As many as 428 infra projects hit cost overruns of Rs 4.98 lakh cr
ROADS & HIGHWAYS

As many as 428 infra projects hit cost overruns of Rs 4.98 lakh cr

As per a report, 428 infrastructure projects, each entailing an investment of Rs 150 crore or above, have been hit by cost overruns of more than Rs 4.98 lakh crore.

According to the Ministry of Statistics and Programme Implementation, which monitors infrastructure projects of Rs 150 crore and more, out of 1,559 projects, 428 projects declared cost overruns, and around 647 projects were delayed.

The ministry's latest report for April 2022 said the total original cost of execution of the 1559 projects was Rs 21,73,907.11 crore, and their expected completion cost is likely to be Rs 26,72,201.26 crore, which reflects overall cost overruns of Rs 4,98,294.15 crore.

The expenditure incurred on these infrastructure projects till April 2022 was Rs 13,50,610.98 crore, which was 50.54% of their expected cost, according to the report.

However, the number of delayed projects drops to 525 if the delay is calculated based on the latest plan of completion.

Further, for 619 projects neither the commissioning year nor the tentative gestation period has been declared.

Out of the 647 delayed projects, 103 have overall delays in the range of 1-12 months, 111 have been stalled for 13-24 months, 314 projects for 25-60 months, and 119 projects have been stalled for 61 months and more.

The average time overrun in these 647 stalled projects was 42.83 months.

Reasons for time overruns as informed by various project executing agencies include delay in land acquisition, delay in acquiring forest and environment approvals, delay in finalisation of detailed engineering, lack of infrastructure support and linkages, ordering and equipment supply, delay in tie-up for project financing, change in scope, delay in tendering, and law and order problems.

The report also mentioned state-wise lockdowns due to Covid-19 as a cause for the delay in execution of these projects.

It has also been observed that project companies are not informing revised cost estimates and commissioning plans for many projects, which indicates that time and cost overrun figures are under-reported.

Image Source

Also read: Around 425 infra projects note cost overruns worth Rs 4.83 lakh cr

As per a report, 428 infrastructure projects, each entailing an investment of Rs 150 crore or above, have been hit by cost overruns of more than Rs 4.98 lakh crore. According to the Ministry of Statistics and Programme Implementation, which monitors infrastructure projects of Rs 150 crore and more, out of 1,559 projects, 428 projects declared cost overruns, and around 647 projects were delayed. The ministry's latest report for April 2022 said the total original cost of execution of the 1559 projects was Rs 21,73,907.11 crore, and their expected completion cost is likely to be Rs 26,72,201.26 crore, which reflects overall cost overruns of Rs 4,98,294.15 crore. The expenditure incurred on these infrastructure projects till April 2022 was Rs 13,50,610.98 crore, which was 50.54% of their expected cost, according to the report. However, the number of delayed projects drops to 525 if the delay is calculated based on the latest plan of completion. Further, for 619 projects neither the commissioning year nor the tentative gestation period has been declared. Out of the 647 delayed projects, 103 have overall delays in the range of 1-12 months, 111 have been stalled for 13-24 months, 314 projects for 25-60 months, and 119 projects have been stalled for 61 months and more. The average time overrun in these 647 stalled projects was 42.83 months. Reasons for time overruns as informed by various project executing agencies include delay in land acquisition, delay in acquiring forest and environment approvals, delay in finalisation of detailed engineering, lack of infrastructure support and linkages, ordering and equipment supply, delay in tie-up for project financing, change in scope, delay in tendering, and law and order problems. The report also mentioned state-wise lockdowns due to Covid-19 as a cause for the delay in execution of these projects. It has also been observed that project companies are not informing revised cost estimates and commissioning plans for many projects, which indicates that time and cost overrun figures are under-reported. Image Source Also read: Around 425 infra projects note cost overruns worth Rs 4.83 lakh cr

Next Story
Infrastructure Urban

Daikin Boosts Haryana’s Innovation Push with Rs 10 billion R&D Plan

Japanese multinational Daikin Industries has committed an investment of Rs 10 billion to set up a new research and development centre in Haryana. The proposed facility will focus on advanced technologies and sustainable industrial solutions, marking a significant boost to the state’s innovation and industrial ecosystem. The announcement follows the signing of a Memorandum of Understanding (MoU) in Osaka, Japan, during a visit by a Haryana government delegation held from October 6 to 8. The MoU was signed by Amit Kumar Agrawal, Commissioner and Secretary, Industries and Commerce Department, ..

Next Story
Building Material

Lloyds Metals to Build Rs 250 billion Steel Plant in Gadchiroli

Lloyds Metals & Energy Limited (LMEL) has announced an investment of Rs 250 billion aimed at transforming Gadchiroli in Maharashtra from a region once associated with the red corridor into a key industrial and growth hub. The company’s plans are centred on establishing an integrated steel production ecosystem, which will contribute significantly to regional development and employment. As part of its expansion strategy, LMEL is setting up a 4.5-million-tonne blast furnace in Gadchiroli, scheduled for completion by 2027–28, along with another 1.2-million-tonne facility in Chandrapur by 2029..

Next Story
Infrastructure Urban

UPI Crosses 500 Million Users, Fuels MSME and Digital Growth

The Unified Payments Interface (UPI) has achieved a new milestone, surpassing 500 million consumers and 65 million merchants across India. The platform, developed by the National Payments Corporation of India (NPCI), has expanded its reach to nearly 99 percent of the country’s pin codes, underlining its deep penetration into both urban and rural markets. According to a report by NPCI and the Boston Consulting Group (BCG) launched during the Global Fintech Fest 2025, UPI has evolved from being a digital payments mechanism into a key enabler of financial inclusion and small business growth. I..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Talk to us?