Chennai metro collects soil samples from Adyar bed from next week
RAILWAYS & METRO RAIL

Chennai metro collects soil samples from Adyar bed from next week

Starting next week, a team of engineers of Chennai metro will collect samples from the Adyar river bed ahead of tunnel construction to operate driverless trains. The test will be finished before tunnelling starts in October.

Twin for about 400 m lengths will be built under the river up to 29 m depth to connect Greenways Road metro station with Adyar junction station. For the three corridors 118.9 km phase-2 project, the deadline is 2025.

A metro rail official told the media that the samples would be collected at 12 m to 18 m depth for every 25 m to 50 m distance. Two drilling rigs will be deployed in specially designed boats measuring 10 m X 6 m.

It will take at least three to four months to finish the soil sample collection and investigation. Now, the water flowing in the river is at 6 m depth, so we require boats to take the rigs for sample collection.

While Chennai Metro Rail Limited (CMRL) had conducted soil tests before awarding construction contracts, the contractors were offered an option to do their tests. Thick sturdy tunnels will be constructed through rocky soil strata under the river, with heavily reinforced concrete slabs and additional grouting to seal the surface to ensure no water seepage.

In phase-1, tunnels were constructed under Buckingham Canal at about 30 m depth. Special tunnel rings with heavy reinforcement were created and established to counter the load from the top overburdened crust and the canal water. Under the Adyar river, the top of the tunnel will be at 18.75 m to 22.35 m depth from the river bed, while the bottom of the tunnel will be 25.05 m to 28.65 m depths.

Image Source

Also read: Construction work on Phase-2 Metro rail to begin soon in Chennai

Starting next week, a team of engineers of Chennai metro will collect samples from the Adyar river bed ahead of tunnel construction to operate driverless trains. The test will be finished before tunnelling starts in October. Twin for about 400 m lengths will be built under the river up to 29 m depth to connect Greenways Road metro station with Adyar junction station. For the three corridors 118.9 km phase-2 project, the deadline is 2025. A metro rail official told the media that the samples would be collected at 12 m to 18 m depth for every 25 m to 50 m distance. Two drilling rigs will be deployed in specially designed boats measuring 10 m X 6 m. It will take at least three to four months to finish the soil sample collection and investigation. Now, the water flowing in the river is at 6 m depth, so we require boats to take the rigs for sample collection. While Chennai Metro Rail Limited (CMRL) had conducted soil tests before awarding construction contracts, the contractors were offered an option to do their tests. Thick sturdy tunnels will be constructed through rocky soil strata under the river, with heavily reinforced concrete slabs and additional grouting to seal the surface to ensure no water seepage. In phase-1, tunnels were constructed under Buckingham Canal at about 30 m depth. Special tunnel rings with heavy reinforcement were created and established to counter the load from the top overburdened crust and the canal water. Under the Adyar river, the top of the tunnel will be at 18.75 m to 22.35 m depth from the river bed, while the bottom of the tunnel will be 25.05 m to 28.65 m depths. Image Source Also read: Construction work on Phase-2 Metro rail to begin soon in Chennai

Next Story
Infrastructure Transport

Shivraj Chouhan Launches PMGSY IV and Announces Package for Madhya Pradesh

Union Minister Shivraj Singh Chouhan launched the Pradhan Mantri Gram Sadak Yojana (PMGSY) IV at Bhairunda in Sehore district during the 25 year celebrations and announced a development package for Madhya Pradesh. The programme was organised by the Union Ministry of Rural Development and attended by Chief Minister Dr Mohan Yadav, ministers of state, state ministers, legislators and senior officials from the centre and the state. The minister said the central government under the Prime Minister is committed to strengthening rural livelihoods through improved connectivity, housing and women's in..

Next Story
Infrastructure Urban

DMR Engineering Reports FY 25-26 Financial Results

DMR Engineering reported its half year results for the financial year ended 31 March 2026 and published full year figures on a standalone basis. Standalone revenue from operations decreased by 2.01 per cent year-over-year to Rs 102.58 million (mn), while profit after tax declined by 43.94 per cent to nine point five six mn, leaving a profit after tax margin of nine point zero five per cent. Earnings per share stood at Rs zero point nine two, a fall of 44.71 per cent year-over-year. The company attributed part of the decline to one-off provisioning for bad debts and additional financing charges..

Next Story
Infrastructure Urban

Atlanta Electricals Posts Strong FY26 Growth And Debt Free Finish

Atlanta Electricals reported audited consolidated results for the quarter and year ended 31 March 2026. The company recorded significant year-on-year revenue growth driven by capacity ramp-up at new facilities and higher utilisation at legacy plants. The announcement summarised operating improvements and strategic milestones achieved during the year. For Q4 the company reported revenue of Rs 7.48 bn and for FY26 revenue of Rs 18.52 bn, representing robust growth versus the prior year. EBITDA in Q4 was Rs. 1.49 bn and Rs. 3.44 bn for the full year, with margins expanding to 20 per cent in the q..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement