300 Km Viaduct Complete on Mumbai-Ahmedabad Bullet Train
RAILWAYS & METRO RAIL

300 Km Viaduct Complete on Mumbai-Ahmedabad Bullet Train

Union Minister Ashwini Vaishnaw on Tuesday shared a major progress update on India’s ambitious Mumbai–Ahmedabad Bullet Train project. Posting a video on his official X handle, the Railway Minister announced that 300 kilometres of viaduct construction have been completed.

The National High-Speed Rail Corporation Limited (NHSRCL), which is overseeing the project, also reported that approximately 76 per cent of excavation work for the Mumbai bullet train station at Bandra Kurla Complex (BKC) has been completed. Notably, it will be the only underground station on the high-speed corridor.

Three batching plants with a capacity of 120 cubic metres per hour are currently operational at the site. The station features a modern concrete testing laboratory, equipped for water permeability and rapid chloride penetration testing.

Each base slab is being cast using M-60 grade temperature-controlled concrete, produced on-site using dedicated batching and chiller plants. The underground station will be about 26 metres deep, featuring three levels—platform, concourse, and service floors.

It will include six platforms, each approximately 415 metres long, designed to accommodate the high-speed trains. This update follows a similar announcement shared by the Minister earlier on 12 May.

Union Minister Ashwini Vaishnaw on Tuesday shared a major progress update on India’s ambitious Mumbai–Ahmedabad Bullet Train project. Posting a video on his official X handle, the Railway Minister announced that 300 kilometres of viaduct construction have been completed.The National High-Speed Rail Corporation Limited (NHSRCL), which is overseeing the project, also reported that approximately 76 per cent of excavation work for the Mumbai bullet train station at Bandra Kurla Complex (BKC) has been completed. Notably, it will be the only underground station on the high-speed corridor.Three batching plants with a capacity of 120 cubic metres per hour are currently operational at the site. The station features a modern concrete testing laboratory, equipped for water permeability and rapid chloride penetration testing.Each base slab is being cast using M-60 grade temperature-controlled concrete, produced on-site using dedicated batching and chiller plants. The underground station will be about 26 metres deep, featuring three levels—platform, concourse, and service floors.It will include six platforms, each approximately 415 metres long, designed to accommodate the high-speed trains. This update follows a similar announcement shared by the Minister earlier on 12 May.

Next Story
Infrastructure Urban

Panasonic Showcases Connected Display Solutions

Panasonic Life Solutions India showcased its integrated display, projection, broadcast and communication technologies at Panasonic Tech Summit 2026 in New Delhi. Hosted through its System Solutions Division, the two-day event highlighted connected technology solutions for education, healthcare, retail, transportation, corporate offices and entertainment.The summit, themed ‘Turning Technology into Value’, featured experience-led zones covering QSR, retail, transit, corporate offices, healthcare, education, security, projection, home theatre and professional displays. Panasonic also introduc..

Next Story
Infrastructure Transport

Kapsch to Deliver India’s First C-ITS Project

"Kapsch TrafficCom will deliver India’s first Cooperative Intelligent Transport Systems project on a key expressway near New Delhi. The project will be implemented with Superwave Communication And Infrasolution Limited to demonstrate how connected mobility can improve road safety and traffic efficiency.The pilot will use real-time connectivity and AI-enabled situational awareness to support road users, especially in high-risk areas such as temporary work zones. Drivers will receive alerts on roadworks, maintenance vehicles, hazardous locations, traffic queues and temporary virtual signage di..

Next Story
Infrastructure Urban

Eurobond Net Profit Rises 44 Per Cent

Euro Panel Products, the parent company of Eurobond, reported a 44.13 per cent year-on-year rise in net profit for FY25–26. The company’s revenue from operations grew 18.91 per cent to Rs 503.20 crore, compared to Rs 423.18 crore in the previous financial year.The company’s full-year EBITDA stood at Rs 56.67 crore, marking a 31.82 per cent increase. Profit after tax rose to Rs 26.56 crore, while net worth increased 20.15 per cent to Rs 160.07 crore. Earnings per share for the year stood at Rs 10.84.Divyam Rajesh Shah, Whole Time Director and CFO, Euro Panel Products, said the company’s..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

-->