Mumbai-Goa Highway Project Faces Further Delay
ROADS & HIGHWAYS

Mumbai-Goa Highway Project Faces Further Delay

The long-delayed Mumbai-Goa Highway project has been postponed again, with the National Highways Authority of India (NHAI) and Public Works Department (PWD) announcing a revised deadline of 2027. The delay added to the frustration of commuters, who already face deteriorating road conditions on the existing route. Many travellers are forced to take the longer Satara route to reach Goa.

In September 2024, former PWD Minister Ravindra Chavan expressed optimism about completing the highway within two years but acknowledged challenges, including delays in constructing 14 bridges and service roads.

Initially planned under a build-operate-transfer (BOT) model, the project was divided into 10 construction packages. However, issues such as land acquisition hurdles, forest clearance delays, and poor construction quality have significantly hampered progress.

One of the most anticipated segments of the project is the twin tunnels at Kashedi Ghat, designed to provide a safer passage through the mountainous terrain. According to a PWD official, construction on the tunnels is nearly complete, with plans to inaugurate them on Republic Day, January 26.

The tunnels were briefly opened for Ganeshotsav traffic but were closed again due to water leakage and electrical issues. These problems have sparked political disputes, with leaders blaming administrative inefficiencies for the setbacks.

The highway project has become a political battleground, with successive governments accusing each other of mismanagement. However, with both Maharashtra and Goa now governed by the Bharatiya Janata Party (BJP), citizens hope for expedited progress.

The long-delayed Mumbai-Goa Highway project has been postponed again, with the National Highways Authority of India (NHAI) and Public Works Department (PWD) announcing a revised deadline of 2027. The delay added to the frustration of commuters, who already face deteriorating road conditions on the existing route. Many travellers are forced to take the longer Satara route to reach Goa. In September 2024, former PWD Minister Ravindra Chavan expressed optimism about completing the highway within two years but acknowledged challenges, including delays in constructing 14 bridges and service roads. Initially planned under a build-operate-transfer (BOT) model, the project was divided into 10 construction packages. However, issues such as land acquisition hurdles, forest clearance delays, and poor construction quality have significantly hampered progress. One of the most anticipated segments of the project is the twin tunnels at Kashedi Ghat, designed to provide a safer passage through the mountainous terrain. According to a PWD official, construction on the tunnels is nearly complete, with plans to inaugurate them on Republic Day, January 26. The tunnels were briefly opened for Ganeshotsav traffic but were closed again due to water leakage and electrical issues. These problems have sparked political disputes, with leaders blaming administrative inefficiencies for the setbacks. The highway project has become a political battleground, with successive governments accusing each other of mismanagement. However, with both Maharashtra and Goa now governed by the Bharatiya Janata Party (BJP), citizens hope for expedited progress.

Next Story
Equipment

Handling concrete better

Efficiently handling the transportation and placement of concrete is essential to help maintain the quality of construction, meet project timelines by minimising downtimes, and reduce costs – by 5 to 15 per cent, according to Sandeep Jain, Director, Arkade Developers. CW explores what the efficient handling of concrete entails.Select wellFirst, a word on choosing the right equipment, such as a mixer with a capacity aligned to the volume required onsite, from Vaibhav Kulkarni, Concrete Expert. “An overly large mixer will increase the idle time (and cost), while one that ..

Next Story
Real Estate

Elevated floors!

Raised access flooring, also called false flooring, is a less common interiors feature than false ceilings, but it has as many uses – if not more.A raised floor is a modular panel installed above the structural floor. The space beneath the raised flooring is typically used to accommodate utilities such as electrical cables, plumbing and HVAC systems. And so, raised flooring is usually associated with buildings with heavy cabling and precise air distribution needs, such as data centres.That said, CW interacted with designers and architects and discovered that false flooring can come in handy ..

Next Story
Infrastructure Urban

The Variation Challenge

A variation or change in scope clause is defined in construction contracts to take care of situations arising from change in the defined scope of work. Such changes may arise due to factors such as additions or deletions in the scope of work, modifications in the type, grade or specifications of materials, alterations in specifications or drawings, and acts or omissions of other contractors. Further, ineffective planning, inadequate investigations or surveys and requests from the employer or those within the project’s area of influence can contribute to changes in the scope of work. Ext..

Advertisement

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Advertisement

Talk to us?