Rail Electrification Now Set for FY26 End
RAILWAYS & METRO RAIL

Rail Electrification Now Set for FY26 End

Indian Railways' ambitious broad-gauge electrification drive has hit delays, pushing the revised completion target to the end of FY26. Initially aimed for September 2024, the project now faces bottlenecks in last-mile connections—especially in Assam, Karnataka, Tamil Nadu, and parts of Rajasthan and Goa. As of March 2025, 68,701 km, or 98.83 per cent of the 69,512 km network, has been electrified, according to the Ministry of Railways.

Progress has been hampered by geographic and infrastructure constraints, particularly in the northeast. Although Tripura is fully electrified, 382 km remain unfinished in Assam. Other remaining segments include 93 km in Rajasthan, 151 km in Karnataka, 169 km in Tamil Nadu, and 16 km in Goa.

Electrification progress slowed in FY25, with only 2,701 km completed—well below the 6,000 km-plus annual average since FY21. Officials attribute the delay to complexities in the final routes involving tunnels, bridges, and curved tracks that require precision engineering.

Of 30 Indian states and union territories for which data is available, 25 are now fully electrified. Four others are above 90 per cent, and one exceeds 85 per cent completion. The government has allocated Rs 61.59 billion for electrification in FY26, including unspent funds from the previous year.

Electrification is a critical part of Indian Railways' decarbonisation strategy, aiming to cut its Rs 150 billion fuel bill and achieve net-zero emissions by 2030. Since independence, nearly 22,000 km has been electrified, with most of that achieved after FY18. At its peak, Indian Railways was electrifying over 16 km per day—one of the fastest rates globally, outpacing the EU (56 per cent), UK (38 per cent), and the US (1 per cent), with only Switzerland ahead at 99 per cent.

Indian Railways' ambitious broad-gauge electrification drive has hit delays, pushing the revised completion target to the end of FY26. Initially aimed for September 2024, the project now faces bottlenecks in last-mile connections—especially in Assam, Karnataka, Tamil Nadu, and parts of Rajasthan and Goa. As of March 2025, 68,701 km, or 98.83 per cent of the 69,512 km network, has been electrified, according to the Ministry of Railways.Progress has been hampered by geographic and infrastructure constraints, particularly in the northeast. Although Tripura is fully electrified, 382 km remain unfinished in Assam. Other remaining segments include 93 km in Rajasthan, 151 km in Karnataka, 169 km in Tamil Nadu, and 16 km in Goa.Electrification progress slowed in FY25, with only 2,701 km completed—well below the 6,000 km-plus annual average since FY21. Officials attribute the delay to complexities in the final routes involving tunnels, bridges, and curved tracks that require precision engineering.Of 30 Indian states and union territories for which data is available, 25 are now fully electrified. Four others are above 90 per cent, and one exceeds 85 per cent completion. The government has allocated Rs 61.59 billion for electrification in FY26, including unspent funds from the previous year.Electrification is a critical part of Indian Railways' decarbonisation strategy, aiming to cut its Rs 150 billion fuel bill and achieve net-zero emissions by 2030. Since independence, nearly 22,000 km has been electrified, with most of that achieved after FY18. At its peak, Indian Railways was electrifying over 16 km per day—one of the fastest rates globally, outpacing the EU (56 per cent), UK (38 per cent), and the US (1 per cent), with only Switzerland ahead at 99 per cent.

Next Story
Infrastructure Urban

TCC Concept Reports 480% Revenue Growth in Q1FY27

TCC Concept  has reported strong financial performance for the first quarter of FY27, with revenue from operations rising 480% year-on-year to Rs 1,283 million.The company’s EBITDA increased 158% year-on-year to Rs 463 million, with an EBITDA margin of 36.1%. Profit after tax (PAT) grew 34% year-on-year to Rs 126 million during the quarter.The growth was supported by continued execution across TCC’s integrated ecosystem spanning consumer commerce, supply chain, digital infrastructure, cloud, PropTech and AI-led platforms.Pepperfry continued to strengthen its omnichannel expansion stra..

Next Story
Real Estate

ANHAD Developers Appoints Akash Lakhina as Sales Head

ANHAD Developers has appointed Akash Lakhina as Head of Sales, Marketing and CRM as the company strengthens its leadership team ahead of its entry into Gurugram’s premium residential market.The appointment follows Adil Altaf taking charge as CEO of the group’s real estate vertical. Lakhina will be responsible for driving the company’s sales, marketing and customer relationship initiatives for its upcoming luxury developments.With nearly three decades of professional experience, Lakhina brings expertise across multiple industries, including over a decade in luxury real estate. His experie..

Next Story
Real Estate

BXB Estates Records AED 110 Million Luxury Villa Sale in Dubai

BXB Estates has completed a record AED 110 million residential transaction at Jumeirah Golf Estates, marking the highest-value residential sale in the history of one of Dubai’s most prestigious communities.The transaction, negotiated by Alfie Tabrez, Managing Partner, BXB Estates, surpasses the previous record of AED 58 million for a completed ready villa.The six-bedroom luxury residence features a built-up area of 21,714 sq ft on a 15,873 sq ft plot. The property includes nine bathrooms, four living lounges, a home office, bar lounge, private cinema and rooftop terrace. Its wellness facilit..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement