DMRC Completes Tunnel Under Red Line Without Halting Services
RAILWAYS & METRO RAIL

DMRC Completes Tunnel Under Red Line Without Halting Services

The Delhi Metro Rail Corporation (DMRC) has achieved a major engineering feat by constructing an underground tunnel beneath the operational Red Line at Pulbangash without suspending train services even for a single day. The tunnel forms part of the Janakpuri West–RK Ashram Marg extension of the Magenta Line under Phase IV.

In an update shared on X, DMRC highlighted the complexity of the operation, noting that tunnelling between Pulbangash and Sadar Bazar stations was carried out while trains continued to run normally on the elevated Red Line viaduct above. The viaduct at this location stands on open foundations with a balanced cantilever span, requiring exceptional engineering precautions during tunnelling.

To ensure structural stability, engineers implemented an extensive strengthening strategy around the Red Line pier. A grouting programme known as TAM (Tube-a-Manchette) was executed, involving the installation of 180 TAM boreholes around the pier. High-strength cement grouting was then undertaken to stabilise the soil, fill voids and enhance load-bearing capacity. DMRC added that every measure was taken to eliminate any risk of soil settlement during tunnelling.

Real-time safety monitoring was conducted using advanced instrumentation, including surface settlement markers, deep inclinometers, building settlement points, pier tilt metres, load cells and an Automatic Total Station (ATS). A dedicated team monitored these parameters round the clock, and all readings remained within permissible safety limits throughout the operation.

DMRC confirmed that the down-line tunnel on this stretch has now been completed, while work on the up-line tunnel is progressing with the same level of caution and monitoring. With the Red Line carrying around 7 lakh (0.7 million) passengers daily, the corporation emphasised that avoiding service disruption was critical to preventing widespread public inconvenience.

"Join industry leaders at RAHSTA Expo, India's premier platform for roads, highways and traffic infrastructure. Register now to explore innovations, network with experts and shape the future of mobility."

The Delhi Metro Rail Corporation (DMRC) has achieved a major engineering feat by constructing an underground tunnel beneath the operational Red Line at Pulbangash without suspending train services even for a single day. The tunnel forms part of the Janakpuri West–RK Ashram Marg extension of the Magenta Line under Phase IV. In an update shared on X, DMRC highlighted the complexity of the operation, noting that tunnelling between Pulbangash and Sadar Bazar stations was carried out while trains continued to run normally on the elevated Red Line viaduct above. The viaduct at this location stands on open foundations with a balanced cantilever span, requiring exceptional engineering precautions during tunnelling. To ensure structural stability, engineers implemented an extensive strengthening strategy around the Red Line pier. A grouting programme known as TAM (Tube-a-Manchette) was executed, involving the installation of 180 TAM boreholes around the pier. High-strength cement grouting was then undertaken to stabilise the soil, fill voids and enhance load-bearing capacity. DMRC added that every measure was taken to eliminate any risk of soil settlement during tunnelling. Real-time safety monitoring was conducted using advanced instrumentation, including surface settlement markers, deep inclinometers, building settlement points, pier tilt metres, load cells and an Automatic Total Station (ATS). A dedicated team monitored these parameters round the clock, and all readings remained within permissible safety limits throughout the operation. DMRC confirmed that the down-line tunnel on this stretch has now been completed, while work on the up-line tunnel is progressing with the same level of caution and monitoring. With the Red Line carrying around 7 lakh (0.7 million) passengers daily, the corporation emphasised that avoiding service disruption was critical to preventing widespread public inconvenience.

Next Story
Infrastructure Urban

ABS Marine Sees CRISIL Credit Rating Upgrade

ABS Marine Services has secured an upgrade to its long term and short term credit ratings from CRISIL, reflecting improved profitability and revenue growth through long term contracts. CRISIL moved the long term rating from BBB+/Stable to A-/Stable and revised the short term rating from A2 to A2+. The action signals strengthened financial metrics and operational resilience. The company benefited from durable client relationships with firms such as ONGC and Schlumberger. The rating decision followed stronger cash flows and an enlarged bank loan facility, which increased from Rs 3,705 million (m..

Next Story
Infrastructure Transport

Project BRAHMANK Marks 16 Years Of Strategic Roads In Arunachal

Project BRAHMANK is marking 16 years of work to establish strategic road and bridge links across Arunachal Pradesh, maintaining and developing 811 kilometres of roads and nearly 86 bridges that range from small culverts to large steel and arch bridges. These transport links are described as critical for ensuring year-round movement of defence personnel, equipment and essential supplies while improving everyday travel for people in remote villages. The project balances national security requirements with regional development by focusing on reliable access in challenging terrain. Notable enginee..

Next Story
Infrastructure Transport

Longleng CSOs Give One Week Ultimatum Over Two-Lane Highway

Civil society organisations (CSOs) in Longleng district have demanded immediate restoration of the deteriorating Changtongya–Longleng two-lane road and sought a detailed status report on the stalled construction within one week. The demand followed a consultative meeting convened under the Phom Peoples' Council (PPC) to discuss welfare and development concerns. PPC president YB Angam Phom said prolonged non-maintenance had caused hardship to commuters and affected transportation, local commerce and the district's development. The meeting urged authorities to undertake immediate restoration a..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement