Over 400 Mumbai infra projects hit by cost and time overruns
SMART CITIES

Over 400 Mumbai infra projects hit by cost and time overruns

As many as 442 infrastructure projects in Mumbai, each worth Rs 150 crore or more, have taken a hit due to cost overruns of more than Rs 4.34 lakh crore.

All infrastructure projects that are worth Rs 150 crore or more are monitored by the Ministry of Statistics and Programme Implementation. Of a total of 1,671 projects, nearly 442 witnessed cost overruns and 536 have suffered postponement.

The total original cost of implementation of nearly 1,671 projects was calculated as Rs 21.21 lakh crore. The expected completion cost is Rs 25.56 lakh crore. It reflects the overall cost overruns of nearly Rs 4.34 lakh crore. It is 20.49% of its original cost.

During November 2020, the expenditure incurred on these projects was Rs 11.94 lakh crore, which is 46.71% of the anticipated costs.

If a delay is calculated based on the latest schedule of completion, then the number of delayed projects gets reduced to 412. For 942 projects, neither the year of commissioning nor the tentative gestation period has been reported.

Of 536 delayed projects, close to 120 have an overall delta of 1-12 months. Whereas, 13 projects are likely to see 13-24 months. Also, 162 indicate delay for 25-60 months and nearly 120 reflect a delay of 61 months and more. Hence, the average time overrun for 536 delayed projects is 44.15 months.

The reasons behind the time overruns:

  • Delay in tie-up for project financing
  • Delays in finalisation of detailed engineering
  • Change in scope
  • Delay in tendering
  • Ordering and equipment supply
  • Law and order issues
  • Delays in land acquisition
  • Delays in obtaining forest and environmental clearances
  • Lockdown in various states in the country

Various project agencies have not reported revisited cost estimates and commissioning schedules for projects. It indicates the time and cost overrun figures to be under-reported.

Image Source

As many as 442 infrastructure projects in Mumbai, each worth Rs 150 crore or more, have taken a hit due to cost overruns of more than Rs 4.34 lakh crore. All infrastructure projects that are worth Rs 150 crore or more are monitored by the Ministry of Statistics and Programme Implementation. Of a total of 1,671 projects, nearly 442 witnessed cost overruns and 536 have suffered postponement. The total original cost of implementation of nearly 1,671 projects was calculated as Rs 21.21 lakh crore. The expected completion cost is Rs 25.56 lakh crore. It reflects the overall cost overruns of nearly Rs 4.34 lakh crore. It is 20.49% of its original cost. During November 2020, the expenditure incurred on these projects was Rs 11.94 lakh crore, which is 46.71% of the anticipated costs. If a delay is calculated based on the latest schedule of completion, then the number of delayed projects gets reduced to 412. For 942 projects, neither the year of commissioning nor the tentative gestation period has been reported. Of 536 delayed projects, close to 120 have an overall delta of 1-12 months. Whereas, 13 projects are likely to see 13-24 months. Also, 162 indicate delay for 25-60 months and nearly 120 reflect a delay of 61 months and more. Hence, the average time overrun for 536 delayed projects is 44.15 months. The reasons behind the time overruns: Delay in tie-up for project financing Delays in finalisation of detailed engineering Change in scope Delay in tendering Ordering and equipment supply Law and order issues Delays in land acquisition Delays in obtaining forest and environmental clearances Lockdown in various states in the country Various project agencies have not reported revisited cost estimates and commissioning schedules for projects. It indicates the time and cost overrun figures to be under-reported. Image Source

Next Story
Infrastructure Urban

India To Invest $37 Billion To Boost Petrochemical Capacity

India is set to become a major global player in the petrochemicals industry, driven by a planned capital expenditure of $37 billion (Rs 3.1 trillion) aimed at reducing import dependency and enhancing self-sufficiency, according to S&P Global Ratings.In its latest report titled “First China, Now India: Self-Sufficiency Goals Will Add To Petrochemicals Supply”, S&P said India’s large-scale capacity expansion—mirroring China’s earlier push—will likely intensify oversupply pressures in Asia’s petrochemical markets.Currently the world’s third-largest petrochemical consumer a..

Next Story
Infrastructure Transport

Indian Railways Expands Global Exports Of Rail Equipment

Indian Railways has announced that it is rapidly emerging as a global exporter of railway equipment, including bogies, coaches, locomotives, and propulsion systems, under the government’s ‘Make in India, Make for the World’ initiative.According to an official statement, India’s railway products are now reaching over 16 international markets, reflecting the country’s growing capacity to design, develop, and deliver world-class rail solutions.Metro coaches have been exported to Australia and Canada; bogies to the United Kingdom, Saudi Arabia, France, and Australia; propulsion systems t..

Next Story
Infrastructure Transport

RailTel Awards Rs 163 Million Contract To RTNS Technology

RailTel Corporation of India Limited (RailTel), a Mini Ratna Public Sector Undertaking, has awarded a domestic work order worth Rs 163 million to RTNS Technology Private Limited.The contract, issued on 30 September 2025, involves the supply and installation of equipment and related services for one of RailTel’s key customers. The project underscores RailTel’s commitment to advancing technology and communication infrastructure through collaboration with domestic system integrators.RTNS Technology Private Limited, an ISO-certified system integrator, provides comprehensive solutions for perim..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Talk to us?