Panvel to Kasu concretisation complete
ROADS & HIGHWAYS

Panvel to Kasu concretisation complete

80% of the work on the Mumbai-Goa highway has been completed, and they expect it to be ready by the end of the year. 
Before Ganeshotsav, the National Highways Authority of India (NHAI) opened one side of the 42 km stretch of the Mumbai-Goa highway from Panvel to Kasu in Raigad district to traffic. The NHAI had divided the total 84 km of the highway into two packages: Panvel to Kasu (42 km) and Kasu to Indapur (42 km).
NHAI had concretized 38 km of the stretch from Panvel to Kasu, and the remaining 4 km mostly consisted of a bridge and flyover. Some sections of the road were undergoing curing, where they regularly watered the stretches to strengthen the road surface. They had placed steel slags on the bridge and flyover temporarily to allow vehicles to ply.
Additionally, 10 km of the other package up to Nagothane in Raigad district had been made pothole-free. They applied white topping and Cement Treatment Base (CTB) to make the road suitable for motor vehicles, as per the official.
As a result, commuters were now able to use the highway from Palaspe Junction in Panvel to Nagothane and cover the distance in less than one hour.
JM Mhatre Infra had been awarded the work order for Package 1 (Panvel to Kasu), amounting to Rs 1.51 billion, while Kalyan Toll Infra had received the work order for Package 2 (Kasu to Indapur) in November 2022.

Also read: 

If you want to learn more about Indian Roads, make sure you sign-up for the India Roads Conference at the India Construction Festival on October 12th in New Delhi.

Click HERE and reserve your seats! Or call Deepali on 82919 95574....

80% of the work on the Mumbai-Goa highway has been completed, and they expect it to be ready by the end of the year. Before Ganeshotsav, the National Highways Authority of India (NHAI) opened one side of the 42 km stretch of the Mumbai-Goa highway from Panvel to Kasu in Raigad district to traffic. The NHAI had divided the total 84 km of the highway into two packages: Panvel to Kasu (42 km) and Kasu to Indapur (42 km).NHAI had concretized 38 km of the stretch from Panvel to Kasu, and the remaining 4 km mostly consisted of a bridge and flyover. Some sections of the road were undergoing curing, where they regularly watered the stretches to strengthen the road surface. They had placed steel slags on the bridge and flyover temporarily to allow vehicles to ply.Additionally, 10 km of the other package up to Nagothane in Raigad district had been made pothole-free. They applied white topping and Cement Treatment Base (CTB) to make the road suitable for motor vehicles, as per the official.As a result, commuters were now able to use the highway from Palaspe Junction in Panvel to Nagothane and cover the distance in less than one hour.JM Mhatre Infra had been awarded the work order for Package 1 (Panvel to Kasu), amounting to Rs 1.51 billion, while Kalyan Toll Infra had received the work order for Package 2 (Kasu to Indapur) in November 2022.Also read: MMRDA plans 350 sq km Town in Mumbai Harbour           Dwarka comes up with mega convention space, Yashobhoomi If you want to learn more about Indian Roads, make sure you sign-up for the India Roads Conference at the India Construction Festival on October 12th in New Delhi.Click HERE and reserve your seats! Or call Deepali on 82919 95574....

Next Story
Infrastructure Urban

India Expands Semiconductor Training To 500 Institutions

Under the Chips to Startups programme of the India Semiconductor Mission, the Union minister responsible for Railways, Information and Broadcasting, and Electronics and IT reported notable progress in talent development. He indicated that over the past four years substantial steps have been taken towards a 10-year target of training 85,000 engineers in semiconductor design. World-class EDA tools have been deployed in 315 academic institutions across the country to provide students with practical exposure to chip design. These EDA tools are supported by leading global firms and are accessible t..

Next Story
Infrastructure Urban

Delhi Institutions Support India Semiconductor Mission

The Government of India has prioritised talent development through training, upskilling and workforce development under the Chips to Startups initiative of the India Semiconductor Mission, with officials noting progress in four years towards a 10-year target of training 85,000 engineers in semiconductor design. Electronic design automation tools provided by Synopsys, Cadence, Siemens, Renesas, Ansys and AMD have been deployed in 315 academic institutions, enabling students to gain practical chip design experience. Chips have been fabricated and tested at the Semiconductor Laboratory, Mohali, a..

Next Story
Infrastructure Urban

NHA Announces Winners Of NHCX Hackathon At IIT Hyderabad

The National Health Authority (NHA) has concluded the NHCX Hackathon under the Ayushman Bharat Digital Mission (ABDM) to stimulate innovation around the National Health Claims Exchange (NHCX). The winning teams presented their solutions at the NHCX Innovation Meet held at IIT Hyderabad during a two-day event in March 2026 that also served as the hackathon grand finale. The hackathon itself ran from 22 to 28 February 2026 and aimed to accelerate paperless, transparent claims processing across India. The event was organised with a range of ecosystem partners, including the Insurance Regulatory a..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement