Rail Electrification Now Set for FY26 End
RAILWAYS & METRO RAIL

Rail Electrification Now Set for FY26 End

Indian Railways' ambitious broad-gauge electrification drive has hit delays, pushing the revised completion target to the end of FY26. Initially aimed for September 2024, the project now faces bottlenecks in last-mile connections—especially in Assam, Karnataka, Tamil Nadu, and parts of Rajasthan and Goa. As of March 2025, 68,701 km, or 98.83 per cent of the 69,512 km network, has been electrified, according to the Ministry of Railways.

Progress has been hampered by geographic and infrastructure constraints, particularly in the northeast. Although Tripura is fully electrified, 382 km remain unfinished in Assam. Other remaining segments include 93 km in Rajasthan, 151 km in Karnataka, 169 km in Tamil Nadu, and 16 km in Goa.

Electrification progress slowed in FY25, with only 2,701 km completed—well below the 6,000 km-plus annual average since FY21. Officials attribute the delay to complexities in the final routes involving tunnels, bridges, and curved tracks that require precision engineering.

Of 30 Indian states and union territories for which data is available, 25 are now fully electrified. Four others are above 90 per cent, and one exceeds 85 per cent completion. The government has allocated Rs 61.59 billion for electrification in FY26, including unspent funds from the previous year.

Electrification is a critical part of Indian Railways' decarbonisation strategy, aiming to cut its Rs 150 billion fuel bill and achieve net-zero emissions by 2030. Since independence, nearly 22,000 km has been electrified, with most of that achieved after FY18. At its peak, Indian Railways was electrifying over 16 km per day—one of the fastest rates globally, outpacing the EU (56 per cent), UK (38 per cent), and the US (1 per cent), with only Switzerland ahead at 99 per cent.

Indian Railways' ambitious broad-gauge electrification drive has hit delays, pushing the revised completion target to the end of FY26. Initially aimed for September 2024, the project now faces bottlenecks in last-mile connections—especially in Assam, Karnataka, Tamil Nadu, and parts of Rajasthan and Goa. As of March 2025, 68,701 km, or 98.83 per cent of the 69,512 km network, has been electrified, according to the Ministry of Railways.Progress has been hampered by geographic and infrastructure constraints, particularly in the northeast. Although Tripura is fully electrified, 382 km remain unfinished in Assam. Other remaining segments include 93 km in Rajasthan, 151 km in Karnataka, 169 km in Tamil Nadu, and 16 km in Goa.Electrification progress slowed in FY25, with only 2,701 km completed—well below the 6,000 km-plus annual average since FY21. Officials attribute the delay to complexities in the final routes involving tunnels, bridges, and curved tracks that require precision engineering.Of 30 Indian states and union territories for which data is available, 25 are now fully electrified. Four others are above 90 per cent, and one exceeds 85 per cent completion. The government has allocated Rs 61.59 billion for electrification in FY26, including unspent funds from the previous year.Electrification is a critical part of Indian Railways' decarbonisation strategy, aiming to cut its Rs 150 billion fuel bill and achieve net-zero emissions by 2030. Since independence, nearly 22,000 km has been electrified, with most of that achieved after FY18. At its peak, Indian Railways was electrifying over 16 km per day—one of the fastest rates globally, outpacing the EU (56 per cent), UK (38 per cent), and the US (1 per cent), with only Switzerland ahead at 99 per cent.

Related Stories

Gold Stories

Next Story
Infrastructure Urban

Assam Gets Approval For 350,000 PMAY Homes

Assam Chief Minister Himanta Biswa Sarma met Union Agriculture Minister Shivraj Singh Chouhan in New Delhi, where the minister handed an approval document for 310,000 new homes under the Pradhan Mantri Awas Yojana. The chief minister subsequently posted on X expressing gratitude and noting that the minister had formally handed approval for 380,000 homes as well. The release and the social media post contained varying figures, with broader references to 350,000 homes reported in some summaries. The approvals carry central assistance equivalent to Rs 50 billion (bn), corresponding to the five th..

Next Story
Infrastructure Urban

KPIGreen Achieves Highest Energised Capacity of 630+ MW DC

KPI Green Energy energised more than 630 MW DC of capacity in the June to August quarter, marking the highest quarterly addition in the company's history. The capacity was brought online across its Independent Power Producer (IPP) and Engineering, Procurement and Construction (EPC) businesses. The company said the achievement reflected the scale, speed and consistency of its project execution engine. The firm described the quarter as a material operational milestone since its founding. The milestone covers a diversified mix of IPP assets and projects executed under the EPC vertical, spanning u..

Next Story
Infrastructure Energy

Adani Energy Solutions Wins Rs 47 bn Maharashtra Transmission Project

Adani Energy Solutions has won a transmission contract in Maharashtra valued at Rs 47 billion (Rs 47 bn) to evacuate 4,500 megawatt (MW) of renewable and storage power. The company informed exchanges that the project will facilitate pumped storage potential near Satara and strengthen the inter-regional corridor between the Western and Southern grids. The award follows a competitive bidding process and will support renewable energy evacuation to major load centres in the state. The scope includes establishment of a 765/400 kV substation at Satara, construction of a Kolhapur-Satara 765 kV double..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

SPECIAL OFFER
QR Code