Panvel to Kasu concretisation complete
ROADS & HIGHWAYS

Panvel to Kasu concretisation complete

80% of the work on the Mumbai-Goa highway has been completed, and they expect it to be ready by the end of the year. 
Before Ganeshotsav, the National Highways Authority of India (NHAI) opened one side of the 42 km stretch of the Mumbai-Goa highway from Panvel to Kasu in Raigad district to traffic. The NHAI had divided the total 84 km of the highway into two packages: Panvel to Kasu (42 km) and Kasu to Indapur (42 km).
NHAI had concretized 38 km of the stretch from Panvel to Kasu, and the remaining 4 km mostly consisted of a bridge and flyover. Some sections of the road were undergoing curing, where they regularly watered the stretches to strengthen the road surface. They had placed steel slags on the bridge and flyover temporarily to allow vehicles to ply.
Additionally, 10 km of the other package up to Nagothane in Raigad district had been made pothole-free. They applied white topping and Cement Treatment Base (CTB) to make the road suitable for motor vehicles, as per the official.
As a result, commuters were now able to use the highway from Palaspe Junction in Panvel to Nagothane and cover the distance in less than one hour.
JM Mhatre Infra had been awarded the work order for Package 1 (Panvel to Kasu), amounting to Rs 1.51 billion, while Kalyan Toll Infra had received the work order for Package 2 (Kasu to Indapur) in November 2022.

Also read: 

If you want to learn more about Indian Roads, make sure you sign-up for the India Roads Conference at the India Construction Festival on October 12th in New Delhi.

Click HERE and reserve your seats! Or call Deepali on 82919 95574....

80% of the work on the Mumbai-Goa highway has been completed, and they expect it to be ready by the end of the year. Before Ganeshotsav, the National Highways Authority of India (NHAI) opened one side of the 42 km stretch of the Mumbai-Goa highway from Panvel to Kasu in Raigad district to traffic. The NHAI had divided the total 84 km of the highway into two packages: Panvel to Kasu (42 km) and Kasu to Indapur (42 km).NHAI had concretized 38 km of the stretch from Panvel to Kasu, and the remaining 4 km mostly consisted of a bridge and flyover. Some sections of the road were undergoing curing, where they regularly watered the stretches to strengthen the road surface. They had placed steel slags on the bridge and flyover temporarily to allow vehicles to ply.Additionally, 10 km of the other package up to Nagothane in Raigad district had been made pothole-free. They applied white topping and Cement Treatment Base (CTB) to make the road suitable for motor vehicles, as per the official.As a result, commuters were now able to use the highway from Palaspe Junction in Panvel to Nagothane and cover the distance in less than one hour.JM Mhatre Infra had been awarded the work order for Package 1 (Panvel to Kasu), amounting to Rs 1.51 billion, while Kalyan Toll Infra had received the work order for Package 2 (Kasu to Indapur) in November 2022.Also read: MMRDA plans 350 sq km Town in Mumbai Harbour           Dwarka comes up with mega convention space, Yashobhoomi If you want to learn more about Indian Roads, make sure you sign-up for the India Roads Conference at the India Construction Festival on October 12th in New Delhi.Click HERE and reserve your seats! Or call Deepali on 82919 95574....

Related Stories

Gold Stories

Next Story
Products

Koemmerling opens Navi Mumbai experience centre

Koemmerling, a brand of the profine Group, has expanded its presence in the Mumbai metropolitan region with the opening of a new experience centre in Navi Mumbai and launched its Allure S46 minimal sliding door system for the Indian market.Located in CBD Belapur, the facility was inaugurated by Peter Mrosik, Owner and CEO, profine Group, along with Farid Khan, Chairman and Managing Director, profine India, and Kamal Bajaj, CEO, profine India.The company said the new centre will showcase its portfolio of uPVC and aluminium window and door systems to architects, developers and homeowners.The ina..

Next Story
Products

India's waterproofing market nears Rs 150 bn milestone

India's waterproofing industry is approaching a market size of Rs 150 billion and is expected to surpass the $2 billion milestone, according to speakers at the 2nd India International Waterproofers Conference & Expo 2026 organised by the Waterproofers Association of India (WAI) in New Delhi.The two-day event brought together more than 20 speakers, 55 international delegates and 53 exhibition booths, with discussions focusing on climate-resilient construction, advanced waterproofing technologies and international collaboration.Inaugurating the event, Durga Shanker Mishra, former Secretary, ..

Next Story
Real Estate

Dilip Buildcon Q1 FY27 Revenue at Rs 23.78 billion

Dilip Buildcon Limited reported consolidated revenue from operations of Rs 2,378 crore in Q1 FY27, along with EBITDA of Rs 429 crore and profit after tax of Rs 128 crore.Consolidated EBITDA margin stood at 18.1%, improving from 17.1% in Q4 FY26. On a standalone basis, revenue from operations was Rs 1,930 crore, EBITDA stood at Rs 199 crore and PAT was Rs 39 crore, with an EBITDA margin of 10.3%.The company’s order book stood at Rs 27,691 crore as of 30 June 2026, compared with Rs 28,830 crore as of 31 March 2026. Roads and highways accounted for 17.1% of the order book, irrigation and water ..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement