+
Kerala’s Seaport-Airport Road second phase delayed by 20 years
ROADS & HIGHWAYS

Kerala’s Seaport-Airport Road second phase delayed by 20 years

After the start of initial development, the second phase of the Seaport-Airport Road, a 14.3 km length from Kalamassery HMT Road to Nedumbassery airport, has been delayed for more than 20 years. Two phases make up the 25.7 km Seaport-Airport Road project, which runs from Irumpanam to the Kochi airport. In 2003, the 11.3 kilometre first phase from Irumpanam to Kalamassery was finished.

The second phase, however, has been postponed as a result of the land acquisition impasse. To expedite the purchase of land for the second phase, a review meeting was convened and presided over by Aluva MLA Anwar Sadat and Ernakulam Collector N S K Umesh. The decision was made at the meeting, which took place in the Collector's chamber, to finish the land acquisition procedure for the Purayar rail over bridge (ROB) by May 31. As a need for the second stage of the road project, land acquisition must be finished in the villages of Choornikkara, Thrikkakara North, Aluva West, and Keezhmadu. A draught notification regarding the land acquisition has been finalised and will be issued by August 16 according to a formal announcement.

Three pieces made up the second phase. Sections A, B, and C are the sections from HMT Road-NAD Junction to Mahilalayam Junction Road, Chowara, and the part from Chowara to Airport Road. Aluva and Chowara railway stations are separated by the Purayar railway gate. The project is being implemented by the Roads and Bridges Development Corporation (RBDCK), although Kerala Infrastructure Investment Fund Board is providing the finance. The project management expert is Kitco Ltd. The project outlay for the second phase of the NAD to Mahilayalam length is Rs 4.37 billion, according to the RBDCK website.

After the start of initial development, the second phase of the Seaport-Airport Road, a 14.3 km length from Kalamassery HMT Road to Nedumbassery airport, has been delayed for more than 20 years. Two phases make up the 25.7 km Seaport-Airport Road project, which runs from Irumpanam to the Kochi airport. In 2003, the 11.3 kilometre first phase from Irumpanam to Kalamassery was finished. The second phase, however, has been postponed as a result of the land acquisition impasse. To expedite the purchase of land for the second phase, a review meeting was convened and presided over by Aluva MLA Anwar Sadat and Ernakulam Collector N S K Umesh. The decision was made at the meeting, which took place in the Collector's chamber, to finish the land acquisition procedure for the Purayar rail over bridge (ROB) by May 31. As a need for the second stage of the road project, land acquisition must be finished in the villages of Choornikkara, Thrikkakara North, Aluva West, and Keezhmadu. A draught notification regarding the land acquisition has been finalised and will be issued by August 16 according to a formal announcement. Three pieces made up the second phase. Sections A, B, and C are the sections from HMT Road-NAD Junction to Mahilalayam Junction Road, Chowara, and the part from Chowara to Airport Road. Aluva and Chowara railway stations are separated by the Purayar railway gate. The project is being implemented by the Roads and Bridges Development Corporation (RBDCK), although Kerala Infrastructure Investment Fund Board is providing the finance. The project management expert is Kitco Ltd. The project outlay for the second phase of the NAD to Mahilayalam length is Rs 4.37 billion, according to the RBDCK website.

Related Stories

Gold Stories

Next Story
Infrastructure Transport

97 Per Cent Of Rongjeng-Mangsang-Adokgre Road Nears Completion

Deputy Chief Minister in-charge of public works Prestone Tynsong said in Shillong on 26 August that 97 per cent physical progress had been achieved on the ongoing Rongjeng-Mangsang-Adokgre road being constructed under the Non-Lapsable Central Pool of Resources (NLCPR). He noted the project was sanctioned in 2017 and that the stipulated time for completion had been 24 months from issue of the final work order. The deputy chief minister informed the assembly that the government had decided to include the remaining work under a World Bank project. In reply to a query from Rongjeng MLA Jim M Sangm..

Next Story
Infrastructure Transport

First TBM Starts Digging Five Point Three Kilometre Tunnel Under SGNP

The Goregaon-Mulund Link Road (GMLR) Phase three (B) project has reached a key milestone as the first tunnel boring machine (TBM) began excavation of the first of two tunnels beneath the Sanjay Gandhi National Park (SGNP). The machine, named Tulsi, started cutting a five point three kilometre bore that will link Dadasaheb Phalke Chitranagari in Goregaon East with Amar Nagar in Mulund West. Officials issued a statement noting the commencement of tunnelling work under the protected green belt. The twin tunnels are being constructed using mechanised tunnelling methods that aim to limit surface di..

Next Story
Infrastructure Transport

UP Approves Two Expressways And Rs 240 bn Infrastructure Push

The Uttar Pradesh Cabinet approved a series of infrastructure and industrial investment proposals totalling Rs 240 billion (Rs 240 bn), including two major expressway projects, a manufacturing and logistics cluster in Sultanpur and incentives for 11 industrial projects across the state. The decisions, taken at a meeting chaired by Chief Minister Yogi Adityanath, underline the state government’s focus on expanding road connectivity around emerging industrial hubs while attracting manufacturing investment to districts beyond major urban centres. The approvals cover both greenfield expressway c..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

SPECIAL OFFER
QR Code