Rail Electrification Now Set for FY26 End
RAILWAYS & METRO RAIL

Rail Electrification Now Set for FY26 End

Indian Railways' ambitious broad-gauge electrification drive has hit delays, pushing the revised completion target to the end of FY26. Initially aimed for September 2024, the project now faces bottlenecks in last-mile connections—especially in Assam, Karnataka, Tamil Nadu, and parts of Rajasthan and Goa. As of March 2025, 68,701 km, or 98.83 per cent of the 69,512 km network, has been electrified, according to the Ministry of Railways.

Progress has been hampered by geographic and infrastructure constraints, particularly in the northeast. Although Tripura is fully electrified, 382 km remain unfinished in Assam. Other remaining segments include 93 km in Rajasthan, 151 km in Karnataka, 169 km in Tamil Nadu, and 16 km in Goa.

Electrification progress slowed in FY25, with only 2,701 km completed—well below the 6,000 km-plus annual average since FY21. Officials attribute the delay to complexities in the final routes involving tunnels, bridges, and curved tracks that require precision engineering.

Of 30 Indian states and union territories for which data is available, 25 are now fully electrified. Four others are above 90 per cent, and one exceeds 85 per cent completion. The government has allocated Rs 61.59 billion for electrification in FY26, including unspent funds from the previous year.

Electrification is a critical part of Indian Railways' decarbonisation strategy, aiming to cut its Rs 150 billion fuel bill and achieve net-zero emissions by 2030. Since independence, nearly 22,000 km has been electrified, with most of that achieved after FY18. At its peak, Indian Railways was electrifying over 16 km per day—one of the fastest rates globally, outpacing the EU (56 per cent), UK (38 per cent), and the US (1 per cent), with only Switzerland ahead at 99 per cent.

Your next big infra connection is waiting at RAHSTA 2025 – Asia’s Biggest Roads & Highways Expo, Jio World Convention Centre, Mumbai. Don’t miss out!

Indian Railways' ambitious broad-gauge electrification drive has hit delays, pushing the revised completion target to the end of FY26. Initially aimed for September 2024, the project now faces bottlenecks in last-mile connections—especially in Assam, Karnataka, Tamil Nadu, and parts of Rajasthan and Goa. As of March 2025, 68,701 km, or 98.83 per cent of the 69,512 km network, has been electrified, according to the Ministry of Railways.Progress has been hampered by geographic and infrastructure constraints, particularly in the northeast. Although Tripura is fully electrified, 382 km remain unfinished in Assam. Other remaining segments include 93 km in Rajasthan, 151 km in Karnataka, 169 km in Tamil Nadu, and 16 km in Goa.Electrification progress slowed in FY25, with only 2,701 km completed—well below the 6,000 km-plus annual average since FY21. Officials attribute the delay to complexities in the final routes involving tunnels, bridges, and curved tracks that require precision engineering.Of 30 Indian states and union territories for which data is available, 25 are now fully electrified. Four others are above 90 per cent, and one exceeds 85 per cent completion. The government has allocated Rs 61.59 billion for electrification in FY26, including unspent funds from the previous year.Electrification is a critical part of Indian Railways' decarbonisation strategy, aiming to cut its Rs 150 billion fuel bill and achieve net-zero emissions by 2030. Since independence, nearly 22,000 km has been electrified, with most of that achieved after FY18. At its peak, Indian Railways was electrifying over 16 km per day—one of the fastest rates globally, outpacing the EU (56 per cent), UK (38 per cent), and the US (1 per cent), with only Switzerland ahead at 99 per cent.

Next Story
Infrastructure Energy

BGR Tech–Collabrah Wins Rs 530.5 Mn Project from Oil India

BGR Tech, in partnership with Collabrah India, has secured a Rs 530.5 million contract from Oil India (OIL) for the deployment of six Surface Production Facilities (SPFs) across OIL’s operational zones in Assam. The three-year project includes a Framework Agreement, allowing for the provision of additional units if required. The collaboration leverages BGR Tech’s engineering expertise and Collabrah’s execution capabilities to support OIL India’s production expansion plans in line with the Ministry of Petroleum & Natural Gas’s vision for domestic energy growth. Following this win, BG..

Next Story
Infrastructure Energy

Rosatom Showcases Nuclear Energy Solutions at POWERGEN India 2025

Representatives of Rosatom participated in the international forum POWERGEN India & Indian Utility Week 2025, held in New Delhi from September 2–4. As part of the event, a panel discussion titled “Reinventing Atomic Energy for a Net Zero Future” featured industry leaders from Rosatom, the Council on Energy, Environment and Water (CEEW), NTPC Ltd, and other energy experts.Ekaterina Astashina, Rosatom’s Business Development Manager for South Asia, highlighted the importance of nuclear energy in achieving decarbonisation goals and shared Rosatom’s experience in India.“Through the ..

Next Story
Building Material

Assam Govt Defends Land Allotment to Cement Firm in Dima Hasao

The Assam government has informed the Gauhati High Court that the allotment of 3,000 bighas of land in Dima Hasao district to Mahabal Cement for setting up a cement factory was carried out in accordance with the “due process of law.”Appearing before the court, Advocate General Devajit Saikia submitted a report prepared by a three-member committee, which examined the land allotment, its suitability and potential implications.Saikia clarified that the cement company, part of the Trivikram Consortium, had sought 6,000 bighas, of which 3,000 bighas were allotted by the autonomous council in tw..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Talk to us?