+
Chennai Metro Phase II underground work faces 9-month delay
RAILWAYS & METRO RAIL

Chennai Metro Phase II underground work faces 9-month delay

The construction of the underground section of Chennai Metro Rail's Phase II may get pushed back by around nine months, as there is a delay in the tender process.

The initial deadline for the underground section was December 2025. Tenders for construction of a portion of an underground section and some underground stations were cancelled in December 2021 and are yet to be re-floated. Phase II project covers 118.9 km with 128 stations, including a 43 km underground section with 48 stations.

A CMRL official said the tender for construction of an underground section from Kolathur to Nathamuni covering 5.6 km on corridor-5 was cancelled as there was a lack of takers for building the line. Officials said the few bids made were significantly higher than CMRL's estimate.

"We met with very poor response for the Kolathur-Nathamuni stretch primarily because of a JICA requirement that we must procure from Japanese companies or Indian companies or a joint venture of Japanese and Indian companies ... we will get clearance soon," the official said.

JICA is funding construction of 52 km stretch in phase-2 from Madhavaram to Sholinganallur on corridor-3 and Madhavaram to CMBT on corridor-5.

See also:
Anand Vihar RRTS to be a first-of-its-kind underground station
Mitsubishi to supply simulators for bullet train project


The construction of the underground section of Chennai Metro Rail's Phase II may get pushed back by around nine months, as there is a delay in the tender process. The initial deadline for the underground section was December 2025. Tenders for construction of a portion of an underground section and some underground stations were cancelled in December 2021 and are yet to be re-floated. Phase II project covers 118.9 km with 128 stations, including a 43 km underground section with 48 stations. A CMRL official said the tender for construction of an underground section from Kolathur to Nathamuni covering 5.6 km on corridor-5 was cancelled as there was a lack of takers for building the line. Officials said the few bids made were significantly higher than CMRL's estimate. We met with very poor response for the Kolathur-Nathamuni stretch primarily because of a JICA requirement that we must procure from Japanese companies or Indian companies or a joint venture of Japanese and Indian companies ... we will get clearance soon, the official said. JICA is funding construction of 52 km stretch in phase-2 from Madhavaram to Sholinganallur on corridor-3 and Madhavaram to CMBT on corridor-5.See also: Anand Vihar RRTS to be a first-of-its-kind underground stationMitsubishi to supply simulators for bullet train project

Next Story
Infrastructure Urban

ABB to Invest Rs 6.25 Billion to Expand India Manufacturing

ABB recently announced plans to invest approximately Rs 6.25 billion ($75 million) in India during 2026 to expand its manufacturing footprint and research and development capabilities. The investment follows more than $35 million spent in 2025 and reflects the company’s continued focus on strengthening its ‘local-for-local’ strategy in the country.The investment will support ABB’s Electrification, Motion and Automation businesses and expand manufacturing capacity for infrastructure sectors such as renewable energy, metro rail, data centres and industrial applications. Approximately 300..

Next Story
Equipment

Six WOLFF Cranes Handle 60,000 m³ Concrete for German Hospital

Six WOLFF tower cranes are playing a key role in constructing a new hospital complex in Memmingen, Germany, supporting large-scale material handling for the project. The facility is being built on a 7.7-hectare site and will feature six floors, around 480 beds and a gross floor area exceeding 75,000 sq m.Building shell works began recently in February 2025. One WOLFF 6531.12 Cross crane supported early site preparation before being dismantled in autumn 2025, while five remaining cranes continue operations. Over an average deployment period of 16 months, the cranes are expected to move approxim..

Next Story
Equipment

REC Funds Rs 115.6 Million CSR Support for Bihar Eye Hospital

REC recently committed Rs 115.6 million under its Corporate Social Responsibility (CSR) programme for the procurement of clinical and non-clinical equipment at Sankara Eye Hospital in Saharsa, Bihar. The initiative aims to strengthen healthcare infrastructure and improve access to specialised eye care services in the region.A Memorandum of Agreement (MoA) was recently signed between Pradeep Fellows, Executive Director (CSR), REC Limited, and Wg Cdr V. Shankar (Retd), Trustee and Executive Director of Sankara Eye Hospital, at the REC office in the SCOPE Complex, New Delhi.The support is expecte..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement