Phase 2 land takeover for Jewar Airport to begin soon
AVIATION & AIRPORTS

Phase 2 land takeover for Jewar Airport to begin soon

The district government will need an additional week to finish the survey for the land acquisition for phase 2 of the Noida international green field airport in Jewar.

The second phase's property acquisition has been approved, but officials said a survey or census would be conducted to establish how many individuals and families will ultimately be impacted.

The government decides on the compensation and relocation conditions for the impacted families based on the survey results. While the five villages of Kureb, Dayanatpur, Karauli Bangar, Mudrah, and Birampur have finished the survey. Ranhera village, the sixth and last hamlet from which land will be purchased for the second phase, is still in the midst of it.

A total of 1,365 hectares are designated for the airport's second phase, 1,185 of which are owned by farmers and must be purchased. The project's first phase, which will consist of a terminal building covering a total area of one lakh square metres and having a 1.2 crore passenger capacity annually, is now under construction.

The poll was supposed to be completed in a month from when it began in December. But it's already taken more than two months. One of the main causes of the delay is the region's increased number of land transactions, which have significantly altered the conclusions of the initial survey.

According to a preliminary survey of the region, 7,164 farmers must get compensation at a rate of Rs 3,400 per sq m (plus additional incentives under the rehabilitation and resettlement process, or R&R) in order to recover.

Every adult in the impacted family from whose land is being acquired would get an additional compensation of 5 lakh as part of the additional benefits under the R&R procedure.

Also read:
Noida Airport, Faridabad to have direct connectivity via 4-lane road
Number of airports in the country to go up


The district government will need an additional week to finish the survey for the land acquisition for phase 2 of the Noida international green field airport in Jewar. The second phase's property acquisition has been approved, but officials said a survey or census would be conducted to establish how many individuals and families will ultimately be impacted. The government decides on the compensation and relocation conditions for the impacted families based on the survey results. While the five villages of Kureb, Dayanatpur, Karauli Bangar, Mudrah, and Birampur have finished the survey. Ranhera village, the sixth and last hamlet from which land will be purchased for the second phase, is still in the midst of it. A total of 1,365 hectares are designated for the airport's second phase, 1,185 of which are owned by farmers and must be purchased. The project's first phase, which will consist of a terminal building covering a total area of one lakh square metres and having a 1.2 crore passenger capacity annually, is now under construction. The poll was supposed to be completed in a month from when it began in December. But it's already taken more than two months. One of the main causes of the delay is the region's increased number of land transactions, which have significantly altered the conclusions of the initial survey. According to a preliminary survey of the region, 7,164 farmers must get compensation at a rate of Rs 3,400 per sq m (plus additional incentives under the rehabilitation and resettlement process, or R&R) in order to recover. Every adult in the impacted family from whose land is being acquired would get an additional compensation of 5 lakh as part of the additional benefits under the R&R procedure. Also read: Noida Airport, Faridabad to have direct connectivity via 4-lane road Number of airports in the country to go up

Next Story
Infrastructure Transport

Gurgaon-Pataudi-Rewari Highway Set for Completion by December 2025

The National Highways Authority of India (NHAI) has set a new target to complete the four-lane Gurgaon-Pataudi-Rewari highway by December 2025, following a two-year delay.Originally planned in 2018 to upgrade the two-lane state highway into a national highway, the project is estimated to cost Rs 9 billion. Construction, which began in 2021, was initially scheduled for completion in November 2023. According to NHAI, around 70 per cent of the work is already complete, with two major structures still pending: a railway overbridge at Pahari village and a two-lane unidirectional flyover on Dwarka E..

Next Story
Infrastructure Transport

UP Plans Rs 900 Million Extensions to Hindon Elevated Road

The Uttar Pradesh state bridge corporation has prepared the detailed project report and cost estimates for two proposed extensions of the 10.3-km Hindon elevated road, officials said on Thursday. The road connects Raj Nagar Extension to UP-Gate near the east Delhi border, and the project is expected to cost around Rs 900 million.The two extensions, each 400 metres long, will be added to the existing elevated road to ensure smoother traffic flow. “One of the extensions will be from near the Kanawani culvert (near Indirapuram) to the elevated road for commuters heading towards Delhi. The other..

Next Story
Infrastructure Urban

Goa Likely to Miss October Deadline for Maritime Master Plan

Goa is expected to miss the October 31 deadline for submitting its maritime and waterways master plan, which covers the state’s 105 km coastline and river network. The delay is due to the project management consultant not yet being appointed. The plan is now anticipated to be completed by December, Captain of Ports Octavio Rodrigues stated at the India Maritime Week 2025 roadshow.“We have already selected the consultant and will bring them on board within a week. Only then can we begin drafting the master plan, which is essential to secure central government funding,” Rodrigues added.A c..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Talk to us?