Rail Electrification Now Set for FY26 End
RAILWAYS & METRO RAIL

Rail Electrification Now Set for FY26 End

Indian Railways' ambitious broad-gauge electrification drive has hit delays, pushing the revised completion target to the end of FY26. Initially aimed for September 2024, the project now faces bottlenecks in last-mile connections—especially in Assam, Karnataka, Tamil Nadu, and parts of Rajasthan and Goa. As of March 2025, 68,701 km, or 98.83 per cent of the 69,512 km network, has been electrified, according to the Ministry of Railways.

Progress has been hampered by geographic and infrastructure constraints, particularly in the northeast. Although Tripura is fully electrified, 382 km remain unfinished in Assam. Other remaining segments include 93 km in Rajasthan, 151 km in Karnataka, 169 km in Tamil Nadu, and 16 km in Goa.

Electrification progress slowed in FY25, with only 2,701 km completed—well below the 6,000 km-plus annual average since FY21. Officials attribute the delay to complexities in the final routes involving tunnels, bridges, and curved tracks that require precision engineering.

Of 30 Indian states and union territories for which data is available, 25 are now fully electrified. Four others are above 90 per cent, and one exceeds 85 per cent completion. The government has allocated Rs 61.59 billion for electrification in FY26, including unspent funds from the previous year.

Electrification is a critical part of Indian Railways' decarbonisation strategy, aiming to cut its Rs 150 billion fuel bill and achieve net-zero emissions by 2030. Since independence, nearly 22,000 km has been electrified, with most of that achieved after FY18. At its peak, Indian Railways was electrifying over 16 km per day—one of the fastest rates globally, outpacing the EU (56 per cent), UK (38 per cent), and the US (1 per cent), with only Switzerland ahead at 99 per cent.

Indian Railways' ambitious broad-gauge electrification drive has hit delays, pushing the revised completion target to the end of FY26. Initially aimed for September 2024, the project now faces bottlenecks in last-mile connections—especially in Assam, Karnataka, Tamil Nadu, and parts of Rajasthan and Goa. As of March 2025, 68,701 km, or 98.83 per cent of the 69,512 km network, has been electrified, according to the Ministry of Railways.Progress has been hampered by geographic and infrastructure constraints, particularly in the northeast. Although Tripura is fully electrified, 382 km remain unfinished in Assam. Other remaining segments include 93 km in Rajasthan, 151 km in Karnataka, 169 km in Tamil Nadu, and 16 km in Goa.Electrification progress slowed in FY25, with only 2,701 km completed—well below the 6,000 km-plus annual average since FY21. Officials attribute the delay to complexities in the final routes involving tunnels, bridges, and curved tracks that require precision engineering.Of 30 Indian states and union territories for which data is available, 25 are now fully electrified. Four others are above 90 per cent, and one exceeds 85 per cent completion. The government has allocated Rs 61.59 billion for electrification in FY26, including unspent funds from the previous year.Electrification is a critical part of Indian Railways' decarbonisation strategy, aiming to cut its Rs 150 billion fuel bill and achieve net-zero emissions by 2030. Since independence, nearly 22,000 km has been electrified, with most of that achieved after FY18. At its peak, Indian Railways was electrifying over 16 km per day—one of the fastest rates globally, outpacing the EU (56 per cent), UK (38 per cent), and the US (1 per cent), with only Switzerland ahead at 99 per cent.

Next Story
Real Estate

IGBC Launches Green Building Congress 2025 in Mumbai

The Confederation of Indian Industry’s Indian Green Building Council (IGBC) has announced the 23rd edition of its annual flagship event—Green Building Congress 2025—to be held from 27–29 November 2025 at Jio World Convention Centre, Mumbai. With the theme “Green Shifts for Greener Tomorrows: Do Good, Feel Good – Embrace Green Choices for a Sustainable Future,” the event aims to accelerate India’s Green and Net Zero Building Movement through knowledge exchange and business collaboration. This year’s Congress marks 25 years of IGBC’s pioneering work in advancing India’..

Next Story
Resources

Hettich Reimagines Delhi Experience Centre

Hettich, a global leader in furniture fittings, has unveiled its newly reimagined Delhi Experience Centre, marking a new chapter in its 15-year journey of inspiring interior design experiences in India. Originally launched in 2010 as the country’s first Hettich Experience Centre, the upgraded facility showcases the brand’s complete portfolio of interior solutions — from German furniture fittings and architectural hardware to furniture lighting and built-in kitchen appliances. Designed to offer an immersive and standardised customer journey, the new Centre aims to inspire creati..

Next Story
Resources

Concord Control Systems Acquires Fusion Electronics

Concord Control Systems, a leading manufacturer of embedded and critical electronic systems, has acquired Fusion Electronics Private Limited, signalling its entry into India’s high-value flex printed circuit board (PCB) manufacturing segment. Fusion Electronics, India’s largest flex PCB manufacturer, has an installed capacity of 200,000 sq m annually and a revenue potential of about Rs 200 crore at full capacity. Established in 1994, it operates with EBITDA margins exceeding 20 per cent and serves global clients in luxury automotive, industrial, and electronics sectors. “This a..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Talk to us?