Panvel to Kasu concretisation complete
ROADS & HIGHWAYS

Panvel to Kasu concretisation complete

80% of the work on the Mumbai-Goa highway has been completed, and they expect it to be ready by the end of the year. 
Before Ganeshotsav, the National Highways Authority of India (NHAI) opened one side of the 42 km stretch of the Mumbai-Goa highway from Panvel to Kasu in Raigad district to traffic. The NHAI had divided the total 84 km of the highway into two packages: Panvel to Kasu (42 km) and Kasu to Indapur (42 km).
NHAI had concretized 38 km of the stretch from Panvel to Kasu, and the remaining 4 km mostly consisted of a bridge and flyover. Some sections of the road were undergoing curing, where they regularly watered the stretches to strengthen the road surface. They had placed steel slags on the bridge and flyover temporarily to allow vehicles to ply.
Additionally, 10 km of the other package up to Nagothane in Raigad district had been made pothole-free. They applied white topping and Cement Treatment Base (CTB) to make the road suitable for motor vehicles, as per the official.
As a result, commuters were now able to use the highway from Palaspe Junction in Panvel to Nagothane and cover the distance in less than one hour.
JM Mhatre Infra had been awarded the work order for Package 1 (Panvel to Kasu), amounting to Rs 1.51 billion, while Kalyan Toll Infra had received the work order for Package 2 (Kasu to Indapur) in November 2022.

Also read: 

If you want to learn more about Indian Roads, make sure you sign-up for the India Roads Conference at the India Construction Festival on October 12th in New Delhi.

Click HERE and reserve your seats! Or call Deepali on 82919 95574....

80% of the work on the Mumbai-Goa highway has been completed, and they expect it to be ready by the end of the year. Before Ganeshotsav, the National Highways Authority of India (NHAI) opened one side of the 42 km stretch of the Mumbai-Goa highway from Panvel to Kasu in Raigad district to traffic. The NHAI had divided the total 84 km of the highway into two packages: Panvel to Kasu (42 km) and Kasu to Indapur (42 km).NHAI had concretized 38 km of the stretch from Panvel to Kasu, and the remaining 4 km mostly consisted of a bridge and flyover. Some sections of the road were undergoing curing, where they regularly watered the stretches to strengthen the road surface. They had placed steel slags on the bridge and flyover temporarily to allow vehicles to ply.Additionally, 10 km of the other package up to Nagothane in Raigad district had been made pothole-free. They applied white topping and Cement Treatment Base (CTB) to make the road suitable for motor vehicles, as per the official.As a result, commuters were now able to use the highway from Palaspe Junction in Panvel to Nagothane and cover the distance in less than one hour.JM Mhatre Infra had been awarded the work order for Package 1 (Panvel to Kasu), amounting to Rs 1.51 billion, while Kalyan Toll Infra had received the work order for Package 2 (Kasu to Indapur) in November 2022.Also read: MMRDA plans 350 sq km Town in Mumbai Harbour           Dwarka comes up with mega convention space, Yashobhoomi If you want to learn more about Indian Roads, make sure you sign-up for the India Roads Conference at the India Construction Festival on October 12th in New Delhi.Click HERE and reserve your seats! Or call Deepali on 82919 95574....

Next Story
Infrastructure Urban

VECV Sales Rise 7.8 Per Cent In May 2026

VE Commercial Vehicles recorded sales of 7,978 units in May 2026, compared to 7,401 units in May 2025, registering growth of 7.8 per cent. This included 7,789 units from the Eicher brand and 189 units from the Volvo brand.Eicher branded trucks and buses reported sales of 7,789 units during the month, up 7.3 per cent from 7,258 units a year earlier. In the domestic commercial vehicle market, Eicher sales rose 9.1 per cent to 7,375 units from 6,758 units in May 2025.Exports declined 17.2 per cent to 414 units from 500 units in the corresponding month last year. Volvo Trucks and Volvo Buses recor..

Next Story
Infrastructure Urban

Table Space Strengthens DESYN Leadership Team

Table Space has announced strategic leadership appointments within DESYN, its integrated Design and Build business, as it looks to strengthen operations across key enterprise and GCC markets in India. DESYN was launched as a strategic extension of Table Space’s workspace solutions portfolio to meet rising demand for agile, high-quality and rapidly deployable enterprise workspaces.Shruti Ookabhoy has joined DESYN as Executive Director and will lead the Design vertical, focusing on design capability, operational excellence and team development across markets. She brings over 22 years of experi..

Next Story
Infrastructure Transport

Concord Associate Bags Rs 2.79 Bn Kavach Order

Concord Control Systems said its associate company, Progota India, has received a Rs 2.79 bn domestic order from Indian Railways for the supply, installation, testing and commissioning of on-board Kavach 4.0 loco equipment.The order is scheduled for execution within 12 months and strengthens Concord’s role in India’s railway safety and signalling ecosystem. Kavach is India’s indigenous automatic train protection system, designed to improve operational safety by helping prevent signal passing at danger and reducing collision risks.Gaurav Lath, Joint Managing Director, Concord Control Syst..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement