Rail Electrification Now Set for FY26 End
RAILWAYS & METRO RAIL

Rail Electrification Now Set for FY26 End

Indian Railways' ambitious broad-gauge electrification drive has hit delays, pushing the revised completion target to the end of FY26. Initially aimed for September 2024, the project now faces bottlenecks in last-mile connections—especially in Assam, Karnataka, Tamil Nadu, and parts of Rajasthan and Goa. As of March 2025, 68,701 km, or 98.83 per cent of the 69,512 km network, has been electrified, according to the Ministry of Railways.

Progress has been hampered by geographic and infrastructure constraints, particularly in the northeast. Although Tripura is fully electrified, 382 km remain unfinished in Assam. Other remaining segments include 93 km in Rajasthan, 151 km in Karnataka, 169 km in Tamil Nadu, and 16 km in Goa.

Electrification progress slowed in FY25, with only 2,701 km completed—well below the 6,000 km-plus annual average since FY21. Officials attribute the delay to complexities in the final routes involving tunnels, bridges, and curved tracks that require precision engineering.

Of 30 Indian states and union territories for which data is available, 25 are now fully electrified. Four others are above 90 per cent, and one exceeds 85 per cent completion. The government has allocated Rs 61.59 billion for electrification in FY26, including unspent funds from the previous year.

Electrification is a critical part of Indian Railways' decarbonisation strategy, aiming to cut its Rs 150 billion fuel bill and achieve net-zero emissions by 2030. Since independence, nearly 22,000 km has been electrified, with most of that achieved after FY18. At its peak, Indian Railways was electrifying over 16 km per day—one of the fastest rates globally, outpacing the EU (56 per cent), UK (38 per cent), and the US (1 per cent), with only Switzerland ahead at 99 per cent.

Indian Railways' ambitious broad-gauge electrification drive has hit delays, pushing the revised completion target to the end of FY26. Initially aimed for September 2024, the project now faces bottlenecks in last-mile connections—especially in Assam, Karnataka, Tamil Nadu, and parts of Rajasthan and Goa. As of March 2025, 68,701 km, or 98.83 per cent of the 69,512 km network, has been electrified, according to the Ministry of Railways.Progress has been hampered by geographic and infrastructure constraints, particularly in the northeast. Although Tripura is fully electrified, 382 km remain unfinished in Assam. Other remaining segments include 93 km in Rajasthan, 151 km in Karnataka, 169 km in Tamil Nadu, and 16 km in Goa.Electrification progress slowed in FY25, with only 2,701 km completed—well below the 6,000 km-plus annual average since FY21. Officials attribute the delay to complexities in the final routes involving tunnels, bridges, and curved tracks that require precision engineering.Of 30 Indian states and union territories for which data is available, 25 are now fully electrified. Four others are above 90 per cent, and one exceeds 85 per cent completion. The government has allocated Rs 61.59 billion for electrification in FY26, including unspent funds from the previous year.Electrification is a critical part of Indian Railways' decarbonisation strategy, aiming to cut its Rs 150 billion fuel bill and achieve net-zero emissions by 2030. Since independence, nearly 22,000 km has been electrified, with most of that achieved after FY18. At its peak, Indian Railways was electrifying over 16 km per day—one of the fastest rates globally, outpacing the EU (56 per cent), UK (38 per cent), and the US (1 per cent), with only Switzerland ahead at 99 per cent.

Next Story
Infrastructure Transport

Shivraj Chouhan Launches PMGSY IV and Announces Package for Madhya Pradesh

Union Minister Shivraj Singh Chouhan launched the Pradhan Mantri Gram Sadak Yojana (PMGSY) IV at Bhairunda in Sehore district during the 25 year celebrations and announced a development package for Madhya Pradesh. The programme was organised by the Union Ministry of Rural Development and attended by Chief Minister Dr Mohan Yadav, ministers of state, state ministers, legislators and senior officials from the centre and the state. The minister said the central government under the Prime Minister is committed to strengthening rural livelihoods through improved connectivity, housing and women's in..

Next Story
Infrastructure Urban

DMR Engineering Reports FY 25-26 Financial Results

DMR Engineering reported its half year results for the financial year ended 31 March 2026 and published full year figures on a standalone basis. Standalone revenue from operations decreased by 2.01 per cent year-over-year to Rs 102.58 million (mn), while profit after tax declined by 43.94 per cent to nine point five six mn, leaving a profit after tax margin of nine point zero five per cent. Earnings per share stood at Rs zero point nine two, a fall of 44.71 per cent year-over-year. The company attributed part of the decline to one-off provisioning for bad debts and additional financing charges..

Next Story
Infrastructure Urban

Atlanta Electricals Posts Strong FY26 Growth And Debt Free Finish

Atlanta Electricals reported audited consolidated results for the quarter and year ended 31 March 2026. The company recorded significant year-on-year revenue growth driven by capacity ramp-up at new facilities and higher utilisation at legacy plants. The announcement summarised operating improvements and strategic milestones achieved during the year. For Q4 the company reported revenue of Rs 7.48 bn and for FY26 revenue of Rs 18.52 bn, representing robust growth versus the prior year. EBITDA in Q4 was Rs. 1.49 bn and Rs. 3.44 bn for the full year, with margins expanding to 20 per cent in the q..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement