As many as 428 infra projects hit cost overruns of Rs 4.98 lakh cr
ROADS & HIGHWAYS

As many as 428 infra projects hit cost overruns of Rs 4.98 lakh cr

As per a report, 428 infrastructure projects, each entailing an investment of Rs 150 crore or above, have been hit by cost overruns of more than Rs 4.98 lakh crore.

According to the Ministry of Statistics and Programme Implementation, which monitors infrastructure projects of Rs 150 crore and more, out of 1,559 projects, 428 projects declared cost overruns, and around 647 projects were delayed.

The ministry's latest report for April 2022 said the total original cost of execution of the 1559 projects was Rs 21,73,907.11 crore, and their expected completion cost is likely to be Rs 26,72,201.26 crore, which reflects overall cost overruns of Rs 4,98,294.15 crore.

The expenditure incurred on these infrastructure projects till April 2022 was Rs 13,50,610.98 crore, which was 50.54% of their expected cost, according to the report.

However, the number of delayed projects drops to 525 if the delay is calculated based on the latest plan of completion.

Further, for 619 projects neither the commissioning year nor the tentative gestation period has been declared.

Out of the 647 delayed projects, 103 have overall delays in the range of 1-12 months, 111 have been stalled for 13-24 months, 314 projects for 25-60 months, and 119 projects have been stalled for 61 months and more.

The average time overrun in these 647 stalled projects was 42.83 months.

Reasons for time overruns as informed by various project executing agencies include delay in land acquisition, delay in acquiring forest and environment approvals, delay in finalisation of detailed engineering, lack of infrastructure support and linkages, ordering and equipment supply, delay in tie-up for project financing, change in scope, delay in tendering, and law and order problems.

The report also mentioned state-wise lockdowns due to Covid-19 as a cause for the delay in execution of these projects.

It has also been observed that project companies are not informing revised cost estimates and commissioning plans for many projects, which indicates that time and cost overrun figures are under-reported.

Image Source

Also read: Around 425 infra projects note cost overruns worth Rs 4.83 lakh cr

As per a report, 428 infrastructure projects, each entailing an investment of Rs 150 crore or above, have been hit by cost overruns of more than Rs 4.98 lakh crore. According to the Ministry of Statistics and Programme Implementation, which monitors infrastructure projects of Rs 150 crore and more, out of 1,559 projects, 428 projects declared cost overruns, and around 647 projects were delayed. The ministry's latest report for April 2022 said the total original cost of execution of the 1559 projects was Rs 21,73,907.11 crore, and their expected completion cost is likely to be Rs 26,72,201.26 crore, which reflects overall cost overruns of Rs 4,98,294.15 crore. The expenditure incurred on these infrastructure projects till April 2022 was Rs 13,50,610.98 crore, which was 50.54% of their expected cost, according to the report. However, the number of delayed projects drops to 525 if the delay is calculated based on the latest plan of completion. Further, for 619 projects neither the commissioning year nor the tentative gestation period has been declared. Out of the 647 delayed projects, 103 have overall delays in the range of 1-12 months, 111 have been stalled for 13-24 months, 314 projects for 25-60 months, and 119 projects have been stalled for 61 months and more. The average time overrun in these 647 stalled projects was 42.83 months. Reasons for time overruns as informed by various project executing agencies include delay in land acquisition, delay in acquiring forest and environment approvals, delay in finalisation of detailed engineering, lack of infrastructure support and linkages, ordering and equipment supply, delay in tie-up for project financing, change in scope, delay in tendering, and law and order problems. The report also mentioned state-wise lockdowns due to Covid-19 as a cause for the delay in execution of these projects. It has also been observed that project companies are not informing revised cost estimates and commissioning plans for many projects, which indicates that time and cost overrun figures are under-reported. Image Source Also read: Around 425 infra projects note cost overruns worth Rs 4.83 lakh cr

Next Story
Infrastructure Urban

Reliance, Diehl Advance Pact for Precision-Guided Munitions

Diehl Defence CEO Helmut Rauch and Reliance Group’s Founder Chairman Anil D. Ambani have held discussions to advance their ongoing strategic partnership focused on Guided and Terminally Guided Munitions (TGM), under a cooperation agreement originally signed in 2019.This collaboration underscores Diehl Defence’s long-term commitment to the Indian market and its support for the Indian Government’s Make in India initiative. The partnership’s current emphasis is on the urgent supply of the Vulcano 155mm Precision Guided Munition system to the Indian Armed Forces.Simultaneously, the “Vulc..

Next Story
Infrastructure Urban

Modis Navnirman to Migrate to Main Board, Merge Subsidiary

Modis Navnirman Limited has announced that its Board of Directors has approved a key strategic initiative involving migration from the BSE SME platform to the Main Board of both BSE and NSE, alongside a merger with its wholly owned subsidiary, Shree Modis Navnirman Private Limited.The move to the main boards marks a major milestone in the company’s growth trajectory, reflecting its consistent financial performance, robust corporate governance, and long-term commitment to value creation. This transition will grant the company access to a broader investor base, improve market participation, en..

Next Story
Infrastructure Urban

Global Capital Flows Remain Subdued, EMEA Leads in Q1 2025

The Bharat InvITs Association’s industry update for Q1 2025 shows subdued global capital flows, with investment volumes remaining at the lower end of the five-year range despite a late 2024 recovery. According to data from Colliers and MSCI Real Capital Analytics, activity in North America declined slightly, while EMEA maintained steady levels and emerged as the top region for investment in standing assets.The EMEA region now hosts seven of the top ten cross-border capital destinations for standing assets, pushing the United States’ share of global activity below 15 per cent. Meanwhile, in..

Advertisement

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Advertisement

Talk to us?