Pune Metro Line III Completion Likely Delayed to September 2025
RAILWAYS & METRO RAIL

Pune Metro Line III Completion Likely Delayed to September 2025

Pune Metro Line III, connecting Hinjawadi to Shivajinagar, is now expected to be completed by September 2025, following a request from the concessionaire for an extension. The original target for completion was March 2025. According to PMRDA officials, the delay is mainly due to issues with the integrated flyover component, which was initially set for December 2024 completion but is now projected to finish by March 2025.

The overall 23-km corridor is 74 per cent complete, with the integrated flyover at 65 per cent. The critical ramp and deck slabs are still under construction, and the 1.7-km flyover is expected to be completed by April 2025. Despite multiple review meetings and expedited efforts, heavy traffic and delays in obtaining necessary permissions have hindered progress.

With Chief Minister Devendra Fadnavis and Deputy CM Ajit Pawar overseeing the project, revised timelines will be discussed. The government is also working to address the remaining challenges, including road widening and the relocation of utilities along the University Chowk stretch.

While Metro stations from Maan to Balewadi Highstreet are expected to be operational by April, the University Chowk stretch faces further delays due to the need for road modifications. The government has allocated additional funds to ensure timely completion, with Rs 6 billion (bn) of the Rs 12 bn commitment already released.

Pune Metro Line III, connecting Hinjawadi to Shivajinagar, is now expected to be completed by September 2025, following a request from the concessionaire for an extension. The original target for completion was March 2025. According to PMRDA officials, the delay is mainly due to issues with the integrated flyover component, which was initially set for December 2024 completion but is now projected to finish by March 2025. The overall 23-km corridor is 74 per cent complete, with the integrated flyover at 65 per cent. The critical ramp and deck slabs are still under construction, and the 1.7-km flyover is expected to be completed by April 2025. Despite multiple review meetings and expedited efforts, heavy traffic and delays in obtaining necessary permissions have hindered progress. With Chief Minister Devendra Fadnavis and Deputy CM Ajit Pawar overseeing the project, revised timelines will be discussed. The government is also working to address the remaining challenges, including road widening and the relocation of utilities along the University Chowk stretch. While Metro stations from Maan to Balewadi Highstreet are expected to be operational by April, the University Chowk stretch faces further delays due to the need for road modifications. The government has allocated additional funds to ensure timely completion, with Rs 6 billion (bn) of the Rs 12 bn commitment already released.

Next Story
Real Estate

Integrated Waterproofing Strategies

Waterproofing buildings used to be an annual pre-monsoon affair but the evolution of real-estate development has changed that approach. In new developments, developers are weaving waterproofing solutions into both the design and construction phases, an approach that Nikhil Madan, Managing Director, Mahima Group, says, “is all about ensuring lasting durability [of the building] and keeping lifecycle risks including water seepage and extensive maintenance to a minimum.”Watertight by designAluminium formwork systems aren’t commonly thought of as a waterproofing tool but at the Mahima Group,..

Next Story
Infrastructure Urban

GROHE Showcases Water-Led Design At Milan

GROHE unveiled its GROHE SPA Aqua Sanctuary at Milan Design Week 2026, transforming Piccolo Teatro Studio Melato into an immersive showcase of water, design and wellbeing. Built on the philosophy of ‘Wellbeing Through Water’, the installation reimagined bathrooms as holistic spaces for relaxation, rejuvenation and self-care.The Aqua Sanctuary was presented through three interconnected sanctums. The first showcased the 3D-printed GROHE SPA AquaTree shower and faucet, highlighting bespoke innovation and biophilic design. The second featured the Atrio Private Collection and GROHE SPA x Buster..

Next Story
Infrastructure Transport

Rahee Group Expands Rail Manufacturing Capacity

Rahee Group has outlined a multi-year investment roadmap to expand its operational footprint and strengthen manufacturing capabilities for India’s growing railway and urban transit sector. The Group is expanding in Odisha with a new Track Component Casting Unit, for which the groundbreaking ceremony was held on 8 April 2026 in the presence of Odisha Chief Minister Mohan Charan Majhi.The Group’s flagship EPC arm, Rahee Infratech Ltd, continues to focus on complex rail infrastructure projects, including track systems, bridges, viaducts and ballastless infrastructure. Its wholly owned subsidi..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement