+
Mumbai-Goa Highway Project Faces Further Delay
ROADS & HIGHWAYS

Mumbai-Goa Highway Project Faces Further Delay

The long-delayed Mumbai-Goa Highway project has been postponed again, with the National Highways Authority of India (NHAI) and Public Works Department (PWD) announcing a revised deadline of 2027. The delay added to the frustration of commuters, who already face deteriorating road conditions on the existing route. Many travellers are forced to take the longer Satara route to reach Goa.

In September 2024, former PWD Minister Ravindra Chavan expressed optimism about completing the highway within two years but acknowledged challenges, including delays in constructing 14 bridges and service roads.

Initially planned under a build-operate-transfer (BOT) model, the project was divided into 10 construction packages. However, issues such as land acquisition hurdles, forest clearance delays, and poor construction quality have significantly hampered progress.

One of the most anticipated segments of the project is the twin tunnels at Kashedi Ghat, designed to provide a safer passage through the mountainous terrain. According to a PWD official, construction on the tunnels is nearly complete, with plans to inaugurate them on Republic Day, January 26.

The tunnels were briefly opened for Ganeshotsav traffic but were closed again due to water leakage and electrical issues. These problems have sparked political disputes, with leaders blaming administrative inefficiencies for the setbacks.

The highway project has become a political battleground, with successive governments accusing each other of mismanagement. However, with both Maharashtra and Goa now governed by the Bharatiya Janata Party (BJP), citizens hope for expedited progress.

The long-delayed Mumbai-Goa Highway project has been postponed again, with the National Highways Authority of India (NHAI) and Public Works Department (PWD) announcing a revised deadline of 2027. The delay added to the frustration of commuters, who already face deteriorating road conditions on the existing route. Many travellers are forced to take the longer Satara route to reach Goa. In September 2024, former PWD Minister Ravindra Chavan expressed optimism about completing the highway within two years but acknowledged challenges, including delays in constructing 14 bridges and service roads. Initially planned under a build-operate-transfer (BOT) model, the project was divided into 10 construction packages. However, issues such as land acquisition hurdles, forest clearance delays, and poor construction quality have significantly hampered progress. One of the most anticipated segments of the project is the twin tunnels at Kashedi Ghat, designed to provide a safer passage through the mountainous terrain. According to a PWD official, construction on the tunnels is nearly complete, with plans to inaugurate them on Republic Day, January 26. The tunnels were briefly opened for Ganeshotsav traffic but were closed again due to water leakage and electrical issues. These problems have sparked political disputes, with leaders blaming administrative inefficiencies for the setbacks. The highway project has become a political battleground, with successive governments accusing each other of mismanagement. However, with both Maharashtra and Goa now governed by the Bharatiya Janata Party (BJP), citizens hope for expedited progress.

Next Story
Infrastructure Urban

ABB to Invest Rs 6.25 Billion to Expand India Manufacturing

ABB recently announced plans to invest approximately Rs 6.25 billion ($75 million) in India during 2026 to expand its manufacturing footprint and research and development capabilities. The investment follows more than $35 million spent in 2025 and reflects the company’s continued focus on strengthening its ‘local-for-local’ strategy in the country.The investment will support ABB’s Electrification, Motion and Automation businesses and expand manufacturing capacity for infrastructure sectors such as renewable energy, metro rail, data centres and industrial applications. Approximately 300..

Next Story
Equipment

Six WOLFF Cranes Handle 60,000 m³ Concrete for German Hospital

Six WOLFF tower cranes are playing a key role in constructing a new hospital complex in Memmingen, Germany, supporting large-scale material handling for the project. The facility is being built on a 7.7-hectare site and will feature six floors, around 480 beds and a gross floor area exceeding 75,000 sq m.Building shell works began recently in February 2025. One WOLFF 6531.12 Cross crane supported early site preparation before being dismantled in autumn 2025, while five remaining cranes continue operations. Over an average deployment period of 16 months, the cranes are expected to move approxim..

Next Story
Equipment

REC Funds Rs 115.6 Million CSR Support for Bihar Eye Hospital

REC recently committed Rs 115.6 million under its Corporate Social Responsibility (CSR) programme for the procurement of clinical and non-clinical equipment at Sankara Eye Hospital in Saharsa, Bihar. The initiative aims to strengthen healthcare infrastructure and improve access to specialised eye care services in the region.A Memorandum of Agreement (MoA) was recently signed between Pradeep Fellows, Executive Director (CSR), REC Limited, and Wg Cdr V. Shankar (Retd), Trustee and Executive Director of Sankara Eye Hospital, at the REC office in the SCOPE Complex, New Delhi.The support is expecte..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement