Rail Electrification Now Set for FY26 End
RAILWAYS & METRO RAIL

Rail Electrification Now Set for FY26 End

Indian Railways' ambitious broad-gauge electrification drive has hit delays, pushing the revised completion target to the end of FY26. Initially aimed for September 2024, the project now faces bottlenecks in last-mile connections—especially in Assam, Karnataka, Tamil Nadu, and parts of Rajasthan and Goa. As of March 2025, 68,701 km, or 98.83 per cent of the 69,512 km network, has been electrified, according to the Ministry of Railways.

Progress has been hampered by geographic and infrastructure constraints, particularly in the northeast. Although Tripura is fully electrified, 382 km remain unfinished in Assam. Other remaining segments include 93 km in Rajasthan, 151 km in Karnataka, 169 km in Tamil Nadu, and 16 km in Goa.

Electrification progress slowed in FY25, with only 2,701 km completed—well below the 6,000 km-plus annual average since FY21. Officials attribute the delay to complexities in the final routes involving tunnels, bridges, and curved tracks that require precision engineering.

Of 30 Indian states and union territories for which data is available, 25 are now fully electrified. Four others are above 90 per cent, and one exceeds 85 per cent completion. The government has allocated Rs 61.59 billion for electrification in FY26, including unspent funds from the previous year.

Electrification is a critical part of Indian Railways' decarbonisation strategy, aiming to cut its Rs 150 billion fuel bill and achieve net-zero emissions by 2030. Since independence, nearly 22,000 km has been electrified, with most of that achieved after FY18. At its peak, Indian Railways was electrifying over 16 km per day—one of the fastest rates globally, outpacing the EU (56 per cent), UK (38 per cent), and the US (1 per cent), with only Switzerland ahead at 99 per cent.

Indian Railways' ambitious broad-gauge electrification drive has hit delays, pushing the revised completion target to the end of FY26. Initially aimed for September 2024, the project now faces bottlenecks in last-mile connections—especially in Assam, Karnataka, Tamil Nadu, and parts of Rajasthan and Goa. As of March 2025, 68,701 km, or 98.83 per cent of the 69,512 km network, has been electrified, according to the Ministry of Railways.Progress has been hampered by geographic and infrastructure constraints, particularly in the northeast. Although Tripura is fully electrified, 382 km remain unfinished in Assam. Other remaining segments include 93 km in Rajasthan, 151 km in Karnataka, 169 km in Tamil Nadu, and 16 km in Goa.Electrification progress slowed in FY25, with only 2,701 km completed—well below the 6,000 km-plus annual average since FY21. Officials attribute the delay to complexities in the final routes involving tunnels, bridges, and curved tracks that require precision engineering.Of 30 Indian states and union territories for which data is available, 25 are now fully electrified. Four others are above 90 per cent, and one exceeds 85 per cent completion. The government has allocated Rs 61.59 billion for electrification in FY26, including unspent funds from the previous year.Electrification is a critical part of Indian Railways' decarbonisation strategy, aiming to cut its Rs 150 billion fuel bill and achieve net-zero emissions by 2030. Since independence, nearly 22,000 km has been electrified, with most of that achieved after FY18. At its peak, Indian Railways was electrifying over 16 km per day—one of the fastest rates globally, outpacing the EU (56 per cent), UK (38 per cent), and the US (1 per cent), with only Switzerland ahead at 99 per cent.

Next Story
Infrastructure Transport

Paras Railtech Wins Rs 1.22 Billion Mumbai Metro Contract

Paras Railtech Private Limited has received the Letter of Acceptance (LoA) for the second ballastless track contract, Package CA-273, of Mumbai Metro Line 2B (Yellow Line). The 23.6-km corridor runs between Andheri West and Mandale.The Mumbai Metropolitan Region Development Authority (MMRDA) had floated the tender in March 2025 with an estimated value of Rs 1.22 billion. Technical bids were opened on 22 April, with three firms submitting offers. Following technical evaluation on 14 May, two bids were rejected during the financial assessment. Paras Railtech was declared the lowest bidder and on..

Next Story
Infrastructure Urban

Agartala Smart City Projects Worth Rs 8.44 Billion Progressing

Agartala Smart City Limited is currently executing projects worth over Rs 8.44 billion and has set a target to complete storm water drain and road works before Durga Puja this year.According to Chief Executive Officer Dr Shailesh, the organisation has taken up 65 projects, all of which have been completed. Among the major works, the city addressed long-standing problems of waterlogging and flooding. To resolve this, 24 projects worth Rs 646 million were implemented, which included the installation of six new flood pumps. Storm water drains were also redesigned to ensure easier cleaning.For mai..

Next Story
Infrastructure Urban

BNT Marine Gets Nod For First Marine EOU Under MEPZ

The 8th Unit Approval Committee of the Madras Export Processing Zone (MEPZ) SEZ has approved BNT Marine Crafts (India) to convert its Domestic Tariff Area unit in Abishegakuppam, Puducherry, into a 100 per cent export oriented unit (EOU).This marks the first marine sector EOU under MEPZ’s jurisdiction. The company will manufacture semi-submarines, tourist vessels, commercial vessels and premium vessels for international markets. With an investment of Rs 22.5 million, the unit aims to generate net foreign exchange earnings of Rs 320 million over the next five years. It is also expected to cre..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Talk to us?