+
Over 400 Mumbai infra projects hit by cost and time overruns
SMART CITIES

Over 400 Mumbai infra projects hit by cost and time overruns

As many as 442 infrastructure projects in Mumbai, each worth Rs 150 crore or more, have taken a hit due to cost overruns of more than Rs 4.34 lakh crore.

All infrastructure projects that are worth Rs 150 crore or more are monitored by the Ministry of Statistics and Programme Implementation. Of a total of 1,671 projects, nearly 442 witnessed cost overruns and 536 have suffered postponement.

The total original cost of implementation of nearly 1,671 projects was calculated as Rs 21.21 lakh crore. The expected completion cost is Rs 25.56 lakh crore. It reflects the overall cost overruns of nearly Rs 4.34 lakh crore. It is 20.49% of its original cost.

During November 2020, the expenditure incurred on these projects was Rs 11.94 lakh crore, which is 46.71% of the anticipated costs.

If a delay is calculated based on the latest schedule of completion, then the number of delayed projects gets reduced to 412. For 942 projects, neither the year of commissioning nor the tentative gestation period has been reported.

Of 536 delayed projects, close to 120 have an overall delta of 1-12 months. Whereas, 13 projects are likely to see 13-24 months. Also, 162 indicate delay for 25-60 months and nearly 120 reflect a delay of 61 months and more. Hence, the average time overrun for 536 delayed projects is 44.15 months.

The reasons behind the time overruns:

  • Delay in tie-up for project financing
  • Delays in finalisation of detailed engineering
  • Change in scope
  • Delay in tendering
  • Ordering and equipment supply
  • Law and order issues
  • Delays in land acquisition
  • Delays in obtaining forest and environmental clearances
  • Lockdown in various states in the country

Various project agencies have not reported revisited cost estimates and commissioning schedules for projects. It indicates the time and cost overrun figures to be under-reported.

Image Source

As many as 442 infrastructure projects in Mumbai, each worth Rs 150 crore or more, have taken a hit due to cost overruns of more than Rs 4.34 lakh crore. All infrastructure projects that are worth Rs 150 crore or more are monitored by the Ministry of Statistics and Programme Implementation. Of a total of 1,671 projects, nearly 442 witnessed cost overruns and 536 have suffered postponement. The total original cost of implementation of nearly 1,671 projects was calculated as Rs 21.21 lakh crore. The expected completion cost is Rs 25.56 lakh crore. It reflects the overall cost overruns of nearly Rs 4.34 lakh crore. It is 20.49% of its original cost. During November 2020, the expenditure incurred on these projects was Rs 11.94 lakh crore, which is 46.71% of the anticipated costs. If a delay is calculated based on the latest schedule of completion, then the number of delayed projects gets reduced to 412. For 942 projects, neither the year of commissioning nor the tentative gestation period has been reported. Of 536 delayed projects, close to 120 have an overall delta of 1-12 months. Whereas, 13 projects are likely to see 13-24 months. Also, 162 indicate delay for 25-60 months and nearly 120 reflect a delay of 61 months and more. Hence, the average time overrun for 536 delayed projects is 44.15 months. The reasons behind the time overruns: Delay in tie-up for project financing Delays in finalisation of detailed engineering Change in scope Delay in tendering Ordering and equipment supply Law and order issues Delays in land acquisition Delays in obtaining forest and environmental clearances Lockdown in various states in the country Various project agencies have not reported revisited cost estimates and commissioning schedules for projects. It indicates the time and cost overrun figures to be under-reported. Image Source

Next Story
Infrastructure Transport

Lucknow Metro East-West Corridor Consultancy Contract Awarded

The Uttar Pradesh Metro Rail Corporation has awarded the first construction-related consultancy contract for the Lucknow Metro East West Corridor to a joint venture of AYESA Ingenieria Arquitectura SAU and AYESA India Pvt Ltd. The firm was declared the lowest bidder for the Detailed Design Consultant contract for Lucknow Metro Line-2 under Phase 1B and the contract was recommended following the financial bid. The contract is valued at Rs 159.0 million (mn), covering design services for the corridor. Lucknow Metro Line-2 envisages the construction of an 11.165 kilometre corridor connecting Cha..

Next Story
Infrastructure Urban

Div Com Kashmir Urges Fast Tracking Of Jhelum Water Transport Project

The Divisional Commissioner of Kashmir has called for the fast-tracking of the Jhelum water transport project, urging district administrations and relevant agencies to accelerate planning and clearances. In a meeting convened at the divisional headquarters, the commissioner instructed officials from irrigation, public health engineering and municipal departments to prioritise the project and coordinate survey and design work. The directive emphasised removal of administrative bottlenecks and close monitoring to ensure timely mobilisation of resources and contractors. Officials were told to in..

Next Story
Infrastructure Urban

Interarch Reports Strong Q3 And Nine Month Results

Interarch Building Solutions Limited reported unaudited results for the third quarter and nine months ended 31 December 2025, recording strong revenue growth driven by execution and a robust order book. Net revenue for the third quarter rose by 43.7 per cent to Rs 5.225 billion (bn), compared with Rs 3.636 bn a year earlier, reflecting heightened demand in pre-engineered building projects. The company’s total order book as at 31 January 2026 stood at Rs 16.85 bn, supporting near-term visibility. EBITDA excluding other income for the quarter increased by 43.2 per cent to Rs 503 million (mn),..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Open In App