Completion Of Avinashi Flyover Project Likely To Be Delayed
ROADS & HIGHWAYS

Completion Of Avinashi Flyover Project Likely To Be Delayed

The Highways Department has set March 2025 as the target for completing the 10.1-km Avinashi Road flyover project. However, sources suggest that the timeline may be extended due to ongoing major works. 

The construction of the main entry ramp from Goldwins is nearing completion and is expected to be finished shortly. Although the department has directed the contractor to complete the main carriageway by March 2025, delays appear likely, potentially pushing the deadline by a few months. While pillars have been installed in most areas, deck slab placement is still pending at locations such as Peelamedu and Nava India.

Additionally, high-voltage power lines in the Nava India area, which pose an obstruction to the work, are being relocated underground. This includes shifting transformers and electricity poles to facilitate smooth progress. 

Meanwhile, the preparation of the Detailed Project Report (DPR) for a proposed 5-km extension of the flyover from Goldwins to Neelambur is in progress and expected to be completed within a month. Soil testing for this extension was conducted in November. 

Given the planned metro rail infrastructure from Ukkadam Bus Stand to Neelambur, the DPRs for both the flyover extension and metro rail projects will be reviewed together. Construction of the flyover extension will commence following consultations with relevant departments and stakeholders. 

The Highways Department has set March 2025 as the target for completing the 10.1-km Avinashi Road flyover project. However, sources suggest that the timeline may be extended due to ongoing major works. The construction of the main entry ramp from Goldwins is nearing completion and is expected to be finished shortly. Although the department has directed the contractor to complete the main carriageway by March 2025, delays appear likely, potentially pushing the deadline by a few months. While pillars have been installed in most areas, deck slab placement is still pending at locations such as Peelamedu and Nava India. Additionally, high-voltage power lines in the Nava India area, which pose an obstruction to the work, are being relocated underground. This includes shifting transformers and electricity poles to facilitate smooth progress. Meanwhile, the preparation of the Detailed Project Report (DPR) for a proposed 5-km extension of the flyover from Goldwins to Neelambur is in progress and expected to be completed within a month. Soil testing for this extension was conducted in November. Given the planned metro rail infrastructure from Ukkadam Bus Stand to Neelambur, the DPRs for both the flyover extension and metro rail projects will be reviewed together. Construction of the flyover extension will commence following consultations with relevant departments and stakeholders. 

Next Story
Building Material

CCI Clears Dalmia’s Full Acquisition of Jaiprakash Associates

The Competition Commission of India (CCI) has approved Dalmia Cement (Bharat) Limited’s 100% acquisition of Jaiprakash Associates Limited (JAL) under the Insolvency and Bankruptcy Code (IBC), 2016.Dalmia Cement is a wholly owned subsidiary of Dalmia Bharat Limited and a key player in the cement manufacturing sector. The acquisition supports the group’s consolidation strategy in the sector.JAL, currently under a corporate insolvency resolution process, has diversified business interests in real estate, cement, hospitality, and EPC. The acquisition marks a strategic step for Dalmia in enhanc..

Next Story
Infrastructure Urban

Tata AutoComp Expands in Europe with Slovakia Acquisition

Tata AutoComp Systems has entered into a conditional agreement to acquire 100% of IAC Group Slovakia through its UK-based subsidiary, Artifex Interior Systems Limited. The financial terms were not disclosed.The acquisition is part of Tata AutoComp’s broader strategy to strengthen its European presence and deepen ties with global OEMs. It follows the earlier acquisition of Artifex and aligns with the company’s plan to be a leading supplier in the UK and EU markets.Pending regulatory approvals, the acquisition will boost Tata AutoComp’s capabilities in the automotive interiors space, posit..

Next Story
Infrastructure Transport

IndiGo Starts Work on Bengaluru MRO, to Create 1,000+ Jobs

IndiGo has initiated construction of its major Maintenance, Repair, and Overhaul (MRO) facility at Kempegowda International Airport (KIA) in Bengaluru. The airline expects the facility to be operational by early 2028.The new MRO will span 31 acres, significantly larger than IndiGo’s existing MROs in Delhi and Bengaluru. With 12 aircraft bays and capabilities to service both narrow- and wide-body aircraft, this MRO aims to support IndiGo’s goal of becoming a global aviation leader by 2030.IndiGo signed the land allotment MoU with Bangalore International Airport Ltd. (BIAL) in May 2025. The ..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Talk to us?