have not reported revisited cost estimates and commissioning schedules for projects. It indicates the time and cost overrun figures to be under-reported.

Image Source

As many as 442 infrastructure projects in Mumbai, each worth Rs 150 crore or more, have taken a hit due to cost overruns of more than Rs 4.34 lakh crore. All infrastructure projects that are worth Rs 150 crore or more are monitored by the Ministry of Statistics and Programme Implementation. Of a total of 1,671 projects, nearly 442 witnessed cost overruns and 536 have suffered postponement. The total original cost of implementation of nearly 1,671 projects was calculated as Rs 21.21 lakh crore. The expected completion cost is Rs 25.56 lakh crore. It reflects the overall cost overruns of nearly Rs 4.34 lakh crore. It is 20.49% of its original cost. During November 2020, the expenditure incurred on these projects was Rs 11.94 lakh crore, which is 46.71% of the anticipated costs. If a delay is calculated based on the latest schedule of completion, then the number of delayed projects gets reduced to 412. For 942 projects, neither the year of commissioning nor the tentative gestation period has been reported. Of 536 delayed projects, close to 120 have an overall delta of 1-12 months. Whereas, 13 projects are likely to see 13-24 months. Also, 162 indicate delay for 25-60 months and nearly 120 reflect a delay of 61 months and more. Hence, the average time overrun for 536 delayed projects is 44.15 months. The reasons behind the time overruns: Delay in tie-up for project financing Delays in finalisation of detailed engineering Change in scope Delay in tendering Ordering and equipment supply Law and order issues Delays in land acquisition Delays in obtaining forest and environmental clearances Lockdown in various states in the country Various project agencies have not reported revisited cost estimates and commissioning schedules for projects. It indicates the time and cost overrun figures to be under-reported. Image Source

Next Story
Infrastructure Transport

Chembur Metro to Boost East Mumbai Links

MMRDA is advancing eastern Mumbai’s urban mobility network, with the upcoming Chembur Metro Station set to emerge as a key interchange and the Mumbai Monorail preparing for relaunch.Dr Sanjay Mukherjee, Metropolitan Commissioner, MMRDA, conducted a site visit to Chembur Metro Station along with Kanhuraj Bagate, Managing Director, MMMOCL. He also visited the nearby VN Purav Monorail Station to review system preparedness and ease of interconnectivity.Once operational, the interchange is expected to offer commuters across the eastern suburbs quicker access, smoother transfers and seamless conne..

Next Story
Equipment

Herrenknecht TBMs Drive Thane–Borivali Tunnel Progress

Herrenknecht India has supplied two of the four tunnel boring machines (TBMs) required for the 11-km Thane–Borivali Twin Tunnel Project being developed by the Mumbai Metropolitan Region Development Authority (MMRDA). The project is expected to reduce travel time between Thane and Borivali from 60–90 minutes to around 15 minutes while easing congestion across the Mumbai Metropolitan Region.The first two Single Shield TBMs, named Nayak and Arjuna, feature 13.34-m cutterhead diameters and are designed for hard-rock excavation. They will be deployed to tunnel through the challenging geological..

Next Story
Resources

KBL Launches Smart Skid Mounted Fire Pump Set

Kirloskar Brothers (KBL) has launched its Smart Skid Mounted Fire Pump Set, an integrated fire protection solution designed to improve operational efficiency, remote monitoring and installation flexibility. The system was inaugurated by Ms Madhuritai Misal, Hon. Minister of State for Urban Development, Government of Maharashtra.The Smart Skid Mounted Fire Pump Set is a factory-tested, pre-packaged solution that combines FM/UL-certified motor and engine pump sets with IoT-enabled remote monitoring. Designed to deliver a flow rate of 170 m³/hr at a head of 100 metres, the system aims to provide..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

-->