Phase 2 land takeover for Jewar Airport to begin soon
AVIATION & AIRPORTS

Phase 2 land takeover for Jewar Airport to begin soon

The district government will need an additional week to finish the survey for the land acquisition for phase 2 of the Noida international green field airport in Jewar.

The second phase's property acquisition has been approved, but officials said a survey or census would be conducted to establish how many individuals and families will ultimately be impacted.

The government decides on the compensation and relocation conditions for the impacted families based on the survey results. While the five villages of Kureb, Dayanatpur, Karauli Bangar, Mudrah, and Birampur have finished the survey. Ranhera village, the sixth and last hamlet from which land will be purchased for the second phase, is still in the midst of it.

A total of 1,365 hectares are designated for the airport's second phase, 1,185 of which are owned by farmers and must be purchased. The project's first phase, which will consist of a terminal building covering a total area of one lakh square metres and having a 1.2 crore passenger capacity annually, is now under construction.

The poll was supposed to be completed in a month from when it began in December. But it's already taken more than two months. One of the main causes of the delay is the region's increased number of land transactions, which have significantly altered the conclusions of the initial survey.

According to a preliminary survey of the region, 7,164 farmers must get compensation at a rate of Rs 3,400 per sq m (plus additional incentives under the rehabilitation and resettlement process, or R&R) in order to recover.

Every adult in the impacted family from whose land is being acquired would get an additional compensation of 5 lakh as part of the additional benefits under the R&R procedure.

Also read:
Noida Airport, Faridabad to have direct connectivity via 4-lane road
Number of airports in the country to go up


The district government will need an additional week to finish the survey for the land acquisition for phase 2 of the Noida international green field airport in Jewar. The second phase's property acquisition has been approved, but officials said a survey or census would be conducted to establish how many individuals and families will ultimately be impacted. The government decides on the compensation and relocation conditions for the impacted families based on the survey results. While the five villages of Kureb, Dayanatpur, Karauli Bangar, Mudrah, and Birampur have finished the survey. Ranhera village, the sixth and last hamlet from which land will be purchased for the second phase, is still in the midst of it. A total of 1,365 hectares are designated for the airport's second phase, 1,185 of which are owned by farmers and must be purchased. The project's first phase, which will consist of a terminal building covering a total area of one lakh square metres and having a 1.2 crore passenger capacity annually, is now under construction. The poll was supposed to be completed in a month from when it began in December. But it's already taken more than two months. One of the main causes of the delay is the region's increased number of land transactions, which have significantly altered the conclusions of the initial survey. According to a preliminary survey of the region, 7,164 farmers must get compensation at a rate of Rs 3,400 per sq m (plus additional incentives under the rehabilitation and resettlement process, or R&R) in order to recover. Every adult in the impacted family from whose land is being acquired would get an additional compensation of 5 lakh as part of the additional benefits under the R&R procedure. Also read: Noida Airport, Faridabad to have direct connectivity via 4-lane road Number of airports in the country to go up

Next Story
Infrastructure Transport

MMRDA advances 250 m on Orange Gate–Marine Drive tunnel

The Mumbai Metropolitan Region Development Authority (MMRDA) has completed 250 m of underground tunnelling for the Orange Gate–Marine Drive Urban Road Tunnel using India’s largest slurry shield tunnel boring machine (TBM) deployed for an urban road project.The project involves twin tunnels extending over 7 km beneath critical transport corridors, including Central Railway, Western Railway and Metro Line 3. The work requires high-precision engineering to navigate densely developed urban infrastructure.Once completed, the tunnel is expected to reduce travel time between Orange Gate and Marin..

Next Story
Infrastructure Urban

Hindustan Zinc Pays Rs 188.46 Billion in FY26

Hindustan Zinc contributed Rs 188.46 billion to the public exchequer in FY 2025-26, according to its 9th Tax Transparency Report. The contribution, equivalent to 46 per cent of the company’s revenue, included direct and indirect taxes, government royalties, dividends to the Government of India, withholding taxes and other statutory levies.The company’s five-year cumulative contribution to the exchequer stood at Rs 915.72 billion. In FY26, Hindustan Zinc reported revenue of Rs 408.44 billion, EBITDA of Rs 221.62 billion and profit after tax of Rs 138.32 billion. It also achieved its highest..

Next Story
Infrastructure Urban

World of Concrete India 2026 Opens in Mumbai

Informa Markets in India will host the 12th edition of World of Concrete India 2026 from 3–5 June 2026 at the Bombay Exhibition Centre, Mumbai. The specialised B2B exhibition will bring together manufacturers, suppliers, contractors, developers, architects, consultants, infrastructure companies, project leaders and government stakeholders.The event is expected to feature over 350 brands and more than 18,000 trade professionals. It will cover concrete and cement, dry mortar, precast technologies, formwork, construction chemicals, industrial and commercial flooring, scaffolding, safety solutio..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement