Rail Electrification Now Set for FY26 End
RAILWAYS & METRO RAIL

Rail Electrification Now Set for FY26 End

Indian Railways' ambitious broad-gauge electrification drive has hit delays, pushing the revised completion target to the end of FY26. Initially aimed for September 2024, the project now faces bottlenecks in last-mile connections—especially in Assam, Karnataka, Tamil Nadu, and parts of Rajasthan and Goa. As of March 2025, 68,701 km, or 98.83 per cent of the 69,512 km network, has been electrified, according to the Ministry of Railways.

Progress has been hampered by geographic and infrastructure constraints, particularly in the northeast. Although Tripura is fully electrified, 382 km remain unfinished in Assam. Other remaining segments include 93 km in Rajasthan, 151 km in Karnataka, 169 km in Tamil Nadu, and 16 km in Goa.

Electrification progress slowed in FY25, with only 2,701 km completed—well below the 6,000 km-plus annual average since FY21. Officials attribute the delay to complexities in the final routes involving tunnels, bridges, and curved tracks that require precision engineering.

Of 30 Indian states and union territories for which data is available, 25 are now fully electrified. Four others are above 90 per cent, and one exceeds 85 per cent completion. The government has allocated Rs 61.59 billion for electrification in FY26, including unspent funds from the previous year.

Electrification is a critical part of Indian Railways' decarbonisation strategy, aiming to cut its Rs 150 billion fuel bill and achieve net-zero emissions by 2030. Since independence, nearly 22,000 km has been electrified, with most of that achieved after FY18. At its peak, Indian Railways was electrifying over 16 km per day—one of the fastest rates globally, outpacing the EU (56 per cent), UK (38 per cent), and the US (1 per cent), with only Switzerland ahead at 99 per cent.

Indian Railways' ambitious broad-gauge electrification drive has hit delays, pushing the revised completion target to the end of FY26. Initially aimed for September 2024, the project now faces bottlenecks in last-mile connections—especially in Assam, Karnataka, Tamil Nadu, and parts of Rajasthan and Goa. As of March 2025, 68,701 km, or 98.83 per cent of the 69,512 km network, has been electrified, according to the Ministry of Railways.Progress has been hampered by geographic and infrastructure constraints, particularly in the northeast. Although Tripura is fully electrified, 382 km remain unfinished in Assam. Other remaining segments include 93 km in Rajasthan, 151 km in Karnataka, 169 km in Tamil Nadu, and 16 km in Goa.Electrification progress slowed in FY25, with only 2,701 km completed—well below the 6,000 km-plus annual average since FY21. Officials attribute the delay to complexities in the final routes involving tunnels, bridges, and curved tracks that require precision engineering.Of 30 Indian states and union territories for which data is available, 25 are now fully electrified. Four others are above 90 per cent, and one exceeds 85 per cent completion. The government has allocated Rs 61.59 billion for electrification in FY26, including unspent funds from the previous year.Electrification is a critical part of Indian Railways' decarbonisation strategy, aiming to cut its Rs 150 billion fuel bill and achieve net-zero emissions by 2030. Since independence, nearly 22,000 km has been electrified, with most of that achieved after FY18. At its peak, Indian Railways was electrifying over 16 km per day—one of the fastest rates globally, outpacing the EU (56 per cent), UK (38 per cent), and the US (1 per cent), with only Switzerland ahead at 99 per cent.

Next Story
Equipment

Liebherr Cranes Rapidly Progress on Scandinavia’s Second Tallest Tower

An impressive structure has emerged at remarkable speed in Karlskrona. Standing at a height of 200 metres, the NKT Tower 3 is the second tallest tower in Scandinavia. Two Liebherr cranes, a 542 HC-L 12/24 Litronic and a 258 HC-L 10/18 Fibre, are a key part of this ambitious construction project. The tower which is built by Skanska will be an integral part of the world’s largest high-voltage submarine cable factory, which will supply wind turbines and solar parks with essential components. Weighing 28,000 tonnes in total, the NKT Tower 3 is a feat of engineering.Liebherr Tower Crane Center an..

Next Story
Resources

GCCIA Concludes AI Forum in Kuwait with Discussions on Enhancing Power

The Gulf Cooperation Council Interconnection Authority (GCCIA), concluded its two-day regional forum held on April 29–30, 2025, under the theme, “Empowering the Future Grid: Exploring the Application of Generative AI in GCC Power Systems,” which took place in Kuwait City. The event brought together a distinguished group of global technology leaders, including GCCIA, the Saudi Electricity Company, ENOWA (NEOM’s Energy and Water Company), GCC energy authorities and utilities, as well as Microsoft, NVIDIA, Oracle, and EPRI Gulf (Electric Power Research Institute), alongside representative..

Next Story
Resources

Hindustan Zinc Accelerates Research in Emerging Zinc Battery Tech

Hindustan Zinc Limited, India’s only and the world’s largest integrated zinc producer, sees early breakthrough in the research of next-generation zinc-based battery technologies. The research targets delivering higher energy efficiency, improved safety and longer operational life. The company is pioneering emerging zinc battery technology to support the ongoing clean energy transition.Zinc has emerged as a powerful alternative to lithium owing to its abundance, stability and cost effectiveness. While the lithium market continues to face supply constraints and rising costs, zinc-based syste..

Advertisement

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Advertisement

Talk to us?