Pune Metro Line III Completion Likely Delayed to September 2025
RAILWAYS & METRO RAIL

Pune Metro Line III Completion Likely Delayed to September 2025

Pune Metro Line III, connecting Hinjawadi to Shivajinagar, is now expected to be completed by September 2025, following a request from the concessionaire for an extension. The original target for completion was March 2025. According to PMRDA officials, the delay is mainly due to issues with the integrated flyover component, which was initially set for December 2024 completion but is now projected to finish by March 2025.

The overall 23-km corridor is 74 per cent complete, with the integrated flyover at 65 per cent. The critical ramp and deck slabs are still under construction, and the 1.7-km flyover is expected to be completed by April 2025. Despite multiple review meetings and expedited efforts, heavy traffic and delays in obtaining necessary permissions have hindered progress.

With Chief Minister Devendra Fadnavis and Deputy CM Ajit Pawar overseeing the project, revised timelines will be discussed. The government is also working to address the remaining challenges, including road widening and the relocation of utilities along the University Chowk stretch.

While Metro stations from Maan to Balewadi Highstreet are expected to be operational by April, the University Chowk stretch faces further delays due to the need for road modifications. The government has allocated additional funds to ensure timely completion, with Rs 6 billion (bn) of the Rs 12 bn commitment already released.

Pune Metro Line III, connecting Hinjawadi to Shivajinagar, is now expected to be completed by September 2025, following a request from the concessionaire for an extension. The original target for completion was March 2025. According to PMRDA officials, the delay is mainly due to issues with the integrated flyover component, which was initially set for December 2024 completion but is now projected to finish by March 2025. The overall 23-km corridor is 74 per cent complete, with the integrated flyover at 65 per cent. The critical ramp and deck slabs are still under construction, and the 1.7-km flyover is expected to be completed by April 2025. Despite multiple review meetings and expedited efforts, heavy traffic and delays in obtaining necessary permissions have hindered progress. With Chief Minister Devendra Fadnavis and Deputy CM Ajit Pawar overseeing the project, revised timelines will be discussed. The government is also working to address the remaining challenges, including road widening and the relocation of utilities along the University Chowk stretch. While Metro stations from Maan to Balewadi Highstreet are expected to be operational by April, the University Chowk stretch faces further delays due to the need for road modifications. The government has allocated additional funds to ensure timely completion, with Rs 6 billion (bn) of the Rs 12 bn commitment already released.

Next Story
Infrastructure Transport

MMRDA advances 250 m on Orange Gate–Marine Drive tunnel

The Mumbai Metropolitan Region Development Authority (MMRDA) has completed 250 m of underground tunnelling for the Orange Gate–Marine Drive Urban Road Tunnel using India’s largest slurry shield tunnel boring machine (TBM) deployed for an urban road project.The project involves twin tunnels extending over 7 km beneath critical transport corridors, including Central Railway, Western Railway and Metro Line 3. The work requires high-precision engineering to navigate densely developed urban infrastructure.Once completed, the tunnel is expected to reduce travel time between Orange Gate and Marin..

Next Story
Infrastructure Urban

Hindustan Zinc Pays Rs 188.46 Billion in FY26

Hindustan Zinc contributed Rs 188.46 billion to the public exchequer in FY 2025-26, according to its 9th Tax Transparency Report. The contribution, equivalent to 46 per cent of the company’s revenue, included direct and indirect taxes, government royalties, dividends to the Government of India, withholding taxes and other statutory levies.The company’s five-year cumulative contribution to the exchequer stood at Rs 915.72 billion. In FY26, Hindustan Zinc reported revenue of Rs 408.44 billion, EBITDA of Rs 221.62 billion and profit after tax of Rs 138.32 billion. It also achieved its highest..

Next Story
Infrastructure Urban

World of Concrete India 2026 Opens in Mumbai

Informa Markets in India will host the 12th edition of World of Concrete India 2026 from 3–5 June 2026 at the Bombay Exhibition Centre, Mumbai. The specialised B2B exhibition will bring together manufacturers, suppliers, contractors, developers, architects, consultants, infrastructure companies, project leaders and government stakeholders.The event is expected to feature over 350 brands and more than 18,000 trade professionals. It will cover concrete and cement, dry mortar, precast technologies, formwork, construction chemicals, industrial and commercial flooring, scaffolding, safety solutio..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

-->