DMRC Completes Tunnel Under Red Line Without Halting Services
RAILWAYS & METRO RAIL

DMRC Completes Tunnel Under Red Line Without Halting Services

The Delhi Metro Rail Corporation (DMRC) has achieved a major engineering feat by constructing an underground tunnel beneath the operational Red Line at Pulbangash without suspending train services even for a single day. The tunnel forms part of the Janakpuri West–RK Ashram Marg extension of the Magenta Line under Phase IV.

In an update shared on X, DMRC highlighted the complexity of the operation, noting that tunnelling between Pulbangash and Sadar Bazar stations was carried out while trains continued to run normally on the elevated Red Line viaduct above. The viaduct at this location stands on open foundations with a balanced cantilever span, requiring exceptional engineering precautions during tunnelling.

To ensure structural stability, engineers implemented an extensive strengthening strategy around the Red Line pier. A grouting programme known as TAM (Tube-a-Manchette) was executed, involving the installation of 180 TAM boreholes around the pier. High-strength cement grouting was then undertaken to stabilise the soil, fill voids and enhance load-bearing capacity. DMRC added that every measure was taken to eliminate any risk of soil settlement during tunnelling.

Real-time safety monitoring was conducted using advanced instrumentation, including surface settlement markers, deep inclinometers, building settlement points, pier tilt metres, load cells and an Automatic Total Station (ATS). A dedicated team monitored these parameters round the clock, and all readings remained within permissible safety limits throughout the operation.

DMRC confirmed that the down-line tunnel on this stretch has now been completed, while work on the up-line tunnel is progressing with the same level of caution and monitoring. With the Red Line carrying around 7 lakh (0.7 million) passengers daily, the corporation emphasised that avoiding service disruption was critical to preventing widespread public inconvenience.

The Delhi Metro Rail Corporation (DMRC) has achieved a major engineering feat by constructing an underground tunnel beneath the operational Red Line at Pulbangash without suspending train services even for a single day. The tunnel forms part of the Janakpuri West–RK Ashram Marg extension of the Magenta Line under Phase IV. In an update shared on X, DMRC highlighted the complexity of the operation, noting that tunnelling between Pulbangash and Sadar Bazar stations was carried out while trains continued to run normally on the elevated Red Line viaduct above. The viaduct at this location stands on open foundations with a balanced cantilever span, requiring exceptional engineering precautions during tunnelling. To ensure structural stability, engineers implemented an extensive strengthening strategy around the Red Line pier. A grouting programme known as TAM (Tube-a-Manchette) was executed, involving the installation of 180 TAM boreholes around the pier. High-strength cement grouting was then undertaken to stabilise the soil, fill voids and enhance load-bearing capacity. DMRC added that every measure was taken to eliminate any risk of soil settlement during tunnelling. Real-time safety monitoring was conducted using advanced instrumentation, including surface settlement markers, deep inclinometers, building settlement points, pier tilt metres, load cells and an Automatic Total Station (ATS). A dedicated team monitored these parameters round the clock, and all readings remained within permissible safety limits throughout the operation. DMRC confirmed that the down-line tunnel on this stretch has now been completed, while work on the up-line tunnel is progressing with the same level of caution and monitoring. With the Red Line carrying around 7 lakh (0.7 million) passengers daily, the corporation emphasised that avoiding service disruption was critical to preventing widespread public inconvenience.

Related Stories

Gold Stories

Next Story
Resources

Schindler named among Forbes’ World’s Best Employers 2026

Schindler has been named among Forbes’ World’s Best Employers 2026, a global ranking recognising companies for their workplace environments.Compiled by Forbes in partnership with Statista, the ranking is based on independent employee feedback, including whether employees would recommend their organisation to friends and family.The company said the recognition reflected its focus on creating a workplace where employees can develop their expertise and build careers. ..

Next Story
Infrastructure Urban

India needs an export-execution mindset: Vishesh Jain

Interview with Vishesh Jain, Founder & CEO, EximpleWhat gaps in India’s global trade ecosystem led you to build Eximple, and what problem did you see businesses struggling with most?Eximple came out of a problem that all three founders had seen from different choke points in the trade ecosystem. India has millions of MSMEs and manufacturers, and many of them can make products that are genuinely competitive on quality. Yet only a small fraction is able to build meaningful international businesses. In our experience, the gap is usually not manufacturing capability; it is the ability to exe..

Next Story
Building Material

Nuvoco reports 13.5% revenue growth in Q2 FY27

Nuvoco Vistas Corp. Ltd. reported consolidated revenue of Rs 27.9 billion for Q2 FY27, up 13.5% year on year. Cement sales volume rose 9% to 4.7 million tonnes (MMT), while EBITDA increased 11% to Rs 4.11 billion.The company said it began its cement operations in 2014 with a 2.3 MMT per annum (MMTPA) operation at Nimbol. It now aims to reach 35 MMTPA of cement capacity by FY28, nearly 15 times its initial capacity. Its portfolio spans cement, ready-mix concrete and modern building materials.On sustainability and cost efficiency, Nuvoco partnered with CleanMax for a 46.4 MW wind-solar hybrid re..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

SPECIAL OFFER
QR Code