Chennai metro collects soil samples from Adyar bed from next week
RAILWAYS & METRO RAIL

Chennai metro collects soil samples from Adyar bed from next week

Starting next week, a team of engineers of Chennai metro will collect samples from the Adyar river bed ahead of tunnel construction to operate driverless trains. The test will be finished before tunnelling starts in October.

Twin for about 400 m lengths will be built under the river up to 29 m depth to connect Greenways Road metro station with Adyar junction station. For the three corridors 118.9 km phase-2 project, the deadline is 2025.

A metro rail official told the media that the samples would be collected at 12 m to 18 m depth for every 25 m to 50 m distance. Two drilling rigs will be deployed in specially designed boats measuring 10 m X 6 m.

It will take at least three to four months to finish the soil sample collection and investigation. Now, the water flowing in the river is at 6 m depth, so we require boats to take the rigs for sample collection.

While Chennai Metro Rail Limited (CMRL) had conducted soil tests before awarding construction contracts, the contractors were offered an option to do their tests. Thick sturdy tunnels will be constructed through rocky soil strata under the river, with heavily reinforced concrete slabs and additional grouting to seal the surface to ensure no water seepage.

In phase-1, tunnels were constructed under Buckingham Canal at about 30 m depth. Special tunnel rings with heavy reinforcement were created and established to counter the load from the top overburdened crust and the canal water. Under the Adyar river, the top of the tunnel will be at 18.75 m to 22.35 m depth from the river bed, while the bottom of the tunnel will be 25.05 m to 28.65 m depths.

Image Source

Also read: Construction work on Phase-2 Metro rail to begin soon in Chennai

Starting next week, a team of engineers of Chennai metro will collect samples from the Adyar river bed ahead of tunnel construction to operate driverless trains. The test will be finished before tunnelling starts in October. Twin for about 400 m lengths will be built under the river up to 29 m depth to connect Greenways Road metro station with Adyar junction station. For the three corridors 118.9 km phase-2 project, the deadline is 2025. A metro rail official told the media that the samples would be collected at 12 m to 18 m depth for every 25 m to 50 m distance. Two drilling rigs will be deployed in specially designed boats measuring 10 m X 6 m. It will take at least three to four months to finish the soil sample collection and investigation. Now, the water flowing in the river is at 6 m depth, so we require boats to take the rigs for sample collection. While Chennai Metro Rail Limited (CMRL) had conducted soil tests before awarding construction contracts, the contractors were offered an option to do their tests. Thick sturdy tunnels will be constructed through rocky soil strata under the river, with heavily reinforced concrete slabs and additional grouting to seal the surface to ensure no water seepage. In phase-1, tunnels were constructed under Buckingham Canal at about 30 m depth. Special tunnel rings with heavy reinforcement were created and established to counter the load from the top overburdened crust and the canal water. Under the Adyar river, the top of the tunnel will be at 18.75 m to 22.35 m depth from the river bed, while the bottom of the tunnel will be 25.05 m to 28.65 m depths. Image Source Also read: Construction work on Phase-2 Metro rail to begin soon in Chennai

Next Story
Infrastructure Urban

Vice-President Backs Global Unity at IN-STEP 2025

Vice-President of India, Shri C. P. Radhakrishnan, addressed delegates at the 3rd edition of the International Strategic Engagement Programme (IN-STEP) held at the Vice-President’s Enclave in New Delhi. IN-STEP serves as a key dialogue platform for senior national security officers from India and friendly foreign nations. The current edition hosts 44 delegates, including 32 international participants representing 24 Global South countries. Commending the joint efforts of the National Defence College, National Security Council Secretariat, Ministry of External Affairs, and Ministry of Defen..

Next Story
Infrastructure Urban

India to Host Global Maritime Events in Visakhapatnam

India will host three major international maritime events in February 2026 at Visakhapatnam — the International Fleet Review (IFR) 2026, Exercise MILAN 2026, and the Indian Ocean Naval Symposium (IONS) Conclave of Chiefs. Scheduled from 15 to 25 February 2026, this marks the first time India will conduct all three significant maritime gatherings simultaneously. The events embody Prime Minister Shri Narendra Modi’s MAHASAGAR vision — Mutual and Holistic Advancement for Security and Growth Across Regions — announced in 2025. The MAHASAGAR framework extends India’s SAGAR (Security and ..

Next Story
Infrastructure Urban

Heavy Industries Ministry Frees 4.4 Million Sq Ft Under SCDPM 5.0

Inspired by the Prime Minister’s vision to institutionalise Swachhata and clear long-pending matters, the Ministry of Heavy Industries (MHI), along with its Central Public Sector Enterprises (CPSEs) and Autonomous Bodies (ABs), actively participated in the fifth consecutive year of the Special Campaign for Disposal of Pending Matters (SCDPM) 5.0, held from 2 to 31 October 2025. Throughout the campaign, MHI worked closely with the Department of Administrative Reforms and Public Grievances, reporting daily progress on a dedicated monitoring portal. Shri Bhupathi Raju Srinivasa Varma, Minister..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Talk to us?