Panvel to Kasu concretisation complete
ROADS & HIGHWAYS

Panvel to Kasu concretisation complete

80% of the work on the Mumbai-Goa highway has been completed, and they expect it to be ready by the end of the year. 
Before Ganeshotsav, the National Highways Authority of India (NHAI) opened one side of the 42 km stretch of the Mumbai-Goa highway from Panvel to Kasu in Raigad district to traffic. The NHAI had divided the total 84 km of the highway into two packages: Panvel to Kasu (42 km) and Kasu to Indapur (42 km).
NHAI had concretized 38 km of the stretch from Panvel to Kasu, and the remaining 4 km mostly consisted of a bridge and flyover. Some sections of the road were undergoing curing, where they regularly watered the stretches to strengthen the road surface. They had placed steel slags on the bridge and flyover temporarily to allow vehicles to ply.
Additionally, 10 km of the other package up to Nagothane in Raigad district had been made pothole-free. They applied white topping and Cement Treatment Base (CTB) to make the road suitable for motor vehicles, as per the official.
As a result, commuters were now able to use the highway from Palaspe Junction in Panvel to Nagothane and cover the distance in less than one hour.
JM Mhatre Infra had been awarded the work order for Package 1 (Panvel to Kasu), amounting to Rs 1.51 billion, while Kalyan Toll Infra had received the work order for Package 2 (Kasu to Indapur) in November 2022.

Also read: 

If you want to learn more about Indian Roads, make sure you sign-up for the India Roads Conference at the India Construction Festival on October 12th in New Delhi.

Click HERE and reserve your seats! Or call Deepali on 82919 95574....

80% of the work on the Mumbai-Goa highway has been completed, and they expect it to be ready by the end of the year. Before Ganeshotsav, the National Highways Authority of India (NHAI) opened one side of the 42 km stretch of the Mumbai-Goa highway from Panvel to Kasu in Raigad district to traffic. The NHAI had divided the total 84 km of the highway into two packages: Panvel to Kasu (42 km) and Kasu to Indapur (42 km).NHAI had concretized 38 km of the stretch from Panvel to Kasu, and the remaining 4 km mostly consisted of a bridge and flyover. Some sections of the road were undergoing curing, where they regularly watered the stretches to strengthen the road surface. They had placed steel slags on the bridge and flyover temporarily to allow vehicles to ply.Additionally, 10 km of the other package up to Nagothane in Raigad district had been made pothole-free. They applied white topping and Cement Treatment Base (CTB) to make the road suitable for motor vehicles, as per the official.As a result, commuters were now able to use the highway from Palaspe Junction in Panvel to Nagothane and cover the distance in less than one hour.JM Mhatre Infra had been awarded the work order for Package 1 (Panvel to Kasu), amounting to Rs 1.51 billion, while Kalyan Toll Infra had received the work order for Package 2 (Kasu to Indapur) in November 2022.Also read: MMRDA plans 350 sq km Town in Mumbai Harbour           Dwarka comes up with mega convention space, Yashobhoomi If you want to learn more about Indian Roads, make sure you sign-up for the India Roads Conference at the India Construction Festival on October 12th in New Delhi.Click HERE and reserve your seats! Or call Deepali on 82919 95574....

Next Story
Infrastructure Urban

TBO Tek Q2 Profit Climbs 12%, Revenue Surges 26% YoY

TBO Tek Limited one of the world’s largest travel distribution platforms, reported a solid performance for Q2 FY26 with a 26 per cent year-on-year increase in revenue to Rs 5.68 billion, reflecting broad-based growth and improving profitability.The company recorded a Gross Transaction Value (GTV) of Rs 8,901 crore, up 12 per cent YoY, driven by strong performance across Europe, MEA, and APAC regions. Adjusted EBITDA before acquisition-related costs stood at Rs 1.04 billion, up 16 per cent YoY, translating into an 18.32 per cent margin compared to 16.56 per cent in Q1 FY26. Profit after tax r..

Next Story
Infrastructure Energy

Northern Graphite, Rain Carbon Secure R&D Grant for Greener Battery Materials

Northern Graphite Corporation and Rain Carbon Canada Inc, a subsidiary of Rain Carbon Inc, have jointly received up to C$860,000 (€530,000) in funding under the Canada–Germany Collaborative Industrial Research and Development Programme to develop sustainable battery anode materials.The two-year, C$2.2 million project aims to transform natural graphite processing by-products into high-performance, battery-grade anode material (BAM). Supported by the National Research Council of Canada Industrial Research Assistance Programme (NRC IRAP) and Germany’s Federal Ministry for Economic Affairs a..

Next Story
Infrastructure Urban

Antony Waste Q2 Revenue Jumps 16%; Subsidiary Wins Rs 3,200 Cr WtE Projects

Antony Waste Handling Cell Limited (AWHCL), a leading player in India’s municipal solid waste management sector, announced a 16 per cent year-on-year increase in total operating revenue to Rs 2.33 billion for Q2 FY26. The growth was driven by higher waste volumes, escalated contracts, and strong operational execution.EBITDA rose 18 per cent to Rs 570 million, with margins steady at 21.6 per cent, while profit after tax stood at Rs 173 million, up 13 per cent YoY. Revenue from Municipal Solid Waste Collection and Transportation (MSW C&T) reached Rs 1.605 billion, and MSW Processing re..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement