Chennai metro collects soil samples from Adyar bed from next week
RAILWAYS & METRO RAIL

Chennai metro collects soil samples from Adyar bed from next week

Starting next week, a team of engineers of Chennai metro will collect samples from the Adyar river bed ahead of tunnel construction to operate driverless trains. The test will be finished before tunnelling starts in October.

Twin for about 400 m lengths will be built under the river up to 29 m depth to connect Greenways Road metro station with Adyar junction station. For the three corridors 118.9 km phase-2 project, the deadline is 2025.

A metro rail official told the media that the samples would be collected at 12 m to 18 m depth for every 25 m to 50 m distance. Two drilling rigs will be deployed in specially designed boats measuring 10 m X 6 m.

It will take at least three to four months to finish the soil sample collection and investigation. Now, the water flowing in the river is at 6 m depth, so we require boats to take the rigs for sample collection.

While Chennai Metro Rail Limited (CMRL) had conducted soil tests before awarding construction contracts, the contractors were offered an option to do their tests. Thick sturdy tunnels will be constructed through rocky soil strata under the river, with heavily reinforced concrete slabs and additional grouting to seal the surface to ensure no water seepage.

In phase-1, tunnels were constructed under Buckingham Canal at about 30 m depth. Special tunnel rings with heavy reinforcement were created and established to counter the load from the top overburdened crust and the canal water. Under the Adyar river, the top of the tunnel will be at 18.75 m to 22.35 m depth from the river bed, while the bottom of the tunnel will be 25.05 m to 28.65 m depths.

Image Source

Also read: Construction work on Phase-2 Metro rail to begin soon in Chennai

Starting next week, a team of engineers of Chennai metro will collect samples from the Adyar river bed ahead of tunnel construction to operate driverless trains. The test will be finished before tunnelling starts in October. Twin for about 400 m lengths will be built under the river up to 29 m depth to connect Greenways Road metro station with Adyar junction station. For the three corridors 118.9 km phase-2 project, the deadline is 2025. A metro rail official told the media that the samples would be collected at 12 m to 18 m depth for every 25 m to 50 m distance. Two drilling rigs will be deployed in specially designed boats measuring 10 m X 6 m. It will take at least three to four months to finish the soil sample collection and investigation. Now, the water flowing in the river is at 6 m depth, so we require boats to take the rigs for sample collection. While Chennai Metro Rail Limited (CMRL) had conducted soil tests before awarding construction contracts, the contractors were offered an option to do their tests. Thick sturdy tunnels will be constructed through rocky soil strata under the river, with heavily reinforced concrete slabs and additional grouting to seal the surface to ensure no water seepage. In phase-1, tunnels were constructed under Buckingham Canal at about 30 m depth. Special tunnel rings with heavy reinforcement were created and established to counter the load from the top overburdened crust and the canal water. Under the Adyar river, the top of the tunnel will be at 18.75 m to 22.35 m depth from the river bed, while the bottom of the tunnel will be 25.05 m to 28.65 m depths. Image Source Also read: Construction work on Phase-2 Metro rail to begin soon in Chennai

Next Story
Technology

AI-Enabled Workflows Lift Profitability and Productivity

Organisations modernising frontline workflows with artificial intelligence, automation and real-time data are reporting stronger financial performance, higher productivity and improved employee engagement, according to a global study by Zebra Technologies and Oxford Economics.The research covered 1,000 senior leaders across retail, manufacturing, transportation and logistics in the US, Mexico, the UK, Germany, India, Japan, Australia and New Zealand.In transportation and logistics, 54 per cent of companies that improved picking and packing operations reported faster operational performance, wh..

Next Story
Real Estate

India Leads Global AI Readiness but Implementation Lags

Indian companies lead global averages across all eight artificial intelligence readiness indicators tracked by JLL, but only 19 per cent have started making changes to their workplaces, according to the JLL 2026 Future of Work Survey.The study found that 77 per cent of Indian business leaders expect AI to change their office requirements, creating a 58-percentage-point gap between awareness and implementation. The survey covered more than 2,200 CEOs, CFOs and real estate leaders across 21 countries during the first quarter of 2026.Despite concerns over automation, 58 per cent of Indian leaders..

Next Story
Equipment

Three WOLFF Cranes Build Riyadh Cable-Stayed Bridges

Three WOLFF 180 B luffing jib cranes are supporting the construction of two cable-stayed bridges alongside the existing Wadi Laban Bridge in Riyadh, Saudi Arabia. The project is being developed for the Royal Commission for Riyadh City and executed by the ICRC joint venture comprising IC Ictas and Al Rashid Trading & Contracting Company.The cranes are handling lifting operations including formwork, reinforcement, concrete placement, work platforms, surveying equipment and other construction materials. Each crane is fitted with a 40 m jib, reaches a hook height of 157 m and offers a maximum ..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement