Chennai metro collects soil samples from Adyar bed from next week
RAILWAYS & METRO RAIL

Chennai metro collects soil samples from Adyar bed from next week

Starting next week, a team of engineers of Chennai metro will collect samples from the Adyar river bed ahead of tunnel construction to operate driverless trains. The test will be finished before tunnelling starts in October.

Twin for about 400 m lengths will be built under the river up to 29 m depth to connect Greenways Road metro station with Adyar junction station. For the three corridors 118.9 km phase-2 project, the deadline is 2025.

A metro rail official told the media that the samples would be collected at 12 m to 18 m depth for every 25 m to 50 m distance. Two drilling rigs will be deployed in specially designed boats measuring 10 m X 6 m.

It will take at least three to four months to finish the soil sample collection and investigation. Now, the water flowing in the river is at 6 m depth, so we require boats to take the rigs for sample collection.

While Chennai Metro Rail Limited (CMRL) had conducted soil tests before awarding construction contracts, the contractors were offered an option to do their tests. Thick sturdy tunnels will be constructed through rocky soil strata under the river, with heavily reinforced concrete slabs and additional grouting to seal the surface to ensure no water seepage.

In phase-1, tunnels were constructed under Buckingham Canal at about 30 m depth. Special tunnel rings with heavy reinforcement were created and established to counter the load from the top overburdened crust and the canal water. Under the Adyar river, the top of the tunnel will be at 18.75 m to 22.35 m depth from the river bed, while the bottom of the tunnel will be 25.05 m to 28.65 m depths.

Image Source

Also read: Construction work on Phase-2 Metro rail to begin soon in Chennai

Starting next week, a team of engineers of Chennai metro will collect samples from the Adyar river bed ahead of tunnel construction to operate driverless trains. The test will be finished before tunnelling starts in October. Twin for about 400 m lengths will be built under the river up to 29 m depth to connect Greenways Road metro station with Adyar junction station. For the three corridors 118.9 km phase-2 project, the deadline is 2025. A metro rail official told the media that the samples would be collected at 12 m to 18 m depth for every 25 m to 50 m distance. Two drilling rigs will be deployed in specially designed boats measuring 10 m X 6 m. It will take at least three to four months to finish the soil sample collection and investigation. Now, the water flowing in the river is at 6 m depth, so we require boats to take the rigs for sample collection. While Chennai Metro Rail Limited (CMRL) had conducted soil tests before awarding construction contracts, the contractors were offered an option to do their tests. Thick sturdy tunnels will be constructed through rocky soil strata under the river, with heavily reinforced concrete slabs and additional grouting to seal the surface to ensure no water seepage. In phase-1, tunnels were constructed under Buckingham Canal at about 30 m depth. Special tunnel rings with heavy reinforcement were created and established to counter the load from the top overburdened crust and the canal water. Under the Adyar river, the top of the tunnel will be at 18.75 m to 22.35 m depth from the river bed, while the bottom of the tunnel will be 25.05 m to 28.65 m depths. Image Source Also read: Construction work on Phase-2 Metro rail to begin soon in Chennai

Next Story
Real Estate

Serene, Gardencity to Develop Rs 3 Billion Senior Living Project in Bengaluru

Serene Communities, a leading senior living brand, has partnered with Gardencity Realty to develop a premium senior living community in Budigere, one of Bengaluru’s fastest-growing residential micro-markets. The project will span approximately 300,000 sq ft, with a Gross Development Value of about Rs 3 billion, and will add roughly 250 senior-friendly residences to the city’s growing retirement housing segment.The launch forms part of Serene Communities’ national expansion strategy. The company has 11 new projects under development with a planned investment of Rs 25 billion that will add..

Next Story
Real Estate

Alliance City Developers Marks Major 2025 Milestones in Vile Parle

Alliance City Developers Realtors has announced significant project milestones and expansions in 2025, underscoring what the company terms a transformational year. The developer completed multiple residential projects and launched two premium developments in Vile Parle (East), one of Mumbai’s most sought-after neighbourhoods.During the year, Alliance Legacy in Matunga (East) received its Occupancy Certificate (OC), while Alliance Eternis in Borivali (West) and Alliance Vista in Vile Parle (East) were granted Completion Certificates (CC), marking final project delivery. Alliance Abhimanyu is ..

Next Story
Infrastructure Energy

Moro Hub and PwC Middle East Partner to Accelerate Smart City Solutions

Moro Hub, a subsidiary of Digital DEWA, the digital arm of Dubai Electricity and Water Authority (DEWA), has announced a strategic collaboration with PwC Middle East to advance Smart City, Integrated Command Centre (ICC), Critical Infrastructure Monitoring and Internet of Things (IoT) initiatives across the region. The partnership brings together Moro Hub’s digital infrastructure and IoT capabilities with PwC’s global expertise in digital trust, smart city strategy and cybersecurity to support the UAE’s vision for intelligent and sustainable cities.“Our collaboration with PwC Middle Ea..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Advertisement

Get CW App