As many as 428 infra projects hit cost overruns of Rs 4.98 lakh cr
ROADS & HIGHWAYS

As many as 428 infra projects hit cost overruns of Rs 4.98 lakh cr

As per a report, 428 infrastructure projects, each entailing an investment of Rs 150 crore or above, have been hit by cost overruns of more than Rs 4.98 lakh crore.

According to the Ministry of Statistics and Programme Implementation, which monitors infrastructure projects of Rs 150 crore and more, out of 1,559 projects, 428 projects declared cost overruns, and around 647 projects were delayed.

The ministry's latest report for April 2022 said the total original cost of execution of the 1559 projects was Rs 21,73,907.11 crore, and their expected completion cost is likely to be Rs 26,72,201.26 crore, which reflects overall cost overruns of Rs 4,98,294.15 crore.

The expenditure incurred on these infrastructure projects till April 2022 was Rs 13,50,610.98 crore, which was 50.54% of their expected cost, according to the report.

However, the number of delayed projects drops to 525 if the delay is calculated based on the latest plan of completion.

Further, for 619 projects neither the commissioning year nor the tentative gestation period has been declared.

Out of the 647 delayed projects, 103 have overall delays in the range of 1-12 months, 111 have been stalled for 13-24 months, 314 projects for 25-60 months, and 119 projects have been stalled for 61 months and more.

The average time overrun in these 647 stalled projects was 42.83 months.

Reasons for time overruns as informed by various project executing agencies include delay in land acquisition, delay in acquiring forest and environment approvals, delay in finalisation of detailed engineering, lack of infrastructure support and linkages, ordering and equipment supply, delay in tie-up for project financing, change in scope, delay in tendering, and law and order problems.

The report also mentioned state-wise lockdowns due to Covid-19 as a cause for the delay in execution of these projects.

It has also been observed that project companies are not informing revised cost estimates and commissioning plans for many projects, which indicates that time and cost overrun figures are under-reported.

Image Source

Also read: Around 425 infra projects note cost overruns worth Rs 4.83 lakh cr

As per a report, 428 infrastructure projects, each entailing an investment of Rs 150 crore or above, have been hit by cost overruns of more than Rs 4.98 lakh crore. According to the Ministry of Statistics and Programme Implementation, which monitors infrastructure projects of Rs 150 crore and more, out of 1,559 projects, 428 projects declared cost overruns, and around 647 projects were delayed. The ministry's latest report for April 2022 said the total original cost of execution of the 1559 projects was Rs 21,73,907.11 crore, and their expected completion cost is likely to be Rs 26,72,201.26 crore, which reflects overall cost overruns of Rs 4,98,294.15 crore. The expenditure incurred on these infrastructure projects till April 2022 was Rs 13,50,610.98 crore, which was 50.54% of their expected cost, according to the report. However, the number of delayed projects drops to 525 if the delay is calculated based on the latest plan of completion. Further, for 619 projects neither the commissioning year nor the tentative gestation period has been declared. Out of the 647 delayed projects, 103 have overall delays in the range of 1-12 months, 111 have been stalled for 13-24 months, 314 projects for 25-60 months, and 119 projects have been stalled for 61 months and more. The average time overrun in these 647 stalled projects was 42.83 months. Reasons for time overruns as informed by various project executing agencies include delay in land acquisition, delay in acquiring forest and environment approvals, delay in finalisation of detailed engineering, lack of infrastructure support and linkages, ordering and equipment supply, delay in tie-up for project financing, change in scope, delay in tendering, and law and order problems. The report also mentioned state-wise lockdowns due to Covid-19 as a cause for the delay in execution of these projects. It has also been observed that project companies are not informing revised cost estimates and commissioning plans for many projects, which indicates that time and cost overrun figures are under-reported. Image Source Also read: Around 425 infra projects note cost overruns worth Rs 4.83 lakh cr

Next Story
Infrastructure Urban

MCD Launches Digital Parking at 8 Locations Across Delhi

The Municipal Corporation of Delhi (MCD) has launched a digital parking system at eight prominent locations across the capital, introducing a tech-driven approach to urban mobility and parking management.The initiative is designed to streamline parking operations, encourage cashless payments, and ensure greater transparency in revenue collection. The pilot rollout has been implemented in busy areas such as Karol Bagh, Lajpat Nagar, Nehru Place (Outer and Inner Ring), Shastri Park, and Kashmere Gate ISBT.Under the new system, four-wheelers will be able to make payments via FASTag, while two-whe..

Next Story
Infrastructure Transport

Delhi Plans 21 New Foot Overbridges for Pedestrian Safety

The Public Works Department (PWD) of Delhi has received a proposal to construct 21 new foot overbridges (FOBs) across high-traffic locations in the city, following a review by Chief Minister Rekha Gupta and the Delhi Traffic Police. Ground surveys are now underway to prepare detailed project reports.The initiative aims to improve pedestrian safety and accessibility in key congested areas. Among the proposed sites are Shyama Prasad Mukherjee Marg near Old Delhi Railway Station’s exit, Shaheed Captain Batra Chowk, the LNJP Hospital in Central Delhi, Ajmeri Gate Chowk, Munja Chowk on Boulevard ..

Next Story
Infrastructure Transport

Carnac Bridge to Reopen By 10 June After Delay

Mumbai’s historic Carnac Bridge, a vital link connecting South Mumbai to the eastern suburbs, is now on course for completion by 10 June 2025, despite recent construction delays.The Brihanmumbai Municipal Corporation (BMC) resumed work after a 15-day setback due to the delayed arrival of essential steel girders. The contractor responsible has been fined Rs 18 million for failing to meet the original delivery deadline of 30 April. Penalties were imposed at Rs 1 million per day from 1 to 2 May, increasing to Rs 2 million per day from 3 to 10 May. To speed up progress, BMC deployed engineers to..

Advertisement

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Advertisement

Talk to us?