Mumbai-Goa Highway Project Faces Further Delay
ROADS & HIGHWAYS

Mumbai-Goa Highway Project Faces Further Delay

The long-delayed Mumbai-Goa Highway project has been postponed again, with the National Highways Authority of India (NHAI) and Public Works Department (PWD) announcing a revised deadline of 2027. The delay added to the frustration of commuters, who already face deteriorating road conditions on the existing route. Many travellers are forced to take the longer Satara route to reach Goa.

In September 2024, former PWD Minister Ravindra Chavan expressed optimism about completing the highway within two years but acknowledged challenges, including delays in constructing 14 bridges and service roads.

Initially planned under a build-operate-transfer (BOT) model, the project was divided into 10 construction packages. However, issues such as land acquisition hurdles, forest clearance delays, and poor construction quality have significantly hampered progress.

One of the most anticipated segments of the project is the twin tunnels at Kashedi Ghat, designed to provide a safer passage through the mountainous terrain. According to a PWD official, construction on the tunnels is nearly complete, with plans to inaugurate them on Republic Day, January 26.

The tunnels were briefly opened for Ganeshotsav traffic but were closed again due to water leakage and electrical issues. These problems have sparked political disputes, with leaders blaming administrative inefficiencies for the setbacks.

The highway project has become a political battleground, with successive governments accusing each other of mismanagement. However, with both Maharashtra and Goa now governed by the Bharatiya Janata Party (BJP), citizens hope for expedited progress.

The long-delayed Mumbai-Goa Highway project has been postponed again, with the National Highways Authority of India (NHAI) and Public Works Department (PWD) announcing a revised deadline of 2027. The delay added to the frustration of commuters, who already face deteriorating road conditions on the existing route. Many travellers are forced to take the longer Satara route to reach Goa. In September 2024, former PWD Minister Ravindra Chavan expressed optimism about completing the highway within two years but acknowledged challenges, including delays in constructing 14 bridges and service roads. Initially planned under a build-operate-transfer (BOT) model, the project was divided into 10 construction packages. However, issues such as land acquisition hurdles, forest clearance delays, and poor construction quality have significantly hampered progress. One of the most anticipated segments of the project is the twin tunnels at Kashedi Ghat, designed to provide a safer passage through the mountainous terrain. According to a PWD official, construction on the tunnels is nearly complete, with plans to inaugurate them on Republic Day, January 26. The tunnels were briefly opened for Ganeshotsav traffic but were closed again due to water leakage and electrical issues. These problems have sparked political disputes, with leaders blaming administrative inefficiencies for the setbacks. The highway project has become a political battleground, with successive governments accusing each other of mismanagement. However, with both Maharashtra and Goa now governed by the Bharatiya Janata Party (BJP), citizens hope for expedited progress.

Next Story
Infrastructure Urban

InsideFPV Delivers ₹10 Crore Kamikaze Drone Order Under MoD’s EPR Route

InsideFPV, a Surat-based drone technology manufacturer, has successfully executed a ₹10 crore defence contract to supply indigenous kamikaze drones under the Ministry of Defence’s Emergency Procurement Route (EPR). The company completed the delivery of hundreds of FPV kamikaze drone platforms within a rapid two-month timeframe, highlighting its ability to meet urgent military procurement timelines.The supply orders were fulfilled under the emergency procurement mechanism, which is aimed at fast-tracking acquisitions for immediate operational needs. InsideFPV’s quick execution reflects it..

Next Story
Infrastructure Energy

Vedanta Resources Secures Fitch Upgrade to ‘BB-’, Best Rating Since 2015

Vedanta Resources Limited (VRL), a global player in metals, oil & gas, critical minerals, power and technology, has received a credit rating upgrade from Fitch Ratings, marking its strongest bond rating in over a decade.Fitch has raised Vedanta Resources’ Long-Term Foreign-Currency Issuer Default Rating (IDR) to ‘BB-’ from ‘B+’, while maintaining a Stable Outlook. The agency also upgraded VRL’s senior unsecured rating, along with the ratings of US dollar-denominated bonds issued by Vedanta Resources Finance II Plc and guaranteed by VRL, to ‘BB-’.The upgrade represents Vedan..

Next Story
Real Estate

NAREDCO NextGen NCR Chapter Launched

The NAREDCO NextGen NCR Chapter was recently launched at Excelerate 2026 in Mumbai, marking a key step towards integrating emerging real estate leaders from the National Capital Region with the national platform. The initiative aims to promote sustainable and responsible urban development through collaboration and knowledge exchange.The event brought together young developers, entrepreneurs, and professionals from across NCR, including Noida, Gurugram, Ghaziabad, Faridabad, Bhiwadi, and Meerut. Discussions focused on urban development, finance, sustainability, innovation, and policy, emphasisi..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement