300 Km Viaduct Complete on Mumbai-Ahmedabad Bullet Train
RAILWAYS & METRO RAIL

300 Km Viaduct Complete on Mumbai-Ahmedabad Bullet Train

Union Minister Ashwini Vaishnaw on Tuesday shared a major progress update on India’s ambitious Mumbai–Ahmedabad Bullet Train project. Posting a video on his official X handle, the Railway Minister announced that 300 kilometres of viaduct construction have been completed.

The National High-Speed Rail Corporation Limited (NHSRCL), which is overseeing the project, also reported that approximately 76 per cent of excavation work for the Mumbai bullet train station at Bandra Kurla Complex (BKC) has been completed. Notably, it will be the only underground station on the high-speed corridor.

Three batching plants with a capacity of 120 cubic metres per hour are currently operational at the site. The station features a modern concrete testing laboratory, equipped for water permeability and rapid chloride penetration testing.

Each base slab is being cast using M-60 grade temperature-controlled concrete, produced on-site using dedicated batching and chiller plants. The underground station will be about 26 metres deep, featuring three levels—platform, concourse, and service floors.

It will include six platforms, each approximately 415 metres long, designed to accommodate the high-speed trains. This update follows a similar announcement shared by the Minister earlier on 12 May.

Union Minister Ashwini Vaishnaw on Tuesday shared a major progress update on India’s ambitious Mumbai–Ahmedabad Bullet Train project. Posting a video on his official X handle, the Railway Minister announced that 300 kilometres of viaduct construction have been completed.The National High-Speed Rail Corporation Limited (NHSRCL), which is overseeing the project, also reported that approximately 76 per cent of excavation work for the Mumbai bullet train station at Bandra Kurla Complex (BKC) has been completed. Notably, it will be the only underground station on the high-speed corridor.Three batching plants with a capacity of 120 cubic metres per hour are currently operational at the site. The station features a modern concrete testing laboratory, equipped for water permeability and rapid chloride penetration testing.Each base slab is being cast using M-60 grade temperature-controlled concrete, produced on-site using dedicated batching and chiller plants. The underground station will be about 26 metres deep, featuring three levels—platform, concourse, and service floors.It will include six platforms, each approximately 415 metres long, designed to accommodate the high-speed trains. This update follows a similar announcement shared by the Minister earlier on 12 May.

Next Story
Real Estate

CREDAI-MCHI to Host 10th Design & Construction Conference

CREDAI-MCHI will host the 10th anniversary edition of its Design & Construction Conference on August 19, 2026, at the Jio World Convention Centre in Mumbai.The event is expected to bring together more than 500 procurement leaders, construction heads, architects, consultants and senior real estate decision-makers, alongside over 50 construction and ancillary brands.The conference will feature product launches, technology showcases, knowledge sessions, strategic business-to-business networking and recognition of procurement professionals contributing to the transformation of the construction..

Next Story
Infrastructure Energy

BorgWarner Wins Extension for High-Voltage Inverter Programmes

BorgWarner has secured a major extension of several high-volume high-voltage inverter programmes from a leading European automotive manufacturer.The contracts cover updated inverter designs for plug-in hybrid and 800V battery-electric vehicle applications. Production is scheduled to begin in 2029.Isabelle McKenzie, President and General Manager, BorgWarner PowerDrive Systems, said the programme extensions demonstrate the company’s position in power electronics and reflect the strength of its technology, in-house expertise and customer relationships.For plug-in hybrid vehicles, BorgWarner wil..

Next Story
Infrastructure Urban

Castrol India Q2 Profit Rises 43% to Rs 3.48 bn

Castrol India reported a 43 per cent year-on-year increase in profit after tax to Rs 3.48 billion for the quarter ended June 30, 2026, supported by growth across its consumer, industrial and institutional businesses.Revenue from operations increased 25 per cent to Rs 18.71 billion during the second quarter of 2026, compared with Rs 14.97 billion in the corresponding period of 2025. EBITDA rose 41 per cent to Rs 4.94 billion from Rs 3.50 billion.Sequentially, revenue increased from Rs 15.45 billion in the first quarter of 2026, while EBITDA rose from Rs 3.29 billion. Profit after tax increased ..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement